Delegated Report - Code - Planning OPW24 0017 · OPW24/0017
15. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
16. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice;
b. The relevant conditions of the higher order Building Works approval viz. DBW21/0208
to which this approval relates;
c. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines; and
d. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Works within Road Reserve/Reinstatement
17. Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out construction
works, Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
18. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
19. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Site Access and Driveways
20. Driveway crossovers must be constructed in accordance with council’s Standard Drawings
RS-049, RS-050 and any associated addendum.
21. Any existing unnecessary or redundant property accesses must be removed, and the kerb,
footpath and verge area reinstated to match the existing footpath and/or verge treatments.
Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
or turf, and must be maintained by the developer until established.
22. The following must be complied with during the construction of the required
crossover/driveway:
a. The driveway surfacing must consist of either an approved hot mixed asphaltic
concrete or patterned/plain concrete;
b. The driveway must be constructed so as not to concentrate stormwater runoff onto
neighbouring properties;
c. Underground service conduits for water supply, electricity and any other services must
be provided as part of the access driveway;
d. Where there is an existing pedestrian path, a matching crossfall must be provided for
the driveway on the alignment of the path, for the full width of the path; and
e. The property access must be located a minimum of 1m clear of existing power poles,
streetlights or other signage. The developer is responsible for any necessary relocation
of existing services to provide this clearance and must contact the relevant service
authorities and comply with their requirements in relation to these works.
Page 7 of 11
Document Set ID: 22937465
Version: 3, Version Date: 17/04/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original