Council archive · source document
SUPERSEDED 23657 DA - Change to Existing Approval - extension of currency [As Published] · 132003.221172.3
Officer: Jack Lewis
Direct Telephone: (07) 5449 5183
Response Address: Locked Bag 72
Sunshine Coast Mail Centre QLD 4560
Email: [email protected]
Our Reference: 23657 DA
Your Reference:
10 August 2010
Harman Family Trust
CARE Karen Harman
35 Lorilet Street
PEREGIAN BEACH QLD 4573
Dear Sir/Madam
Change to an Existing Approval
Sustainable Planning Act 2009
I refer to your request to make a change to an existing approval. On 9 August 2010 Council decided
your requested changes.
Details of the decision with the consolidated conditions are as follows:
1 APPLICATION DETAILS
Application No: 23657 DA
Street address: 61 Elanda Street, Sunshine Beach
Real property description: Lot 408 RP 48112
Planning Scheme: The Noosa Plan
2 DECISION DETAILS
Council on 14 October 2004 decided to issue the following type of approval:-
Preliminary Approval for Material Change of Use - Duplex Dwelling
In relation to representations, Council on 16 December 2004 decided to:
A. Grant a development permit subject to the conditions contained in the preliminary approval
issued on 14 October 2004
B. Agree to delete Condition 1, 12 & 13
C. Agree to amend Condition 2. As a result of the deletion of Condition 1, Condition 17 was
subsequently amended
In relation to your request to extend the relevant period for the above development approval, Council
on 9 December 2008 decided to:
A. Extend the relevant period until 16 December 2010.
B. Approve a change to Condition 17.
C. Issue a Change to an Existing Approval.
Page 1 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 10 pages
Page 2
2003/221172
In relation to your request to extend the relevant period for the above development approval, Council
on 9 August 2010 decided to:
A. Extend the relevant period until 16 December 2012.
B. Approve a change to Condition 17.
C. Issue a Change to an Existing Approval.
3 RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager
conditions.
4 ASSESSMENT MANAGER CONDITIONS
Land Use
1. Deleted.
2. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are numbered 4/1918/S1E 1 & 2,
prepared by Adrian Pooley & Associates and dated 15 November 2004, and as may be
amended by these conditions.
3. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
4. The development must not exceed 40% maximum site cover, as defined by the Schedule to
the Planning Scheme.
2
5. The development is to provide a minimum 264m of landscaped open space, as defined by
the Schedule to the Planning Scheme.
6. The open space and setback areas are to be landscaped in accordance with Council’s Policy
on Landscaping Guidelines and a properly prepared landscape plan prepared by a suitably
qualified Landscape Architect or Horticulturalist. Such landscaping is to be completed prior to
the premises being occupied and maintained at all times thereafter and to include the
following:-
6.1 Dense landscaping is to be implemented along the southern boundary, specifically to
the area where the basement wall extends to 0.900 metres from the southern boundary.
The landscaping shall include understorey plantings and a diverse range of trees
ranging from 45 to 75 Litres and whereby an average height of 3 metres is achieved.
6.2 Screening vegetation in the form of native trees and understorey plantings is required to
be planted along the full length of the northern boundary.
6.3 The Eucalyptus Intermedia located at the front of the site is to be retained.
6.4 All retained trees are to be protected from filling works and barricaded to prevent
damage occurring during construction.
6.5 The two Eucalyptus located at the rear of the site shall be replaced with the same
species during the landscaping of the development.
6.6 Two street trees endemic to the Sunshine Beach locality are to be planted in the road
reserve.
7. Existing trees on the site and within road reserves are to be retained, except where required to
be removed due to building operations or the conduct of the approved use. The landscaped
plans referred to above are to denote areas of existing vegetation or existing trees proposed to
be retained.
Page 2 of 11
Page 3
2003/221172
8. All fencing shall be setback at least 1 metre from the front property boundary, with at least half
of the fencing to be setback 2 metres. The area of land between the fence and the front
property boundary shall be densely landscaped to screen any fencing.
9. Any deck areas are not to be enclosed with shutters, glass panelling or the like, thus
remaining as open structures.
10. Balustrading is to be of open and transparent materials.
11. The development must not exceed a building height of three (3) storeys and twelve (12)
metres measured vertically at any point from both the natural ground level and the finished
ground level, in accordance with the requirements of the Schedule to the Planning Scheme.
12. Deleted.
13. Deleted.
14. The proposed development shall have all kitchen, laundry and bathroom fittings that comply
with the AAA Water Conservation Rating System as defined by the AS/NZS 6400 (Water
Efficient Products - Rating and Labelling 2003) and AS/NZS 3500 (National Plumbing and
Drainage Standard Part 1.2). All tap ware and shower roses shall not exceed a maximum flow
of 9 litres per min. Dishwashers and washing machines are excluded from this requirement.
15. Security in the form of a cash bond or trading bank guarantee to the sum of $20,000 must be
submitted, to secure performance of all conditions of this approval, prior to the issue of a
Development Permit for operational works. The cash bond or trading bank guarantee will be
returned on performance of the conditions of approval less any costs incurred by Council in
respect of enforcing performance of this permit.
16. The requirements of this development approval are to be effected, prior to the use of the
premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
this approval to effect compliance with conditions.
17. This Development Permit for a Material Change of Use lapses if:-
17.1. the use has not commenced by 16 December 2012, unless application is made and
approved by Council for an extension; or
17.2. the use of any premises pursuant to the Development Permit ceases.
18. The developer must obtain all of the other Development Permits referred to in the Decision
Notice, prior to obtaining a Development Permit for building works.
Land Development
Vehicle Access
19. A 4.5 metre wide vehicular access driveway to serve the development shall be constructed
from the Elanda Street frontage of the site.
The driveway shall be designed and constructed to Council’s design standards and to grades
that prevent vehicles from scraping and/or bottoming. Should any driveways be constructed to
grades that do not comply with AS2890.1-1993 and AS2890.2-1989, Council will require that
the driveway be removed and reconstructed to levels that do comply.
20. All vehicles shall enter and leave the site in a forward direction.
Carparking
21. Carparking shall be provided within the site as shown on drawing number 4/1918/S1c dated
2/8/04 by Adrian Pooley & Associates Pty Ltd, except as modified herein.
22. A minimum of 4 covered carpark spaces shall be provided on site and the carparking area
shall be designed to comply with the provisions of AS 2890.1-1993 with a minimum head
clearance (headroom) at any point of 2.2m.
Page 3 of 11
Page 4
2003/221172
23. The column located to the south west of carpark space number 3 (in-line with the garage wall
to the west of carpark space 3) largely inhibits the forward manoeuvre of vehicles that have
reversed from spaces 3 & 4. As such, this column shall be relocated so that it does not inhibit
any vehicle manoeuvres.
Vegetation Protection
24. Existing trees to be retained shall be protected during the construction phase by providing
temporary fencing around the trees. Plans submitted for Operational Works approval shall
clearly show this.
Roadworks Contributions
25. A roadworks contribution of $1,061 towards the Coastal Major Road Network shall be paid to
the Council prior to obtaining a Development Permit for Operational Works. This amount will
be subject to variations in the Price Index, All Groups Brisbane from June 2004 until the date
of payment.
Roadworks Widening
26. The Elanda Street frontage of the development shall be provided with kerb & channelling and
bitumen road widening. The new kerb & channel shall be aligned so that it is located 8 metres
off the existing kerb & channel on the western side of the road measured from the nominal
face of the kerb.
All associated and ancillary work including pavement correction to the existing pavement,
drainage works, modification of the footpath, and adjustments to any existing infrastructure
shall be undertaken to complete the roadworks widening.
Plans detailing this work shall be prepared and submitted to Council for approval prior to
obtaining a Development Permit for Operational Works.
Frontage Works
27. Footpath improvements such as topsoiling, grassing, and tree planting are required to the
Elanda Street frontage of the site in accordance with Planning Scheme Policy PSP1
Landscaping Guidelines. Grass shall be couch, free of weeds.
28. A new 1.2 metre wide concrete path shall be constructed along the frontage of the site in
accordance with Council’s design standards and to an alignment that protects any significant
vegetation or any underground services. The path shall be designed and constructed to
ensure pedestrian safety using non-slip materials and to produce an evenly graded surface
finish.
Pathway Contributions
29. A pathway contribution of $246 towards external major pathways, in accordance with Planning
Scheme Policy PSP41 Coastal Major Pathway Contributions, shall be paid to the Council prior
to obtaining a Development Permit for Operational Works. This amount will be subject to
variations in the Price Index, All Groups Brisbane from June 2004 until the date of payment.
Stormwater Drainage
30. All stormwater drainage shall be collected on site and discharged so there is no net increase
in stormwater runoff from the site. Plans of the drainage design shall be prepared by a
Registered Professional Civil Engineer and submitted to Council prior to obtaining a
Development Permit for Operational Works.
Any stormwater discharged to Council’s street drainage system shall have a maximum
discharge at any one location of 25 litres/second.
31. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
Page 4 of 11
Page 5
2003/221172
32. The site shall be connected to Council’s existing sewerage reticulation systems and be
constructed in accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply
33. The site shall be connected to Council’s existing town water supply and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
34. Each water connection to the water reticulation system shall extend to the property boundary
and be metered. Where multiple units are served by a single service, multiple water meters to
each individual unit shall be installed. All fees for the supply of water meters shall be paid to
the Council.
Service Easements
35. A registered easement shall be created over the existing sewer main that crosses the rear of
the site. The easements shall generally be parallel to and centred over the sewer main and be
equivalent in width to twice the depth to invert level of the sewer at the deepest point within the
allotment (measured from the finished surface) and be no less than 3.0 metres wide.
In this regard, plans submitted for Operational Works approval shall accurately show the
location of the easement.
In addition to this the Applicant’s Solicitor shall give Council’s Solicitor an appropriate
undertaking in writing that the Title Deed and the easement documents will be lodged at the
Land Titles Office and any additional Titles Office forms or requisitions requiring the consent of
Council will be attended to promptly.
A duly executed copy of the easement shall be submitted to Council for perusal prior to the
use commencing.
Any changes required by Council’s Solicitor must be corrected immediately.
36. No building or other structure shall be constructed or encroach over an easement. Any
building or structure within proximity of an easement or any other public utility’s underground
must have its foundations designed so that no surcharge loads are imposed upon such
underground infrastructure. Foundations must be taken down a minimum of 1 metre below a
line of influence measured 1 metre in the direction of the foundation from the centreline of the
closest underground service and along the natural angle of repose of the foundation soil
type(s).
Plans, and supportive documents, detailing these proposed foundations shall be designed by
a registered practicing Geotechnical Engineer and submitted with the application for a
Development Permit for Operational Works.
Headworks
37. Contributions shall be paid to Council in accordance with Planning Scheme Policies PSP28
and PSP30 on Water Supply Headworks Contributions and Sewerage Headworks
Contributions respectively and at the rates applicable at the time of payment. An estimate
only of the contribution rates as of June 2004 under the current policies is as follows:
Water Supply $ 4,255
Sewerage $ 2,905
TOTAL $ 7,160
All headworks contributions must be paid prior to the issue of a Development Permit for
Operational Works.
Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the
headworks contributions not be paid at the due time, Council shall call upon the trading bank
guarantee in full.
In the event that the Development Permit for Material Change of Use of Premises lapses or is
cancelled, the contribution or trading bank guarantee will be returned.
Page 5 of 11
Page 6
2003/221172
Earthworks
38. Earthworks required on site shall be carried out in accordance with Section 3.8 of Council’s
Engineering Design Standards Manual and so as not to cause the ponding of water on any
adjoining lands or the blockage of, or interference with any natural watercourses.
39. Earthworks carried out on site shall not affect the structural integrity of any of the existing
fences that border the development site unless it is intended to replace such fences. In this
regard any fences to be replaced shall be clearly shown on the plans submitted for
Operational Works approval.
Erosion and Sediment Control
40. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
Plans detailing the methods of controlling erosion and sediment are required to be submitted
to the Council for approval prior to obtaining a Development Permit for Operational Works.
General
41. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
42. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
43. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to or
from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
44. A Registered Professional Engineer of Queensland shall certify engineering drawings and
specifications for all engineering works, which shall be submitted in conjunction with an
application for a Development Permit for Operational Works.
Building Services
45. A verification survey of the building is to be carried out by a Licensed Surveyor and a
certificate lodged with Council at completion of the work confirming compliance with the
maximum building height above natural surface, required by the provisions of the Planning
Scheme.
Environmental Health
46. The developer must provide a suitably screened imperviously paved area large enough for all
refuse and recycling containers. A wash down area is required with a cold-water tap, hose and
drain outlet connected to sewer. The drain outlet is to be designed to prevent stormwater entry
to the sewerage system.
47. Swimming pool or spa pumps are to be contained in an acoustically treated enclosure or
located in a manner which prevents a noise nuisance beyond the subject land in accordance
with the nuisance provisions of the Environmental Protection Regulation 1998. On the spot
fines apply for such offences.
48. All lift plant including motors, shall be situated within the building or suitably provided with
noise reduction measures and located as to prevent a noise nuisance beyond the subject land
in accordance with the nuisance provisions of the Environmental Protection Regulation 1998.
On the spot fines apply for such offences.
49. Noise emission from air conditioning equipment shall comply with the following requirements:
Page 6 of 11
Page 7
2003/221172
49.1 The equipment shall be installed and located in a manner which prevents noise
nuisance beyond the subject land in accordance with the nuisance provisions of the
Environmental Protection Regulation 1998 and Council’s Local Law No. 12 - Control of
Nuisances. Infringement Notices (on-the-spot fines) may apply for offences.
49.2 Submission of written certification from a suitably qualified person confirming that the
noise levels comply when measured at the nearest residential boundary. This is
required immediately after installation of the equipment and prior to any occupation of
the building, and in a format approved by Council.
49.3 A person must not use equipment on any day if it makes or causes noise to be made –
49.3.1 Before 7am or after 10pm: More than the lower of either –
40 d(B)A
3 d(B)A above the background noise level
49.3.2 From 7am to 7pm: More than the lower of either –
50 d(B)A
5 d(B)A above the background noise level
49.3.3 From 7pm to 10pm: More than 3 d(B)A above the background noise level.
5 REFERRAL AGENCY CONDITIONS
Not applicable.
6 APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
Plan / Document No. Issue Plan / Document Name Date
4/1918/S1E -1 4 Floor Plans 15 November 2004
4/1918/S1E -2 4 Elevations 15 November 2004
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. Building is to comply with the Building Code of Australia Section C Fire Resistance in regard to
distances or protection required.
2. Payment via credit card transaction will not be an acceptable method of payment for
development contributions conditioned in this permit.
3. The Environmental Protection Regulation 1998 and Local Law No.12 prohibit a builder from
making noise from:-
3.1. Monday to Saturday, before 7:00am or after 6:30pm
3.2. Sunday or public holiday, at any time.
A maximum penalty of $1,500 applies to an offence under these provisions.
4. In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud, paint,
cement, concrete, builders waste or rubbish shall not be permitted to enter or be placed where
it could reasonably be expected to move into a roadside gutter, stormwater drain or a water
course. On the spot fines apply for such offences.
Page 7 of 11
Page 8
2003/221172
5. Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if
the cost of operational works exceeds $80,000, then a portable long service levy is required to
be paid. In accordance with Section 77.(1) of the Act, Council is required to sight the approved
form issued by the Building and Construction Industry (Portable Long Service Leave) Authority
that confirms that the requirements of the Act have been satisfied. A statutory declaration
outlining the cost of the operational works must be submitted to Council with the lodgement of
any application for operational works over the site.
6. We advise ‘interested parties’ i.e. ‘developer’, ‘owner’, ‘tenant’ to consider their responsibilities
under the Disabled Discrimination Act (DDA) in regard to the installation of disabled access
and the provision of disabled facilities, and that access to this building and the provision of
sanitary facilities may need to comply with the requirements of Section D Part D3 and Section
F Clause F2.4 of the Building Code of Australia.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act
can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural
heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.
8 PROPERTY NOTES
Not applicable.
9 PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable
10 FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
Development Permit for Building Works Duplex Dwelling
Development Permit for Operational Works Landscaping, Carparking and Access, Frontage
Works, Stormwater Disposal, Sediment and
Erosion Controls and Filling of the Site
11 SELF ASSESSABLE CODES
Not applicable
12 SUBMISSIONS
There were no properly made submissions about the application.
13 REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable
Page 8 of 11
Page 9
2003/221172
14 RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Sustainable Planning Act 2009 is attached.
15 OTHER DETAILS
Should you wish to obtain more information about Council’s decision electronic copies are available
on line at www.sunshinecoast.qld.gov.au, or at Council Offices.
DECISION NOTICE HISTORY
14 October 2004 Original Decision Notice issued.
16 December 2004 Negotiated Decision Notice issued with amendment to Conditions
2 & 17 and deletion of Conditions 1, 12 & 13.
9 December 2008 Change to an Existing Approval issued with amendment to
Condition 17.
9 August 2010 Change to an Existing Approval issued with amendment to
Condition 17 extending the currency period to 16 December 2012.
Yours faithfully,
Denis Wallace
PLANNING OFFICER
Enc Appeal Rights
Page 9 of 11
Page 10
2003/221172
Appeal Rights
SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING
REGULATION 2009
The following is an extract from the Sustainable (ii) the length of a period mentioned in
Planning Act 2009 (Chapter 6). section 341 for the approval.
(3) However, a submitter may not appeal if the
MATERIAL CHANGE OF USE, RECONFIGURING A
submitter—
LOT & OPERATIONAL WORKS
Division 8 - Appeals to court relating to development (a) withdraws the submission before the
applications application is decided; or
461 Appeals by applicants (b) has given the assessment manager a
notice under section 339(1)(b)(ii).
(1) An applicant for a development application may
appeal to the court against any of the following- (4) The appeal must be started within 20 business
days (the submitter’s appeal period) after the
(a) the refusal, or the refusal in part, of a decision notice or negotiated decision notice is
development application; given to the submitter.
(b) any condition of a development approval, 463 Additional and extended appeal rights for
another matter stated in a development submitters for particular development
approval and the identification or inclusion applications
of a code under section 242
(1) This section applies to a development
(c) the decision to give a preliminary approval application to which chapter 9, part 7
when a development permit was applied applies.
for;
(2) A submitter of a properly made submission for
(d) the length of a period mentioned in section the application may appeal to the court about a
341;; referral agency’s response made by a
(e) a deemed refusal of the development prescribed concurrence agency for the
application. application.
(2) An appeal under subsection (1)(a), (b), (c) or (3) However, the submitter may only appeal
(d) must be started within 20 business days against a referral agency’s response to the
(the applicant’s appeal period) after— extent it relates to—
(a) if a decision notice or negotiated decision (a) if the prescribed concurrence agency is the
notice is given—the day the decision notice chief executive (environment)—
or negotiated decision notice is given to the development for an aquacultural ERA; or
applicant; or (b) if the prescribed concurrence agency is the
(b) otherwise—the day a decision notice was chief executive (fisheries)—development
required to be given to the applicant. that is—
(3) An appeal under subsection (1)(e) may be (i) a material change of use of premises
started at any time after the last day a decision for aquaculture; or
on the matter should have been made. (ii) operational work that is the removal,
462 Appeals by submitters - general damage or destruction of a marine
plant
(1) A submitter for a development application may
appeal to the court only against- (4) Despite section 462(1), the submitter may
appeal against the following matters for the
(a) the part of the approval relating to the application even if the matters relate to code
assessment manager’s decision about any assessment—
part of the application requiring impact
assessment under section 314; or (a) a decision about a matter mentioned in
section 462(2) if it is a decision of the chief
(b) the part of the approval relating to the executive (fisheries);
assessment manager’s decision under
section 327. (b) a referral agency’s response mentioned in
subsection (2).
(2) To the extent an appeal may be made under
subsection (1), the appeal may be against 1 or 464 Appeals by advice agency submitters
more of the following— (1) Subsection (2) applies if an advice agency, in
(a) the giving of a development approval; its response for an application, told the
assessment manager to treat the response as
(b) any provision of the approval including— a properly made submission.
(i) a condition of, or lack of condition for, (2) The advice agency may, within the limits of its
the approval; or jurisdiction, appeal to the court about—
Page 10 of 11
Page 11
2003/221172
(a) any part of the approval relating to the 467 Appeals about changing or cancelling
assessment manager’s decision about any conditions imposed by assessment
part of the application requiring impact manager or concurrence agency
assessment under section 314; or (1) A person to whom a notice under section
(b) any part of the approval relating to the 378(9)(b) giving a decision to change or cancel
assessment manager’s decision under a condition of a development approval has
section 327 been given may appeal to the court against the
(3) The appeal must be started within 20 business decision in the notice.
days after the day the decision notice or (2) The appeal must be started within 20 business
negotiated decision notice is given to the days after the day the notice of the decision is
advice agency as a submitter. given to the person.
(4) However, if the advice agency has given the For Building Works Only
assessment manager a notice under section 532 Appeals by applicants
339(1)(b)(ii), the advice agency may not appeal
the decision. (1) If—
465 Appeals about decisions relating to (a) a person has been given, or is entitled to be
extensions for approvals given—
(1) For a development approval given for a a. an information notice under the
development application, a person to whom a Building Act about a decision
notice is given under section 389, other than a other than a decision under that
notice for a decision under section 386(2), may Act made by the Queensland
appeal to the court against the decision in the Building Services Authority; or
notice. b. an information notice under the
(2) The appeal must be started within 20 business Plumbing and Drainage Act 2002
days after the day the notice of the decision is about a decision under part 4 or
given to the person. 5 of that Act; or
(3) Also, a person who has made a request under (b) a person—
section 383 may appeal to the court against a a. was an applicant for a building
deemed refusal of the request development approval; and r
(4) An appeal under subsection (3) may be started b. is dissatisfied with a decision
at any time after the last day the decision on under the Building Act by a
the matter should have been made. building certifier or referral
agency about inspection of
466 Appeals about decisions relating to
building work the subject of the
permissible changes)
approval; the person may appeal
(1) For a development approval given for a against the decision to a building
development application, the following persons and development committee.
may appeal to the court against a decision on a
(2) An appeal under subsection (1) must be started
request to make a permissible change to the
within 20 business days after the day the
approval—
person is given notice of the decision.
(a) if the responsible entity for making the (3) If—
change is the assessment manager for the
application— (a) under the Building Act, a person makes an
application other than a building
(i) the person who made the request; or development application to a local
(ii) an entity that gave a notice under government; and
section 373 or a pre-request response (b) the period required under that Act for the
notice about the request
local government to decide the application
(b) if the responsible entity for making the (the decision period) has passed; and
change is a concurrence agency for the (c) the local government has not decided the
application—the person who made the application; the person may appeal to a
request.. building and development committee
(2) The appeal must be started within 20 business against the lack of the decision and for the
days after the day the person is given notice of committee to decide the application as if it
the decision on the request under section 376. were the local government.
(3) Also, a person who has made a request under (4) An appeal under subsection (3) must be started
section 369 may appeal to the court against a within 20 business days after the end of the
deemed refusal of the request. decision period..
(4) An appeal under subsection (3) may be started
at any time after the last day the decision on
the matter should have been made.
Page 11 of 11
Used in these records
SUPERSEDED 23657 DA - Change to Existing Approval - extension of currency [As Published]Related documentApplication case desk ↗
About this file
- File size
- 69 KB (small file)
- File type
No other editions are linked here.