Dear Tiani,
Decision Notice – Minor Change
Planning Act 2016
I refer to your application received on 26 March 2026, requesting a minor change to an existing
development approval. Council on 4 June 2026 decided your requested changes.
Details of the decision are as follows:
1. APPLICATION DETAILS
Application No: MCU13/0030.04
Street address: Kabara 20 Topaz St, Cooroy Qld 4563
Real property description: Lot 102 SP 236318
Planning Scheme: Noosa Plan 2020 (Amendment 3 - 20 March 2026)
2. DECISION DETAILS
The following type of approval was issued on 24 June 2013.
• Development Permit for Other Change – Residential Care Facility
In relation to the request to make a minor change to the existing approval, Council on 4 June 2026,
decided to approve the requested changes. The changes are detailed below.
A. Approve the change in part only.
B. Refuse to amend condition 2 for the following reasons:
1. The proposed change is more appropriately addressed as an additional condition of
approval relevant to the changed area of the building.
C. Include additional condition 38.
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
ABN 97.969.214.121 PO Box 141
noosa.qld.gov.au Tewantin QLD 4565
[email protected] 07 5329 6500
Page 1 of 10
Document Set ID: 24843492
Version: 4, Version Date: 10/06/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 9 pages
Page 2
4. ASSESSMENT MANAGER CONDITIONS
PLANNING
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
the use commencing, and then compliance maintained at all times while the use continues.
Approved Plans
2. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
DA0.01 - Cover Sheet, drawn by Middap Architecture 15/11/2021
DA1.01 - Site Plan, drawn by Middap Architecture 15/11/2021
DA2.01 - Proposed Upper Ground Plan, drawn by 15/11/2021
Middap Architecture
DA2.02 - Proposed Lower Ground Plan, drawn by 15/11/2021
Middap Architecture
DA2.03 - Proposed Upper Ground GFA Plan, drawn 15/11/2021
by Middap Architecture
DA2.04 - Proposed Lower Ground GFA Plan, drawn 15/11/2021
by Middap Architecture
DA2.05 - Proposed Roof Plan, drawn by Middap 15/11/2021
Architecture
DA3.01 - Elevations, drawn by Middap Architecture 15/11/2021
DA3.02 - Elevations, drawn by Middap Architecture 15/11/2021
DA4.01 - Site Sections, drawn by Middap 15/11/2021
Architecture
DA4.02 - 3D Perspective Views, drawn by Middap 15/11/2021
Architecture
Amended Plans
3. The plans must be revised to incorporate the amendments listed within this Decision Notice
and resubmitted to Council for endorsement prior to the issue of any Development Permit for
Building Works.
Page 2 of 10
Document Set ID: 24843492
Version: 4, Version Date: 10/06/2026
Page 3
4. The Proposal Plans must be revised such that the development demonstrates compliance
with Performance Outcome PO7 of the Cooroy Local Plan Code. This includes the provision
of:
a. Traditional Queensland style roof design.
b. Broken roof from (in lieu of single wide span roof) to provide articulation and visual
interest where the building has frontage to Topaz Street.
c. Addition of lightweight building materials and a mix of building materials where the
building has frontage to Topaz Street.
d. Design elements which reflective the traditional country town character of Cooroy.
Nature and Extent of Approved Use
5. The development must not exceed the provision of 96 single ensuite rooms.
6. The proposed Kauri building must not exceed a gross floor area of 1,765m2 (upper-level) and
1,970m2 (lower-level).
Building Appearance
7. All air conditioning units or other mechanical equipment must be located at ground level, or
otherwise fully enclosed or screened such that they are not visible from the street frontages
nor adjoining properties.
Currency Period
8. This development approval lapses if the use has not happened by 22 February 2028, unless
an application to extend the currency period is approved by Council.
Building Height
9. The maximum height of the development must not exceed 8.0 metres, except for the eave
overhang of the central Kauri building (as shown on Section A) which may be 8.5 metres
above the finished ground level and the natural ground level.
10. Certification must be submitted to Council from a Licensed Surveyor which certifies that the
building does not exceed the maximum height requirement of this Decision Notice.
Performance Bond
11. Security in the form of a cash bond or trading bank guarantee to the sum of $30,000 must
be submitted to Council, to secure performance of all conditions of this approval, prior to the
issue of a Development Permit for Building Works. The cash bond or trading bank guarantee
will be returned on performance of the conditions of approval less any costs incurred by
Council in respect of enforcing performance of this permit. Council reserves the right to call
upon the bond or guaranteed sum to effect compliance with conditions.
Street Identification
12. The street address of the development must be clearly visible and discernible from the
primary frontage of the site by the provision of a street number and, where appropriate, the
building name.
Water & Sewer Connections
13. An underground connection to reticulated water and sewerage must be provided to the
development site in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
14. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
must be submitted to Council that certifies an underground connection to reticulated water
and sewerage has been provided to the development site.
Page 3 of 10
Document Set ID: 24843492
Version: 4, Version Date: 10/06/2026
Page 4
ENGINEERING
Car Parking
15. A minimum of 24 car parking spaces must be provided and marked on the site and made
available and accessible at all times while the use is open for business. The works must be
undertaken in accordance with an Operational Works approval and must include in particular:
a. staff parking spaces within the total, which are clearly marked for that purpose
b. one (1) disabled parking space/s within the total
c. dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities
16. All car parking areas and access driveways must be maintained exclusively for vehicle
parking and manoeuvring and kept in a tidy and safe condition at all times.
17. Directional signage must be provided to direct visitors and customers to the car parking
spaces provided on site.
Water Management Plan
18. Stormwater is to be managed and treated in accordance with the requirements of the
Integrated Water Management Plan, Version 0, prepared by Callaghan and Toth, dated
January 2022.
LANDSCAPING
19. The development site must be landscaped. The works must be undertaken in accordance
with an Operational Works approval and the Noosa Plan for that specific area and must
include in particular:
a. The works shown on the Approved Plans
b. a 6.0 metre wide landscaping strip along the Topaz Street road frontage of the subject
site, exclusive of the access driveway, generally uncompromised by infrastructure
items
c. vegetated screening of any electrical transformers, bin storage areas and the like from
the road frontage
20. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.
21. All landscape works must be maintained generally in accordance with the approved design
for the life of the development.
DEMOLITION
Works
22. Demolition must be undertaken in a manner that causes no detrimental effect upon the
amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
in accordance with the nuisance provisions of the Environmental Protection Act 1994.
Page 4 of 10
Document Set ID: 24843492
Version: 4, Version Date: 10/06/2026
Page 5
Waste management
23. A Waste Management Plan (demolition) must be submitted in accordance with Planning
Scheme Policy PSP10 - Waste Management and approved by Council’s Waste Coordinator
prior to issue of a development permit for Building Works for demolition, removal or
relocation.
The purpose of the Waste Management Plan is to facilitate the segregation of waste for the
effective reuse and recycling of such materials. Segregated wastes attract significantly
reduced disposal fees at the landfill with some items free. Higher gate fees are charged for
mixed waste.
Waste storage areas must provide for adequate separation of all reusable, recyclable and
waste materials. These must be located so that they are convenient and safe to use.
The Plan must contain the following information:
a. The areas for the storage and separation of waste shown on a site plan;
b. A waste management table as indicated below is to be completed showing how waste
material is to be segregated - recycled – reused or disposed; and
c. Table – Waste Management Table
MATERIALS ON-SITE DESTINATION
Re-use and Recycling Disposal
Expected waste Estimated On-site Off-site *specify contractor
materials volume(m³) *specify proposed *specify contractor and landfill site or
re-use or on-site and recycling outlet other disposal site
recycling methods
Excavation
material
Green waste
Bricks
Concrete
Timber-please
specify
Plasterboard
Metals - please
specify
Asbestos
Other - please
specify
Note * If a demolition contractor is undertaking works, then the Waste Management table is
to be completed by the demolition contractor.
Damage to infrastructure
24. Any damage to footpaths, street plantings, natural vegetation/trees kerb and channel,
bridges or roadways must be repaired or reinstated to at least pre-existing conditions.
Vacant site
25. The site must be left clean and tidy free from debris such as concrete, wire, rubble, brick/s
and the like. If the site remains vacant for more than 30 days the lot/s must be turfed or
landscaped in accordance with Planning Scheme Policy PSP 2 – Landscaping and to the
satisfaction of Council so as to not cause nuisance to the surrounding area.
26. All waste materials must be removed from site.
Page 5 of 10
Document Set ID: 24843492
Version: 4, Version Date: 10/06/2026
Page 6
Litter, erosion and sediment control
27. Litter, erosion and sediment control measures must be installed and maintained until soils
are stabilised by turf, vegetation or sealed.
Note: it is an offence under the Environmental Protection Act 1994 to deposit or potentially
allow litter, waste, soil, or other contaminants to enter a waterway or storm water drainage
system (e.g. roadside gutter).
Asbestos
28. Removal of building materials containing asbestos must be undertaken by a licensed
asbestos removalist.
29. Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
requires a licensed asbestos removalist to give notice to Workplace Health and Safety
Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
commences. Notification must be made using Form 65: Notification of licensed asbestos
removal work, demolition work or emergency demolition.
30. All building materials containing asbestos products are wrapped and disposed of in
accordance with the Public Health Regulation 2006 and the Environmental Protection
Regulation 2008.
Note: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
businesses that transport asbestos waste, and landfills that accept this waste.
31. All building materials containing asbestos, including asbestos cement sheeting or roofing and
lagging are removed from the building prior to demolition/relocation.
Plumbing and Drainage
32. It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
demolition of a building, the existing sanitary drain upstream from the connection point for a
service provider’s sewerage system must be sealed water tight. This work is deemed as
notifiable Work and must be carried out by a suitably licenced plumber who must submit an
As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
Construction Commission) within 10 days of completing the work.
ENVIRONMENTAL HEALTH
Waste Management
33. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy No. 9 “Waste Management Multi-Dwellings and Commercial and
Industrial Premises”. The facilities must include an external impervious area correctly sized
for all refuse and recycling containers and suitably screened from public places and
neighbouring properties. A bin wash area is required with a cold-water tap, hose and drain
outlet connected to sewer, via a bucket trap. The drain outlet must be designed to prevent
storm water entry to the sewerage system. This can be achieved with a nib wall 50mm high
and up to 700mm x 700mm wide (max 0.5m²), or alternatively the waste area can be roofed,
or any other design approved by Council.
34. Refuse containers must be provided in accordance with the requirements of the
Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
Regulation 2000, for the storage and collection of refuse.
35. Public bins must be provided to reduce littering. All bins provided must be for refuse and
recycling and be decanted into the bulk bins by the site operators.
Page 6 of 10
Document Set ID: 24843492
Version: 4, Version Date: 10/06/2026
Page 7
Mechanical Equipment
36. Written certification is required from a suitably qualified person confirming that sound
pressure levels from all mechanical plant and equipment comply with the following:
a. Air-conditioning and Refrigeration
• 7am to 10pm: Maximum background + 5dB(A)
• 10pm to 7am: Maximum background + 3dB(A)
b. Pumps
• 7am to 7pm: Maximum background + 5dB(A)
• 7pm to 10pm: Maximum background + 3dB(A)
• 10pm to 7am: No audible noise.
37. The certification must be submitted to Council, which certifies that operational noise from any
fixed plant and equipment complies with the requirements of this Decision Notice.
Additional Condition – 4 June 2026 – MCU13/0030.04
Approved Plans
38. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
2142 SD01 B Cover Page prepared by Kristen Sirl Design 27/04/2026
2142 SD05 A Site Plan prepared by Kristen Sirl Design 27/04/2026
2142 SD02 A Exist. Cond/Demo Plan prepared by Kristen 23/03/2026
Sirl Design
2142 SD03 A Floor Plan prepared by Kristen Sirl Design 23/03/2026
2142 SD04 A Elevations prepared by Kristen Sirl Design 23/03/2026
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
PLANNING
Aboriginal Cultural Heritage Act 2003
1. There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
carries out an activity must take all reasonable and practicable measures to ensure the
activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
duty of care. Substantial monetary penalties may apply to individuals or corporations
breaching this duty of care. Injunctions may also be issued by the Land and Resources
Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
Page 7 of 10
Document Set ID: 24843492
Version: 4, Version Date: 10/06/2026
Page 8
that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
Equitable Access and Facilities
2. The plans for the proposed building work have NOT been assessed for compliance with the
requirements of the National Construction Code - Building Code of Australia (Volume 1) as
they relate to people with disabilities. Your attention is also directed to the fact that in addition
to the requirements of the National Construction Code as they relate to people with
disabilities, one or more of the following may impact on the proposed building work:
a. the Disability Discrimination Act 1992 (Commonwealth);
b. the Anti-Discrimination Act 1991 (Queensland); and
c. the Disability (Access to Premises – Buildings) Standards.
Advertising Devices
3. All Advertising Devices must comply with Schedule 10 of Subordinate Local Law No.1
(Administration) 2015 including both temporary and permanent signage. All freestanding,
pylon or pole signs or signage that is illuminated requires approval from Council prior to being
installed. All signage identified in s6 of Schedule 10 of Subordinate Local Law No. 1 is
prohibited from being erected in the Shire.
Development Compliance Inspection
4. Prior to the commencement of the use, please contact Council's Development Assessment
Branch to arrange a Development Compliance Inspection.
Resubmission of Amended Plans Required
5. The conditions of this Decision Notice require resubmission of plans to Council with
amendments. Please address the amended plans to Council’s Development Assessment
Branch with the Reference No. MCU13/0030.03. The plans must be resubmitted prior to
lodgement of any Building Works application.
Infrastructure Charges
6. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/Planning-and-
Development/Development-tools-and-guidelines/Infrastructure-Charges
7. PROPERTY NOTES
Not applicable.
8. VARIATION APPROVAL DETAILS
Not applicable.
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Operational Works Landscaping
Development Permit for Building Works All building work.
10. SUBMISSIONS
Not applicable.
Page 8 of 10
Document Set ID: 24843492
Version: 4, Version Date: 10/06/2026
Page 9
11. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.
12. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available online at
www.noosa.qld.gov.au or at Council Offices.
Yours faithfully,
Andrew Gaffney
Senior Development Planner | Development Assessment
Development & Regulation
Enc: Appeal Rights
Infrastructure Charge Notice
Approved Plans/Documents
DECISION NOTICE HISTORY
• Original Decision Notice – 29 April 2013.
• Negotiated Decision Notice – 24 June 2013, with an amend conditions 6 & 27.
• Decision Notice – Minor – MCU13/0030.01 – 24 June 2015, with an amendment to conditions 2, 18, 19 & 20.
• Decision Notice – Minor – MCU13/0030.02 – 27 September 2016, include additional conditions 34-44, agree to include additional
approved plans.
• Decision Notice – Other Change – MCU13/0030.03 – 22 February 2022, demolish existing lodge to rebuild new 2 storey building.
• Decision Notice – Minor – MCU13/0030.04 – 4 June 2026, include additional condition 38.
Page 9 of 10
Document Set ID: 24843492
Version: 4, Version Date: 10/06/2026
Page 10
Appeal Rights
PLANNING ACT 2016 & PLANNING REGULATION 2017
Chapter 6 Dispute resolution (3) The appellant or, for an appeal to a tribunal, the registrar must,
within the service period, give a copy of the notice of appeal to –
Part 1 Appeal rights
(a) the respondent for the appeal; and
229 Appeals to tribunal or P&E Court
(b) each co-respondent for the appeal; and
(1) Schedule 1 of the Planning Act 2016 states –
(c) for an appeal about a development application under schedule
(a) Matters that may be appealed to –
1, table 1, item 1 – each principal submitter for the
(i) either a tribunal or the P&E Court; or development application; and
(ii) only a tribunal; or (d) for and appeal about a change application under schedule 1,
table 1, item 2 – each principal submitter for the change
(iii) only the P&E Court; and
application; and
(b) The person-
(e) each person who may elect to become a co-respondent for the
(i) who may appeal a matter (the appellant); and appeal, other than an eligible submitter who is not a principal
submitter in an appeal under paragraph (c) or (d); and
(ii) who is a respondent in an appeal of the matter; and
(f) for an appeal to the P&E Court – the chief executive; and
(iii) who is a co-respondent in an appeal of the matter; and
(g) for an appeal to a tribunal under another Act – any other
(iv) who may elect to be a co-respondent in an appeal of the
person who the registrar considers appropriate.
matter.
(4) The service period is –
(2) An appellant may start an appeal within the appeal period.
(a) if a submitter or advice agency started the appeal in the P&E
(3) The appeal period is –
Court – 2 business days after the appeal has started; or
(a) for an appeal by a building advisory agency – 10 business
(b) otherwise – 10 business days after the appeal is started.
days after a decision notice for the decision is given to the
agency; or (5) A notice of appeal given to a person who may elect to be a co-
respondent must state the effect of subsection (6).
(b) for an appeal against a deemed refusal – at any time after the
deemed refusal happens; or (6) A person elects to be a co-respondent by filing a notice of election,
in the approved form, within 10 business days after the notice of
(c) for an appeal against a decision of the Minister, under chapter
appeal is given to the person.
7, part 4, to register premises or to renew the registration of
premises – 20 business days after a notice us published under 231 Other appeals
section 269(3)(a) or (4); or
(1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
(d) for an appeal against an infrastructure charges notice – 20 the Supreme Court decides a decision or other matter under this
business days after the infrastructure charges notice is given Act is affected by jurisdictional error, the decision or matter is non-
to the person; or appealable.
(e) for an appeal about a deemed approval of a development (2) The Judicial Review Act 1991, part 5 applies to the decision or
application for which a decision notice has not been given – matter to the extent it is affected by jurisdictional error.
30 business days after the applicant gives the deemed
(3) A person who, but for subsection (1) could have made an
approval notice to the assessment manager; or
application under the Judicial Review Act 1991 in relation to the
(f) for any other appeal – 20 business days after a notice of the decision or matter, may apply under part 4 of that Act for a
decision for the matter, including an enforcement notice, is statement of reasons in relation to the decision or matter.
given to the person.
(4) In this section –
Note – decision includes-
See the P&E Court Act for the court’s power to extend the appeal
(a) conduct engaged in for the purpose of making a decision; and
period.
(b) other conduct that relates to the making of a decision; and
(4) Each respondent and co-respondent for an appeal may be heard
in the appeal. (c) the making of a decision or failure to make a decision; and
(5) If an appeal is only about a referral agency’s response, the (d) a purported decision; and
assessment manager may apply to the tribunal or P&E Court to
(e) a deemed refusal.
withdraw from the appeal.
non-appealable, for a decision or matter, means the decision or
(6) To remove any doubt. It is declared that an appeal against an
matter-
infrastructure charges notice must not be about-
(a) is final and conclusive; and
(a) the adopted charge itself; or
(b) may not be challenged, appealed against, reviewed, quashed,
(b) for a decision about an offset or refund-
set aside or called into question in any other way under the
(i) the establishment cost of trunk infrastructure identified in Judicial Review Act 1991 or otherwise, whether by the
a LGIP; or Supreme Court, another court, a tribunal or another entity; and
(ii) the cost of infrastructure decided using the method (c) is not subject to any declaratory, injunctive or other order of
included in the local government’s charges resolution. the Supreme Court, another court, a tribunal or another entity
on any ground.
230 Notice of appeal
232 Rules of the P&E Court
(1) An appellant starts an appeal by lodging, with the registrar of the
tribunal or P&E Court, a notice of appeal that- (1) A person who is appealing to the P&E Court must comply with the
rules of the court that apply to the appeal.
(a) is in the approved form; and
(b) succinctly states the grounds of the appeal. (2) However, the P&E Court may hear and decide an appeal even if
the person has not complied with the rules of the P&E Court
(2) The notice of appeal must be accompanied by the required fee.
Page 10 of 10
Document Set ID: 24843492
Version: 4, Version Date: 10/06/2026
Used in these records
Minor Change Existing Approval MCU13 0030 04 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 173 KB (small file)
- File type
No other editions are linked here.