  REFERENCE DOCUMENT
MCU21/0117.01 & OPW21/0199.01
      NOOSA COUNCIL
        12 JULY 2024                                                 SITE BASED STORMWATER
                                                                           MANAGEMENT PLAN


                                                   PROPOSED TOWNHOUSE DEVELOPMENT AT
                                                                       5 PEARL STREET
                                                                              COOROY


                                                                                                                 Prepared for

                                                                                                             Altum Property Group
                                                                                                       Attention: Rob McCready



                                                                                                 Document Reference
                                                                                                                23098 - SBSMP/4


     Record of Issue:

      Issue         Status              Author            Date           Checked             Date            Authorised   Date
                                                          18 Sep                             19 Sep      Henry Morgan     20 Sep
         0        For Review           Rick Cui                         Darren Yuen
                                                           2023                               2023        RPEQ 11950       2023
                                                          26 Sep                             28 Sep      Henry Morgan     29 Sep
         1       For Approval          Rick Cui                         Darren Yuen
                                                           2023                               2023        RPEQ 11950       2023
                                                          17 Jan                             17 Jan      Henry Morgan     17 Jan
         2       For Approval          Rick Cui                        Winston Boon
                                                           2024                               2024        RPEQ 11950       2024
                                                         18 Mar        Henry Morgan          18 Mar      Henry Morgan     18 Mar
         3       For Approval       Winston Boon
                                                          2024          RPEQ 11950            2024        RPEQ 11950       2024
                                                         08 May        Henry Morgan         14 May       Henry Morgan     14 May
         4       For Approval       Winston Boon
                                                          2024          RPEQ 11950           2024         RPEQ 11950       2024

     This investigation and report has been authorised by Mr Henry Morgan, a Director of Morgan
     Consulting Engineers Pty Ltd.




     Henry J Morgan           RPEQ 11950                                                                 Tuesday, 14 May 2024

     D:\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\SBSMP\Current\23098 - SBSMP - Rev 4.docx
Full text of the other 59 pages

Page 2

                                                                                             23098 - SBSMP/4
                                                                                                       Page 2




                                            Table of Contents
1     INTRODUCTION ............................................................................................ 3
2     EXISTING SITE.............................................................................................. 4
  2.1    The Site ................................................................................................ 4
  2.2    Surrounding Area ...................................................................................... 4
3     PROPOSED DEVELOPMENT ............................................................................... 5
4     EXISTING DRAINAGE PATTERNS ......................................................................... 6
  4.1    Existing Infrastructure ............................................................................... 6
  4.2    Existing Drainage Patterns ........................................................................... 7
  4.3    Lawful Point of Discharge............................................................................ 7
5     STORMWATER QUANTITY................................................................................. 8
  5.1    Rational Method Assessment ........................................................................ 8
    5.1.1     Design Storms ....................................................................................8
    5.1.2     Rainfall Intensity ................................................................................8
    5.1.3     Times of Concentration .........................................................................8
    5.1.4     Runoff Coefficients ..............................................................................8
    5.1.5     Peak Flows ........................................................................................9
  5.2    Proposed Development Drainage ................................................................... 9
  5.3    DRAINS Modelling Assessment ....................................................................... 9
    5.3.1     Hydraulic Model Parameters ................................................................. 10
    5.3.2     Design Storms .................................................................................. 10
    5.3.3     Intensity Frequency Distribution ............................................................ 10
    5.3.4     Pre-Development Model ...................................................................... 10
    5.3.5     Post-Development Model ..................................................................... 11
    5.3.6     Post-Development Mitigated Model – On-site Detention Tank .......................... 11
    5.3.7     Comparison of Peak Flows at Lawful Point of Discharge ................................. 13
6     STORMWATER QUALITY ................................................................................ 15
  6.1    State Planning Policy Assessment ................................................................ 15
  6.2    Construction Phase ................................................................................. 15
  6.3    Operational Phase .................................................................................. 17
    6.3.1     Sources of Contaminants ..................................................................... 17
    6.3.2     Proposed Treatment Train ................................................................... 18
    6.3.3     Pollutant Export Modelling ................................................................... 18
    6.3.4     MUSIC Modelling Parameters ................................................................. 18
    6.3.5     MUSIC Modelling Results ...................................................................... 19
7     FLOODING ................................................................................................ 21
8     CONCLUSION ............................................................................................. 22
Appendix A DETAILED SITE SURVEY ........................................................................ 23
Appendix B PROPOSED DEVELOPMENT PLANS ............................................................ 24
Appendix C NSC INTERACTIVE MAPPING PLANS .......................................................... 25
Appendix D NSC WATER QUALITY AND DRAINAGE CODE ................................................ 26
Appendix E RATIONAL METHOD CALCULATIONS ......................................................... 27
Appendix F CONCEPT SITE LEVELS AND DRAINAGE PLAN ............................................... 28
Appendix G BOM IFD ......................................................................................... 29
Appendix H DRAINS PRE & POST DEVELOPMENT RESULTS .............................................. 30
Appendix I DRAINS POST DEVELOPMENT MITIGATED RESULTS ........................................ 31
Appendix J STORMWATER QUALITY OPERATION AND MAINTENANCE GUIDELINES .................. 32
Appendix K NSC FLOOD HAZARD OVERLAY MAP .......................................................... 33




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 3

                                                                              23098 - SBSMP/4
                                                                                      Page 3




1 INTRODUCTION
This Site Based Stormwater Management Plan (SBSMP) has been prepared for the Proposed
Townhouse Development at 5 Pearl Street, Cooroy.

This SBSMP has been prepared to investigate the effects the development will have on stormwater
quantity and quality.

The objective of this SBSMP is to ensure that there is no adverse impact by the development on
the environmental value of the receiving waters during the construction and operational phases
of the development. This SBSMP will also provide recommendations to ensure that the post-
development peak outflow conditions are not greater than the pre-development peak outflow
conditions.

In order to achieve this objective, this SBSMP:

    1. Describes the environmental setting of the development site and precinct;

    2. Describes the nature of the proposed development as it relates to stormwater quality;

    3. Calculates the peak flows for both pre and post-development conditions;

    4. Calculates the detention volume if required to achieve the pre-development outflow in the
       post-development state; and

    5. Identifies potential sources of contaminants and describes the management techniques
       designed to be employed on the site to achieve the water quality objectives.

The proposed development has been assessed against the following guidelines and planning
documents:

    1. State Planning Policy 2017 (SPP 2017);

    2. Urban Stormwater Quality Planning Guidelines 2010;

    3. The Queensland Urban Drainage Manual (QUDM); and

    4. Noosa Shire Council Plan 2020;




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 4

                                                                                   23098 - SBSMP/4
                                                                                           Page 4




2 EXISTING SITE

2.1 The Site
The subject site, comprised of Lot 2 on RP153798 and Lot 2 on RP64750 is approximately 2,274m2
(0.2274ha) in area. The site is currently occupied by two existing residential dwellings, with
associated sheds and garages. Trees and shrubs are scattered throughout the subject site.

The subject site generally slopes from the southwest (with an approximate height of 107.41m AHD)
towards the northeast (with an approximate height of 105.2m AHD). Existing access to the subject
site is currently provided from Pearl Street and Elm Street.

Refer to Figure 2.1 for a Locality Plan and Appendix A for the Detailed Site Survey.




   N

                                             Sapphire Street

                                                           Subject Site
                                Elm Street




                                                                                                    Kauri Street
                                                Pearl Street




                         Figure 2.1 – Locality Plan of Site and Surrounding Area

2.2 Surrounding Area
The site is located within the limits of the NSC region and is classified as Medium Density Residential
Zone. The site is surrounded by residential properties to the north and east and commercial
properties to the west and south. Cooroy Creek lies further west and Cooroy Train Station lies
further south west.


Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 5

                                                                      23098 - SBSMP/4
                                                                             Page 5




3    PROPOSED DEVELOPMENT
The Proposed Townhouse Development primarily involves:

    1. Three buildings containing a mix of two and three-bed units;

    2. Carparking spaces for residents and visitors;

    3. Vehicular access via Pearl Street, south of the site; and

    4. Dedicated landscaping and planting throughout the site.


Refer to Appendix B for the Proposed Development Plans.




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 6

                                                                                                   23098 - SBSMP/4
                                                                                                            Page 6




4 EXISTING DRAINAGE PATTERNS

4.1 Existing Infrastructure
Data obtained from the NSC Interactive Mapping plans and detailed site survey indicate the
following existing drainage infrastructure:
    1. Swale drain traversing the northern verge of Pearl Street, south of the site;
    2. Swale drain traversing the eastern verge of Elm Street, west of the site;
    3. A 300mm dia. to 600mm dia. stormwater line traversing the southern verge of Pearl Street,
       south of the site; and
    4. A 1350mm dia. to 1800mm dia. stormwater line traversing the eastern boundary of 11 Pearl
       Street, east of the site.

Refer to Figure 4.1 for the existing stormwater infrastructure and drainage patterns and Appendix
C for the Noosa Council Interactive Mapping Plans.




   N




                                                                 Subject Site

                                                                                         Ø 1350
                    Elm Street




                                                                                                    Ø 375
                                                                                         Ø 1800




 Legend
                                          Pearl Street
 Sheet Flow Path
 Stormwater Line                                         Ø 300

 Stormwater Pit                                                                 Ø 600             Ø 750

 Swale Drain
 Headwall


                                 Figure 4.1 – Existing Drainage Paths & Infrastructure




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 7

                                                                               23098 - SBSMP/4
                                                                                       Page 7




4.2 Existing Drainage Patterns
Following an assessment of the existing site conditions and drainage infrastructure we can confirm
that the site has the following drainage patterns:

Roofwater Runoff
    1. Roofwater runoff from the site is discharged onto the ground where it sheet flows to the
       Environmental Management and Conservation Area, northeast of the site.
Surface Runoff
    1. Surface runoff from the site sheet flows to the Environmental Management and
       Conservation Area, northeast of the site.
External Catchment
    1. There is an external ground catchment contributing runoff from 52 Elm Street, southwest
       of the site, which sheet flows through the site to the Environmental Management and
       Conservation Area, northeast of the site.

It is noted that all sheet flow traversing across the site becomes concentrated along the eastern
boundary of the site due to an existing bund along this boundary that was constructed as part of
7 Pearl Street. Concentrated flow along this boundary is directed to the Environmental
Management and Conservation Area, northeast of the site.

Refer to Figure 4.1 for a drainage schematic and Appendix A for the detailed site survey plan.


4.3 Lawful Point of Discharge
If the proposed development maintains pre-development flow conditions, the lawful point of
discharge (LPD) is the existing Environmental Management and Conservation Area, northeast of
the site.

In consideration of the site characteristics, surrounding topology and stormwater drainage
infrastructure, the aforementioned proposed lawful point of discharge is considered to be
compliant with the criteria for lawful point of discharge outlined in Section 3.9.1. of QUDM 2017
as per below:

    i) The location of the proposed discharge point is under the lawful control of the local
       government or other statutory authority from whom permission to discharge has been
       received.

    ii) The post development discharge will not cause an actionable nuisance, nor environmental
        or property damage, as the existing flow characteristics and drainage patterns will be
        maintained for the proposed development.

    iii) Authority to discharge over affected properties will not be required as the proposed
         drainage patterns does not impact surrounding properties adjacent to and downstream of
         the subject site.

Refer to Section 5 outlining the Stormwater Quantity aspects of this site and Appendix D for the
Water Quality and Drainage Code.




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 8

                                                                               23098 - SBSMP/4
                                                                                        Page 8




5 STORMWATER QUANTITY
A roof and allotment drainage system is to be designed to comply with:

    1. AS/NZS 3500.3:2015 - Plumbing and Drainage Part 3: Stormwater Drainage;

    2. The Queensland Urban Drainage Manual (QUDM), and;

    3. The Noosa Council Engineering Design Standards – Road, drainage and earthworks.


5.1 Rational Method Assessment
The Rational Method has been used to calculate the peak discharges from the site under the
existing (pre-development) and proposed (post-development) conditions.

5.1.1 Design Storms
As defined in the BRC Planning Scheme Policies the following design storms were adopted:

    1. Minor Drainage System: 10 year ARI statistical flood (Q10 storm);

    2. Major Drainage System: 100 year ARI statistical flood (Q100 storm).

5.1.2 Rainfall Intensity
Rainfall intensities for this study were obtained from the Australian Bureau of Meteorology.

5.1.3 Times of Concentration
Times of concentration (tc) were calculated as defined in the QUDM. Refer to Table 5-1 for the
adopted tc’s and Appendix E for tc calculations.

                                     Table 5-1 – Adopted tc values
                                   Pre development         Post development
                                       tc (mins)                tc (mins)

                                          9.7                     5



5.1.4 Runoff Coefficients
The 10 year runoff coefficient’s (C10) were determined as defined in the QUDM. Refer to Table 5-2
below for the adopted C10 values.

                                      Table 5-2 – Adopted C10 Values

                                         Property State               C10

                                       Pre-development                0.75
                                       Post-development               0.85




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 9

                                                                                        23098 - SBSMP/4
                                                                                                 Page 9




5.1.5 Peak Flows
Refer to Table 5-3 for a summary of the predicted minor and major discharge rates for pre and
post development conditions and Appendix E for the Rational Method calculations.

                               Table 5-3 – Pre and Post Development Peak Flows

          Property State              Q2 (m3/s)    Q5 (m3/s)   Q10 (m3/s) Q20 (m3/s) Q50 (m3/s) Q100 (m3/s)

        Pre development                 0.045       0.068       0.083       0.099      0.125       0.143
        Post development                0.062       0.094       0.116       0.139      0.176       0.199

As shown in Table 5-3, an increase in impervious surface areas will consequently increase
stormwater runoff peak flow rates from the proposed development.
Hence, it is proposed to utilise a series of on-site above ground detention tanks to mitigate the
stormwater runoff of the proposed development prior to discharging to the Lawful Point of
Discharge, northeast of the site.

Refer to Appendix E for the Rational Method Calculations, Appendix F for the Concept Site Levels
and Drainage Plans and Section 6 for the Stormwater Quality Management Plan.


5.2 Proposed Development Drainage
The proposed development drainage intent is as follows:

Development Catchment:

    1. Runoff from the roof catchments will flow via downpipes to aboveground detention tanks
       combined with rainwater reuse for mitigation prior to discharging to the lawful point of
       discharge, northeast of the site.
    2. Runoff from the ground catchment will be directed to the bioretention basin and level
       spreader located in the north eastern corner of the site prior to discharging to the lawful
       point of discharge, northeast of the site.
External Catchment:

    1. Runoff from the external ground catchment, southwest of the site, will be collected by a
       positive drainage system and directed to the lawful point of discharge, northeast of the
       site.

Refer to Appendix F for the Concept Site Levels and Drainage Plans.

5.3 DRAINS Modelling Assessment
In order to ensure the proposed development will not discharge stormwater runoff greater than
pre-development flow rates, a detailed detention analysis was undertaken to determine what
detention mitigation is required for the proposed development to meet the requirements outlined
in Noosa Shire Council’s planning scheme policy. The IL-CL hydrological model has been used to
calculate the peak discharges from the site under the existing (pre-development) and proposed
(post development) conditions.




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 10

                                                                                       23098 - SBSMP/4
                                                                                               Page 10




5.3.1 Hydraulic Model Parameters
The following parameters were obtained from the ARR DataHUB and have been adopted as part of
the DRAINS IL-CL hydrological modelling:

    1. Impervious area initial loss (mm): 0mm

    2. Impervious area continuing loss (mm/hr): 0mm

    3. Pervious area initial loss (mm): 32mm

    4. Pervious area continuing loss (mm/hr): 2.6mm

5.3.2 Design Storms
As defined in the NSC City Plan Policies and QUDM, the following design storms were adopted:

    1. Minor Drainage System: 10 year ARI statistical flood (Q10 storm);

    2. Major Drainage System: 100 year ARI statistical flood (Q100 storm).

5.3.3 Intensity Frequency Distribution
The BOM data and temporal patterns have been used for the DRAINS modelling and were obtained
for the following coordinates:

    1. Latitude: -26.4181

    2. Longitude: 152.9128

Refer to Appendix G for a copy of the BOM IFD data table.

5.3.4 Pre-Development Model
The pre-development catchment model utilises the following values in Table 5-4. The sub
catchment area taken into account for the pre-development catchment is 0.2275ha. Refer to
Figure 5.1 below for a screenshot of the pre-development model.

               Table 5-4 – Pre-Development Catchment Characteristics for Catchment
                                                                            Remaining
                                              Effective Impervious Area                     Pervious Area
         IL-CL Hydrological Model                                         Impervious Area
                                                         (EIA)                                  (PA)
                                                                               (RIA)
                    Percentage of area (%)                 0                     8               92
Pre-Development
   Catchment         Time of Concentration
                             (mins)
                                                           5                     2               9.7




                                    Figure 5.1 – Pre-Development Model

Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 11

                                                                                             23098 - SBSMP/4
                                                                                                   Page 11




5.3.5 Post-Development Model
The post-development catchment model utilises the following values in Table 5-5. The sub
catchment area taken into account for the post-development catchment is 0.2275ha. Refer to
Figure 5.2 below for a screenshot of the pre-development model.

              Table 5-5 – Post-Development Catchment Characteristics for Catchment
                                                            Effective         Remaining
                                                                                                Pervious Area
              IL-CL Hydrological Model                     Impervious       Impervious Area
                                                                                                    (PA)
                                                            Area (EIA)           (RIA)

 Post-Development
                           Percentage of area (%)                51               25                 24
    Catchment
                       Time of Concentration (mins)              5                 5                  5




                                  Figure 5.2 – Post-Development Model

5.3.6 Post-Development Mitigated Model – On-site Detention Tank
The post-development mitigated catchment model utilises the following values in Table 5-6. The
sub catchment area taken into account for the post-development mitigated roof catchments are
0.0335ha, 0.0214ha, and 0.0258ha, respectively. The sub catchment area taken into account for
the post-development mitigated ground catchment bypassing to the lawful point of discharge is
0.0258ha.

        Table 5-6 – Post-Development Mitigated Catchment Characteristics for Catchment
                                                                               Remaining
                                                Effective Impervious Area                       Pervious Area
          IL-CL Hydrological Model                                             Impervious
                                                           (EIA)                                    (PA)
                                                                                Area (RIA)
Post-Development Percentage of area (%)                    100                      0                 0
Mitigated – Building
                     Time of Concentration
   1 Catchment
                             (mins)
                                                            5                       0                 0

Post-Development Percentage of area (%)                    100                      0                 0
Mitigated – Building
                     Time of Concentration
   2 Catchment
                             (mins)
                                                            5                       0                 0

Post-Development Percentage of area (%)                    100                      0                 0
Mitigated – Building
                     Time of Concentration
   3 Catchment
                             (mins)
                                                            5                       1                 1

 Post-Development     Percentage of area (%)                0                      56                44
   Bypass Ground
                      Time of Concentration
    Catchment
                              (mins)
                                                            0                       5                 5


Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 12

                                                                                23098 - SBSMP/4
                                                                                       Page 12




In order for the post-development stormwater discharge conditions to match the pre-development
conditions, it is proposed to incorporate 10kL above-ground rainwater tanks with a maximum
detention storage volume of 37.5kL. The combined detention/rainwater reuse tanks are to be
located adjacent to the proposed buildings.

The proposed OSD rainwater tanks will have the following properties:

Building 1, 2, & 3:

    •   Specified internal depth = 1.74m;

    •   Low flow orifice diameter = 0.028m;

    •   High flow orifice diameter = 0.140mm;

    •   Detention volume = 7.5kL; and

    •   Tank volume = 2x10kL (7.5kL detention + 2.5kL rainwater reuse) = 20kL

Building 2:

    •   Specified internal depth = 1.74m;

    •   Low flow orifice diameter = 0.028m;

    •   High flow orifice diameter = 0.140mm;

    •   Detention volume = 7.5kL; and

    •   Tank volume = 10kL (7.5kL detention + 2.5kL rainwater reuse)

Building 3:

    •   Specified internal depth = 1.74m;

    •   Low flow orifice diameter = 0.028m;

    •   High flow orifice diameter = 0.140mm;

    •   Detention volume = 7.5kL; and

    •   Tank volume = 2x10kL (7.5kL detention + 2.5kL rainwater reuse) = 20kL

The tanks will be designed to contain all roofwater flows up to a Q100 storm event and mitigate the
outflow at or less than pre-development flows. Stormwater runoff not conveyed to the detention
tanks will sheet flow across the development boundaries in conjunction with the mitigated flows
from the detention tanks at or less than pre-development.

Refer to Appendix F for the Concept Site Levels and Drainage Plan which details the proposed on-
site detention system and Figure 5.3 below for a screenshot of the post-development mitigated
model.




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 13

                                                                                23098 - SBSMP/4
                                                                                       Page 13




                            Figure 5.3 – Post-Development Mitigated Model

5.3.7 Comparison of Peak Flows at Lawful Point of Discharge
The pre-development and post-development mitigated peak flow rates were compared for the
catchment and are shown in Table 5-6 and Table 5-7 below.

                                     Table 5-6 - Comparison of Peak Flows


                 Pre-Development Peak Flows Post-Development Peak Flows Post-Development Peak Flows
Property State          (Un-Mitigated)             (Un-Mitigated)                (Mitigated)
                            (m3/s)                     (m3/s)                      (m3/s)

   50% AEP
    (m3/s)
                            0.035                          0.055                  0.034
   20% AEP
    (m3/s)
                            0.058                          0.084                  0.048

   10% AEP
    (m3/s)
                            0.065                          0.094                  0.056

5% AEP (m3/s)               0.084                          0.110                  0.064

2% AEP (m3/s)               0.102                          0.135                  0.089

1% AEP (m3/s)               0.115                          0.155                  0.087


Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 14

                                                                                  23098 - SBSMP/4
                                                                                          Page 14




The DRAINS IL-CL hydraulic modelling results have demonstrated that the proposed mitigation
implemented will maintain pre-development flows (or less) for all design storms at the LPD located
north of the subject site.

To address the Water Quality and Drainage Code Performance Outcome PO2 design allowance for
climate change impacts, a 20% increase has been incorporated through the Climate change Rainfall
Multiplier function in the DRAINS program to address climate change considerations. This
adjustment is deemed to be an acceptable outcome to address AO2.4. The pre-development and
post-development mitigated with the 20% rainfall intensity increase peak flow rates were compared
for the catchment and are shown in Table 5-8 below.

             Table 5-8 - Comparison of Peak Flows – Inclusion of 20% rainfall intensity increase


                       Pre-Development Peak Flows           Post-Development Peak Flows (Mitigated) +
  Property
                              (Un-Mitigated)                      20% rainfall intensity increase
   State
                                  (m3/s)                                      (m3/s)

  50% AEP
   (m3/s)
                                   0.035                                     0.035
  20% AEP
   (m3/s)
                                   0.058                                     0.050

  10% AEP
   (m3/s)
                                   0.065                                     0.061

  5% AEP
   (m3/s)
                                   0.084                                     0.078
  2% AEP
   (m3/s)
                                   0.102                                     0.098

  1% AEP
   (m3/s)
                                   0.115                                     0.109

The DRAINS IL-CL hydraulic modelling results with the additional 20% rainfall intensity increase have
demonstrated that the proposed mitigation will maintain pre-development flows (or less) for all
design storms at the LPD located north of the subject site.

Refer to Appendix H for the pre-development and post-development DRAINS results and Appendix
I for the post-development mitigated DRAINS results.




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 15

                                                                                       23098 - SBSMP/4
                                                                                                Page 15




6 STORMWATER QUALITY
The following section of the report will outline the potential contaminants and proposed solutions
to be incorporated during the construction and operational phases of the proposed development.

6.1 State Planning Policy Assessment
The purpose of this sub section is to determine if State Planning Policy (SPP 2017) stormwater
quality requirements, as set out by the Department of Environment and Resource Management, will
be triggered for this development. Refer to Table 6-1 for the State Planning Policy Checklist for
stormwater quality.
                                Table 6-1 – State Planning Policy Checklist

                                    Material Change of Use (MCU)                           Y/N?

            MCU for an urban purpose that involves premises ≥ 2500m 2                       N
            AND
            Will result in 6 or more dwellings
                                                                                            Y
            OR
            Will result in impervious area greater than 25% of the net developable area.
                                                                                            Y

The development has been assessed against the latest State Planning Policy 2017 (SPP 2017). The
proposed development will entail the material change of use for urban purposes, which will involve
a land less than 2,500m2. Consequently, State Planning Policy 2017 (SPP 2017) is not triggered.
However, in accordance with Performance Outcome PO6 outlined in the Water Quality and
Drainage Code (Noosa Plan 2020), all stormwater runoff is treated to achieve maximum removal
of nutrients, gross pollutants and suspended solids as determined by cost to efficiency ratios.
Hence, tertiary stormwater quality treatment is warranted for this development in accordance
with the requirements of Noosa Shire Council.

6.2 Construction Phase
Sediment generated during the construction phase shall be dealt with in accordance with an
Erosion and Sediment Control Plan and kept on site during the construction phase.

Erosion and Sediment Control (ESC) Measures such as silt fences, diversion drains, drainage
structure protection and dust control (clearing) will be implemented. Silt fences are to be erected
along the boundary of the site and around the construction area. These fences are to be cleaned
by the contractor when the capacity is reduced by 25%. Where possible, disturbance to the existing
surface is to be limited to the immediate work area. The existing ground cover is not to be stripped
until the contractor is ready for earthworks to begin.

Stockpiles and construction materials are not permitted to be stored within the road reserve and
should be contained using silt fences. Diversion drains are to be provided at upstream catchments
to reduce flows to earthworks areas. In any areas where flows could enter adjacent properties
temporary stabilisation is to be provided.

All ESC measures are to be provided as soon as earthworks have commenced and staged to suit
construction. The contractor is responsible for this action. A temporary construction exit is to be
located at each entry point to the site and will be determined based on the stage of works being
completed. The contractor is to ensure all dust tracked onto surrounding roads is immediately swept
to remove silt/dust.



Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 16

                                                                                        23098 - SBSMP/4
                                                                                                 Page 16




All new stormwater pits are to be protected from sediment infiltration by wrapping new pits and
grates in geofabric or covering appropriately with timber board. Silt fences are to remain in place
during the maintenance period until the site is established (80% ground cover).

Potential sources of contaminants identified for the construction phase of the development are
outlined in Table 6-2 together with proposed stormwater quality improvement devices,
management and maintenance procedures.

                   Table 6-2 - Potential Contaminants and Proposed Treatments

                                                                                 Proposed Treatment
                                                       Management /
     Pollutant           Potential Source                                       Device and Maintenance
                                                   Maintenance Procedures
                                                                                       Procedure
   Sediment &         Excavated material, fill     Provision of sediment and     Sand filled filter socks.
     Eroded             material, exposed           silt barriers to the site      Removal of excess
    material           ground, stockpiles of        drainage entry and exit       sand/silt build-up at
                            material.                        points.              regular intervals and
                                                                                   after every storm.
       Dust           Stockpiles of material,      Covering the material or       Coverage of material
                         exposed ground.             wetting it down at          with plastic, geotextile,
                                                      regular intervals.        surface binding agents or
                                                                                    regular watering.
      Litter           Refuse generated by         Construction waste is to       Industrial bin is to be
                              staff.                be cleaned off the site        provided within the
                                                   area and disposed of into    construction area - to be
                                                     an industrial bin then       emptied on at least a
                                                      removed by a refuse             weekly basis.
                                                     collection contractor.
     Concrete          Washing of concrete         Provision of a closed area   Liquids to be removed by
                      trucks/tools to remove       onsite for washing off of       a waste collection
                      wet/unused concrete.             concrete slurries.        contractor. Solids to be
                                                                                placed into a refuse bin.
    Surfactants      Washing down operations        No cleaning of vehicles     Monitoring & prevention
   (detergents)      on hardstand area using       will be permitted on site.
                           detergents.
    Chemical         Typically this may occur        Where spills occur, the    A temporary containment
     (Paints,           due to spillage of           containment area is to          area. This is to be
  thinners etc.)             product.                   stop escape. The          impermeable and of a
                                                    material is to be treated           size to permit
                                                        (as required) and          mixing/transfer, and
                                                    removed and cleaned by      with a storage volume of
                                                     a licensed contractor.           twice the largest
                                                     Minor spillage outside            container used.
                                                   this area shall be cleaned    Treatment of spills is to
                                                       up with cloths and             occur on site. No
                                                    disposed of to waste via       discharge of treated
                                                       the industrial bin.      water to the stormwater
                                                                                     system is to occur
                                                                                without council approval.
                                                                                    Incidents are to be
                                                                                   reported to the EPA.
   Wastewater            Spillage from the           A licensed contractor         No leakage is to be
                     relocation of the existing    shall remove any residue      permitted to enter the
                      sewerage reticulation.         sewage from unused         groundwater or discharge
                                                   pipes and contaminated          to the stormwater
                                                    soils are to be disposed            system.
                                                   of via the industrial bin.

Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 17

                                                                                         23098 - SBSMP/4
                                                                                                  Page 17




6.3 Operational Phase
Water quality objectives (WQO’s) for South East Queensland as set out in State Planning Policy 2017
(SPP 2017) should be achieved by identifying and adopting best practise techniques in accordance
with the abovementioned guidelines. Refer to Table 6-3 for the target WQO’s.

                           Table 6-3 – Minimum Mean Annual Load Reductions

                                                             Minimum Mean Annual
                                    Contaminant
                                                                Load Reductions

                            Total Suspended Solids (TSS)            ≥ 80%
                               Total Phosphorus (TP)                ≥ 60%
                                Total Nitrogen (TN)                 ≥ 45%
                               Gross Pollutants (GP)                ≥ 90%

6.3.1 Sources of Contaminants
Potential sources of contaminants and stormwater quality improvement devices identified for the
operational phase of the development are outlined in Table 6-4.

                                   Table 6-4 - Sources of Contaminants

                                                 Pollutant
               Target Pollutant Type                             Acceptable Treatment Examples
                                                   Size

         Primary        Screening of gross                     Litter baskets, swales, buffer strips,
                                                 >5000um
        Pollutants          pollutants                            GPT’s, underground detention

                        Sedimentation of
        Secondary                                125um -
                        coarse to medium                       Swales, sedimentation basins, ponds
        Pollutants                               5000um
                            sediment
                                                               Underground detention, constructed
                           Enhanced
                                                  10um –      wetland macrophyte zones, other bio
                      sedimentation of fine
                                                  125um          technologies, proprietary tertiary
                          particulates
                                                                   stormwater treatment dvices
         Tertiary     Adhesion and filtration                Constructed wetland macrophyte zones,
                                                 0.45um –
        Pollutants    of very fine / colloidal                  other bio technologies, proprietary
                                                   10um
                             sediment                         tertiary stormwater treatment dvices
                       Biological uptake of                  Constructed wetland macrophyte zones,
                                                 <0.45um
                        dissolved particles                          other bio technologies




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 18

                                                                                        23098 - SBSMP/4
                                                                                                 Page 18




6.3.2 Proposed Treatment Train
The proposed treatment train has been modelled using the following methodology:

Proposed Development Catchment

    1. Roofwater from the proposed roof catchments will flow via downpipes to above ground
       rainwater tanks for treatment with overflow to an internal drainage network.

    2. Surface runoff from the proposed ground catchment will be directed to an end of line
       bioretention basin for treatment, which is located in the north eastern corner of the site.

All runoff described above will then discharge to the legal point of discharge. The Concept Site
Levels and Drainage Plans of the proposed internal drainage network detailing the treatment train
assets are included in Appendix F. Refer to Table 6-5 for details of the proposed treatment train
assets.

                                Table 6-5 - Proposed Treatment Assets

          Treatment          Treatment
                                                                    Description
            Level              Asset

                           Rainwater Reuse
                                                Total of 12.5kL located adjacent to each proposed
           Primary/       Tanks (Landscape
                                                building, irrigating an area of 627m2 and servicing
          Secondary       Irrigation, Toilets
                                                toilets and laundry for all units.
                             and Laundry)

          Primary/                                •   9m2 Total Filter Area
         Secondary/      Bioretention Basin       •   0.4m Filter Media Depth
          Tertiary                                •   0.1m Extended Detention Depth


Refer to Appendix J for the Stormwater Quality Operational Management and Maintenance
Guidelines.

6.3.3 Pollutant Export Modelling
Following the definition of water quality objectives for the site and an assessment of the treatment
options suitable for the development, the most appropriate treatment scheme for the site was
identified. The impact of the stormwater management strategy on the quality of stormwater runoff
discharged from the site has been assessed using the pollutant export model, Model for Urban
Stormwater Improvement Conceptualisation (MUSIC).

6.3.4 MUSIC Modelling Parameters
The MUSIC model was set up in accordance with the Water-By-Design MUSIC Modelling Guidelines
for South East Queensland to the parameters listed in Table 6-6. Refer to Figure 6.1 for source
node areas in the proposed development area.




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 19

                                                                                         23098 - SBSMP/4
                                                                                               Page 19




                                           Table 6-6 – MUSIC Parameters

                       Parameter                               Data Used

                      Rainfall Data             40059 Cooroy Composite 1973 to 1983

                   Modelling Timestep                          6 minutes

                         Routing                   No routing drain links were adopted


                              Table 6-7 – Catchment Runoff Generation Parameters

                                   Parameter                       Residential Catchment


                              Rainfall Threshold                              1

                         Soil Storage Capacity (mm)                          18

                     Initial Storage Capacity (% capacity)                   10

                             Field Capacity (mm)                             80

                      Infiltration Capacity Coefficient a                   243

                      Infiltration Capacity Coefficient b                    0.6

                              Initial Depth (mm)                             50

                           Daily Recharge Rate (%)                            0

                           Daily Baseflow Rate (%)                           31

                         Daily Deep Seepage Rate (%)                          0


6.3.5 MUSIC Modelling Results
Refer to Figure 6.1 for a print screen schematic of the MUSIC model for the proposed development
and Figure 6.2 for the annual pollutant loads that will be discharged from the site for the proposed
development.




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 20

                                                                               23098 - SBSMP/4
                                                                                       Page 20




                            Figure 6.1 - MUSIC Model Print Screen Schematic




                                   Figure 6.2 - MUSIC Modelling Results

The modelling results show that the pollutant reduction objectives are met for all contaminants
given in Section 6.

Should operational requirements change, this plan is required to be amended to suit. Substantial
changes may require resubmission to the local authority. Following completion of construction, this
plan is to be incorporated into the total-site management practices.




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 21

                                                                                   23098 - SBSMP/4
                                                                                          Page 21




7 FLOODING
Information from the Noosa Shire Council Flood Hazard Overlay Map confirms that the site is
unaffected by flooding and inundation. As the subject site and proposed infrastructure is not in a
tidal/flood risk area, it is expected that the 800mm to allow for sea level rise is irrelevant in this
instance.

Refer to Appendix K for the NSC Flood Planning Control Property Report.




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 22

                                                                              23098 - SBSMP/4
                                                                                     Page 22




8 CONCLUSION
The Proposed Townhouse Development at 5 Pearl Street, Cooroy has been assessed for its impact
on the quantity and quality of stormwater drainage.

The lawful point of discharge is the existing Environmental Management and Conservation Area,
northeast of the site.

On-site detention (OSD) is warranted for the proposed development. The Water Quality and
Drainage Code Performance Outcome PO2 design allowance for climate change impacts has also
been addressed.

Sediment generated during the construction phase shall be dealt with in accordance with an
Erosion and Sediment Control Plan to be kept on site during the construction phase.

The proposed development requires tertiary stormwater quality treatment in accordance with the
requirements of Noosa Shire Council. Rainwater reuse and bioretention end-of-line treatment will
be incorporated into the proposed development to meet the prescribed water quality objectives.

The subject site is unaffected by flooding.




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 23

                                                            23098 - SBSMP/4
                                                                  Page 23




                                             APPENDIX A


                                     DETAILED SITE SURVEY




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 24

Skyline Surveyors
Suite 11C
Brightwater Corporate Centre   PHONE
                               07 5493 4877
69 Attenuata Drive
MOUNTAIN CREEK QLD 4557
E: [email protected]
W: www.skysurv.com.au

Page 25

                                                           23098 - SBSMP/4
                                                                 Page 24




                                             APPENDIX B


                            PROPOSED DEVELOPMENT PLANS




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 26

 

 

 

 

 

 

 

 

 

 

 
 
 

 

 

 

 

 

 

 

 

 

 

 

   

 

 

 

 

       

   
 
 

  

 

 

 

 

 

 

  

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

 

 

 

 

 

 

 

   
   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  

 

  
  

 

 

 

 

 

   

 

 

 

 

 

 
   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

 

 

 

 

 

 

 

  

   
  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
 
 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

     
  
     
   

 

 

 

 

 

 

  

 

 

 

 

 

 

 

 

   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
   

 

 

 

 

 

  
  
   
      

 

  

 

 

     
 

 

 

 

 
   

 

 

 

 

  

 

 

 

 

 

 

 

 

 

 

 

 

 

  
    

 

 

 

 

 

 

 

 

 

 

 

   
 

 

 

 

 

 

 

 

 

 

 

    

 

 

 

 

& & & § & & & § £
z 2 8 am © arte VAN 3 8 é 8 Ln
v oF T
r 5 = 7 , FT
‘ ‘ : . ' ! f S
q Do i : ' NON SETRACK
: Q 4 ae —Tt tam? .
We H 109m! H nA ! na oo J oon TERRACE 1 *y
\ 5 : \ i ' Wo Wo
\ a a ios po.) 00 fe som PE ed eae
rN % tI
g ;
FB ——
" wn in
. 3 7
“Ts aWT s hot | |
\ KITCHEN,
fy , LY see, oh —
K 1/8 IY 7 BE =a i.
\ ‘| . . ; [Lov LY | 33
uw = is i. ag. |e Hy *\ KITCHEN S| KITCHEN KITCHEN OF i al TF] Ok
ies gt * | EN Pes TEI ES It, a
jé @ H ud J by = \
be Q \ wNA GARAGE ‘ GARAGE BaRAGE ) GARAGE | Ba GARAGE ‘
(A = ir b ‘U0 uo2 uo3 ‘U04 u05 uos. |E U07 U08 ~
me = fe ‘. TYPEO1 TYPE02 TYPEO2 "TYPEO2 TYPEO2 TYPEO2, TYPEO2 TYPE03
5 Exe GARAGE i ‘| '
sal | 4
= \ | :
4 :
om ‘ J ‘ it
| te |v : 108.4m
| mc? Pj NE EES] ST ee ie
I 100» 2500 _|soap *y. \ ee 1120 1000)
! yy un . *, BUILDING 01 . ' 1 7-~--_ |: BUILDING 02 ~~ -----_
| \ Ope Ts 6520 12506 5270 S250 ey S770 s 250y ye S770 250) S770 Oye u ye 270 250 jy¢[ > ~ ~ 527 2506 6520 oye ~ PF -|
| ! . a tf bf —y 4 oF a a + ee Ht
| f z, +4— “ 7 28780 , # 5180 — oe n 17740 == — ~~ SEWER = +
| s- gy ig . \ . ad’ ‘ g OTT gael Tape
& | . 7 3 ‘ + 5 . #1 sto tase ra =
= : : | soy. S200 py 5210 2s0py sz Opp rr = sy 2 .
; : / ! +e} et oF 34 IIs
\ —+——————_4 fo : BUILDING 03... | * sg
‘ : /| | ‘ |
x ; Ty) g
€ € aT 7om € TeDOr ' QT § & | 7 8
5 5 s 3 3 3 | J aw
| 4
tek
106.2m | me
| +e
| HoT
| 105.6m
|
g |
| u09 U10 .
yl TYPEO2 TYPE02 U12
gl GARAGE GARAGE TYPEQ2 TYPE02
4 a 3 g Eo GARAGE GARAGE cf
" KITCHEN q 4
|
106.4 DEVELOPMENT,
nen \ oe
; Feerace | :
Ww TMBER x Bhfenrace [1 150m *
ere 6.6m od wssm  ' ALTUM
BLOCK BALUSTERS. /
fi
1
—— os 1 FLOOR PLAN - LEVEL 1
4000 SETBACK ~~ . /
° H \ \ !
ERMINATES INTO 1800 o ' . ‘ : Development Approval
Fi ‘ aN A . / north scale: 1:100 @A1
ws - 1x 1100L RECYCLING ‘ SN / scale: 1:200 @A3
= 1x 1100L GENERAL WASTE ec ee ‘ ' issue: 05
date: 13-03-24

 

 
 
   

7283-DA04

__Project Number

 

 

TREE

” BUCKBURNEJICKSON

01 FLOOR PLAN LEVEL 1

1:100 Trees

 

 

ARCHITECTURE | LANDSCAPE | INTERIOR | PROJECT MANAGEMENT

 

inte property a Blackbure Jackson Design Py

Page 27

                                                            23098 - SBSMP/4
                                                                  Page 25




                                             APPENDIX C


                            NSC INTERACTIVE MAPPING PLANS




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 28

Noosa Shire Council does not warrant the accuracy of information in this publication and any person using or relying
upon such information does so on the basis that Noosa Shire Council shall bear no responsibility or liability          20/09/2023

Page 29

                                                           23098 - SBSMP/4
                                                                 Page 26




                                             APPENDIX D


                      NSC WATER QUALITY AND DRAINAGE CODE




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 30

Water Quality and Drainage Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: 2020

Performance Outcomes                              Acceptable Outcomes                                    Solution1                     Comments                                      Council Use

Stormwater Drainage Design
PO1                                               AO1                                                                  RO1
The development and its stormwater                A stormwater management plan is prepared                             The proposal complies. Refer to the
management system is planned and                  consistent with PSP6 Engineering Design                              Site Based Stormwater Management
designed having regard to:                        Standards - Roads, drainage and earthworks.                          Plan (SBSMP) report prepared by
 (a) the natural features of the site;                                                                                 MCE.
 (b) the need to avoid impacts and potential
     risks to ecologically important areas;
 (c) the likely effectiveness of erosion and
     sediment control and stormwater                                                                         ✓
     drainage measures during rainfall
     events during and post construction;
     and
 (d) the need to protect environmental
     values and water quality of receiving
     waters both during and post
     construction
PO2                                               AO2.1                                                                RO2.1
Stormwater drainage infrastructure is             Stormwater drainage planning, design and                             The proposal complies. All stormwater
planned, designed and                             construction is in accordance with PSP6                              design will comply with the PSP6
                                                                                                                       Engineering Design Standards –
constructed to:
 (a) incorporate allowance for increased
                                                  Engineering Design Standards - Roads,
                                                  drainage and earthworks and the latest version
                                                                                                             ✓         Roads, drainage and earthworks and
     flood risk and tidal inundation through      of the Queensland Urban Drainage Design                              the latest version of the Queensland
     pipework as a result of cilmate change       Manual.                                                              Urban Drainage Design Manual.
     and sea level rise;                          AO2.2                                                                RO2.2
 (b) ensure the development is adequately         The stormwater drainage system connects to a                         Refer to the SBSMP prepared by
     drained; and                                 lawful point of discharge in accordance with               ✓         MCE for the lawful point of discharge.
 (c) ensure stormwater is managed and             PSP6 Engineering Design Standards - Roads,
     lawfully discharged without altering         drainage and earthworks
     stormwater drainage characteristics          AO2.3                                                                RO2.3
     external to the site.                        Stormwater flows discharging from the                                The proposal complies. Above ground
                                                  development are demonstrated to be                         ✓         detention tanks will be utilised to
                                                  consistent with pre-development                                      mitigate flows prior to discharge to the
                                                  characteristics.                                                     legal point of discharge. Refer to the
                                                                                                                       SBSMP prepared by MCE.


1
    Solution:   ✓     Acceptable Solution                                                                                                                                                       Page 1 of 10
                A/S   Alternative Solution                        \\mcedc01\DATA\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\SBSMP\Working\Appendices\NSC Water Quality and Drainage Code 2020.docx
                N/A   Not applicable to this proposal                                                                                                                                                  Job: 23098
                                                                                                                                                                                                      Rev:      1
Site Address: 5 Pearl Street, Cooroy                                                                                                                                                                18/03/2024

Page 31

Water Quality and Drainage Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: 2020

Performance Outcomes                               Acceptable Outcomes                                     Solution1                     Comments                                      Council Use

                                                   AO2.4                                                                 RO2.4
                                                   Development provides for the management of                            The proposal complies. The
                                                   stormwater to incorporate appropriate                                 development provides for the
                                                   allowance for climate change impacts
                                                   (including rainfall intensity and sea level rise),
                                                                                                               ✓         management of stormwater to
                                                                                                                         incorporate appropriate allowance for
                                                   in accordance with PSP6 Engineering Design                            climate change impacts in accordance
                                                   Standards – Roads, Drainage and Earthworks.                           with PSP6. Refer to the SBSMP
                                                                                                                         prepared by MCE.
PO3                                                AO3.1
Stormwater drainage infrastructure conveys         Stormwater drainage infrastructure meets the
run-off in a manner that allows roads to           desired standards of service for roads
deliver desired standards of service               functionality set out in PSP6 Engineering                  N/A
appropriate to the local conditions and local      Design Standards - Roads, Drainage and
stormwater drainage characteristics.               Earthworks.
PO4                                                AO4.1                                                                 RO4.1
Stormwater infrastructure is compatible with       The location, design and construction of                              Refer to RO2.1.
existing infrastructure, allows for easy           stormwater drainage structures is in
access for the ongoing maintenance by
Council, is cost effective across its design
                                                   accordance with PSP6 Engineering Design
                                                   Standards - Roads, drainage and earthworks.
                                                                                                               ✓
life
                                                   AO4.2
                                                   Where infrastructure is located on private land
                                                   an easement is dedicated over the
                                                   infrastructure in accordance with PSP6                     N/A
                                                   Engineering Design Standards - Roads,
                                                   drainage and earthworks.
                                                   AO4.3                                                                 RO4.3
                                                   Any alterations or repairs to infrastructure as a                     The proposal complies.
                                                   result of the development are made at no cost               ✓
                                                   to Council.
                                                   AO4.4                                                                 RO4.4
                                                   Development avoids stormwater inflow and                              The proposal complies. Stormwater
                                                   infiltration to the sewer infrastructure network.           ✓         will be designed to avoid inflow and
                                                                                                                         infiltration into the sewer infrastructure
                                                                                                                         network.


1
    Solution:   ✓      Acceptable Solution                                                                                                                                                        Page 2 of 10
                A/S    Alternative Solution                         \\mcedc01\DATA\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\SBSMP\Working\Appendices\NSC Water Quality and Drainage Code 2020.docx
                N/A    Not applicable to this proposal                                                                                                                                                   Job: 23098
                                                                                                                                                                                                        Rev:      1
Site Address: 5 Pearl Street, Cooroy                                                                                                                                                                  18/03/2024

Page 32

Water Quality and Drainage Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: 2020

Performance Outcomes                               Acceptable Outcomes                                    Solution1                     Comments                                      Council Use

                                                   AO4.5                                                                RO4.5
                                                   Stormwater infrastructure is designed to                             The proposal complies.
                                                   minimise maintenance costs and the                         ✓
                                                   requirement for specialized equipment for
                                                   maintenance techniques.
PO5                                                AO5.1
Stormwater drainage infrastructure is              Stormwater drainage infrastructure avoids
aligned to avoid crossing waterways,               crossing waterways, wetlands drainage lines               N/A
wetlands, drainage lines and ecological            and ecologically important areas or follows the
important areas, or where it is demonstrated       edge of existing disturbed areas.
this is unavoidable, disturbed areas are           AO5.2
reinstated and revegetated upon completion         Stormwater drainage infrastructure avoids
of works.                                          crossing waterways, wetlands drainage lines               N/A
                                                   and ecologically important areas or follows the
                                                   edge of existing disturbed areas.
                                                   AO5.3
                                                   Temporary vehicular crossings of waterways
                                                   must be designed and constructed to be                    N/A
                                                   consistent with the current International
                                                   Erosion Control Association Best Practice
                                                   Book Series.
Stormwater quality and protection of receiving waters
PO6                                                AO6.1                                                                RO6.1
Development is located, designed,                  Stormwater runoff discharging into High                              The proposal complies.
constructed and operated to protect and            Ecological Value waters as a result of
enhance environmental values and water
quality of waterways, wetlands, lakes,
                                                   development causes no increase in gross
                                                   pollutants, total suspended solids, total
                                                                                                              ✓
ground waters and drainage systems.                phosphorous or total nitrogen compared to
                                                   a pre-development scenario.
Editor’s note: Environmental values of
waters and water quality objectives are            AND
prescribed in Schedule 1 of the                    AO6.2                                                                RO6.2
Environmental Protection (Water) Policy            All stormwater runoff is treated to achieve                          The proposal complies. A bio-
2009 and are identified on the State               maximum removal of nutrients, gross                                  retention system will be incorporated
Planning Policy Interactive Mapping System         pollutants and suspended solids as determined                        into the drainage design to achieve

1
    Solution:   ✓      Acceptable Solution                                                                                                                                                       Page 3 of 10
                A/S    Alternative Solution                        \\mcedc01\DATA\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\SBSMP\Working\Appendices\NSC Water Quality and Drainage Code 2020.docx
                N/A    Not applicable to this proposal                                                                                                                                                  Job: 23098
                                                                                                                                                                                                       Rev:      1
Site Address: 5 Pearl Street, Cooroy                                                                                                                                                                 18/03/2024

Page 33

Water Quality and Drainage Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: 2020

Performance Outcomes                               Acceptable Outcomes                                     Solution1                     Comments                                      Council Use

                                                   by cost to efficiency ratios. (e.g. bioretention                      the target pollutant reduction loads.
                                                   basins must be sized to                                               Refer to the SBSMP prepared by
                                                   achieve at least 80% reduction in total                               MCE.
                                                   suspended solids, 60% reduction in total
                                                   phosphorous, 45% reduction in total nitrogen
                                                                                                               ✓
                                                   and 90% reduction in gross pollutants >5mm)

                                                   OR
                                                   AO6.3
                                                   Developments achieve a minimum 3 drop
                                                   rating consistent with the Water by Design
                                                   Living Waterways Scoring Guide (Healthy
                                                   Land and Water).

                                                   Editor’s note— PSP6 Engineering Design                     N/A
                                                   Standards - Roads, Drainage and Earthworks
                                                   provides guidance on stormwater design and
                                                   modelling requirements

PO7                                                AO7.1                                                                 RO7.1
Water quality treatment systems use natural        Water quality treatment systems are designed                          The proposal complies.
processes and                                      to be integrated into the landscape consistent
materials, whenever possible, and are              with the technical design guideline published
integrated into development                        by Healthy Land and Water Water by Design
to enhance biodiversity and landscape              for the                                                     ✓
benefits                                           feature. (eg. For Bioretention Basins:
                                                   Bioretention Technical Design Guidelines
                                                   (October 2014) and for Wetland Systems the
                                                   Wetland Technical Design Guideline (May
                                                   2017).
PO8                                                AO8.1
Water quality treatment infrastructure to be       Detailed life cycle costing is provided for the
                                                                                                              N/A
dedicated as public assets are proven to be        entire treatment train system including
suitable for its use and of a cost                 replacement costs of asset parts.
effective and efficient standard                   AO8.2
                                                   Treatment systems dedicated as public assets

1
    Solution:   ✓      Acceptable Solution                                                                                                                                                        Page 4 of 10
                A/S    Alternative Solution                         \\mcedc01\DATA\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\SBSMP\Working\Appendices\NSC Water Quality and Drainage Code 2020.docx
                N/A    Not applicable to this proposal                                                                                                                                                   Job: 23098
                                                                                                                                                                                                        Rev:      1
Site Address: 5 Pearl Street, Cooroy                                                                                                                                                                  18/03/2024

Page 34

Water Quality and Drainage Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: 2020

Performance Outcomes                               Acceptable Outcomes                                    Solution1                     Comments                                      Council Use

                                                   are designed to minimise maintenance,
                                                   renewal and adaption costs and the
                                                                                                             N/A
                                                   requirement for specialised equipment,
                                                   material or maintenance
                                                   techniques.
                                                   AO8.3
                                                   Vegetated stormwater management systems
                                                   to be dedicated as public assets are
                                                   established and maintained during the
                                                   maintenance period to ensure optimal                      N/A
                                                   vegetated growth and that the functional
                                                   elements of the system achieve the design
                                                   function at the end of the maintenance period.
PO9                                                AO9.1                                                                RO9.1
Treatment systems are designed to                  Free draining inlets and outlets are provided to                     The proposal complies. The proposal
eliminate or minimise health, safety and           ensure that waters do not pond for more than               ✓         stormwater treatment system will be
aesthetic hazards, including risks associated      24 hours.                                                            designed to be free draining.
with insect breeding, odour and public             AO9.2                                                                RO9.2
safety.                                            Developments are designed to eliminate                               The proposal complies. Retaining
                                                   retaining walls in excess of 0.8m for any water            ✓         walls do not exceed 0.8m.
                                                   quality treatment device.
Hydraulic and Waterway Stability
PO10                                               AO10                                                                 RO10
Development prevents increased bed and             The development is designed to:                                      The proposal complies. Refer to the
bank erosion and                                  (a) limit the peak 1 year ARI event discharge                         SBSMP prepared by MCE.
sedimentation in receiving waterways by               within the receiving waterway to the pre-
avoiding changes in low                               development peak 1 year discharge;
rate, peak flow run-off and flow duration.        (b) maximise pervious areas by using
                                                      pervious alternatives for otherwise
                                                      impervious areas wherever possible;
                                                  (c) provide for capture and reuse of
                                                      stormwater for non-potable purposes for
                                                      gardening, toilet flushing, laundry and hot
                                                      water supply uses;                                      ✓
                                                  (d) incorporate appropriate detention features;

1
    Solution:   ✓      Acceptable Solution                                                                                                                                                       Page 5 of 10
                A/S    Alternative Solution                        \\mcedc01\DATA\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\SBSMP\Working\Appendices\NSC Water Quality and Drainage Code 2020.docx
                N/A    Not applicable to this proposal                                                                                                                                                  Job: 23098
                                                                                                                                                                                                       Rev:      1
Site Address: 5 Pearl Street, Cooroy                                                                                                                                                                 18/03/2024

Page 35

Water Quality and Drainage Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: 2020

Performance Outcomes                              Acceptable Outcomes                                    Solution1                     Comments                                      Council Use

                                                     and
                                                 (e) incorporate natural channel design
                                                     principles.

                                                  Editor’s note: The Sustainable Building
                                                  Design Code includes requirements for
                                                  stormwater capture and reuse.
PO11                                              AO11.1
Water sensitive urban design principles are       The design and construction of a natural
applied to achieve multifunctional design of      channel or natural channel rehabilitation works
waterways, wetlands and drainage lines that       are in accordance with the Natural Channel                N/A
provide for:                                      Design Guidelines (Brisbane City Council)
 (a) stormwater conveyance that uses              having regard to local topography, geology and
     natural channel design;                      geomorphology.
 (b) protection of landscape features and         AO11.2
     ecological important areas including         Landscape features, plant species and habitat
     terrestrial and aquatic habitat;             types used in stormwater conveyance                       N/A
 (c) aesthetic and passive recreation             channels are complementary to the local
     values;                                      context and natural waterways
 (d) flood management and conveyance of           AO11.3
     external catchment stormwater through        Bank and bed stability and planting densities
     the development;                             result in a stable channel over the long term             N/A
 (e) landscaping that incorporates local          and minimal potential for pest plant species.
     native species; and
                                                  AO11.4
 (f) bed and bank stability
                                                  Water Sensitive Design measures are
                                                  incorporated into the development, as detailed
                                                  in the document Water Sensitive Designs
                                                  small improvements, new ideas, concepts and               N/A
                                                  sketch designs for stormwater filtration
                                                  systems (Healthy Waterways Water by
                                                  Design).
                                                  AO11.5
                                                  Floodplain management is designed in
                                                  accordance with the Framework for the
                                                  Integration of Flood and Stormwater                       N/A
                                                  Management into Open Space published by

1
    Solution:   ✓     Acceptable Solution                                                                                                                                                       Page 6 of 10
                A/S   Alternative Solution                        \\mcedc01\DATA\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\SBSMP\Working\Appendices\NSC Water Quality and Drainage Code 2020.docx
                N/A   Not applicable to this proposal                                                                                                                                                  Job: 23098
                                                                                                                                                                                                      Rev:      1
Site Address: 5 Pearl Street, Cooroy                                                                                                                                                                18/03/2024

Page 36

Water Quality and Drainage Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: 2020

Performance Outcomes                              Acceptable Outcomes                                    Solution1                     Comments                                      Council Use

                                                  Healthy Waterways Water by Design (version
                                                  current at the time of development
                                                  application).
PO12                                              AO12.1
Development protects in-stream ecology by         Where run-off from or within the site passes
maintaining pre development low flow              through or drains to natural channels,
discharge regimes and maintaining fish            waterways or wetlands, development protects
passages.                                         in steam ecology by maintaining pre-
                                                  development low flow discharge regimes in                 N/A
                                                  accordance with the frequent flow
                                                  management objectives in PSP6 Engineering
                                                  Design Standards - Roads, drainage and
                                                  earthworks
                                                  AO12.2
                                                  Instream structures such as roads, bridges,
                                                  culverts, and other stormwater infrastructure             N/A
                                                  do not cause barriers to fish passage and
                                                  facilitate the movement of terrestrial and
                                                  aquatic fauna along waterway corridors
                                                  AO12.3
                                                  Benthic substrate retains a continuous grade
                                                  with the direction of flow consistent with the            N/A
                                                  natural bed profile.
PO13                                              AO13.1
Development is designed and constructed to        The location and form of stormwater discharge
maintain surface and ground water balances        points do not alter the pre-development                   N/A
that sustain the environmental values of          hydrology of receiving surface water or
water dependent ecosystems, including             groundwater.
downstream aquatic, riparian, wetland and         AO13.2
terrestrial ecosystems.                           Developments located on groundwater
                                                  recharge or discharge areas are designed and
                                                  managed in accordance with a groundwater
                                                  recharge and discharge management plan
                                                  prepared by a suitably
                                                  experienced and qualified groundwater
                                                  hydrologist. The groundwater recharge or

1
    Solution:   ✓     Acceptable Solution                                                                                                                                                       Page 7 of 10
                A/S   Alternative Solution                        \\mcedc01\DATA\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\SBSMP\Working\Appendices\NSC Water Quality and Drainage Code 2020.docx
                N/A   Not applicable to this proposal                                                                                                                                                  Job: 23098
                                                                                                                                                                                                      Rev:      1
Site Address: 5 Pearl Street, Cooroy                                                                                                                                                                18/03/2024

Page 37

Water Quality and Drainage Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: 2020

Performance Outcomes                               Acceptable Outcomes                                    Solution1                     Comments                                      Council Use

                                                   discharge must demonstrate that the                       N/A
                                                   development does not affect groundwater
                                                   balances beyond the property boundaries

                                                   Editor's Note— PSP6 Engineering Design
                                                   Standards - Roads, drainage and earthworks
                                                   provides guidance on prepare a groundwater
                                                   recharge and discharge plan.
Construction and establishment of stormwater management systems
PO14                                               AO14.1                                                               RO14.1
Construction methods provide for                   An erosion and sediment control plan prepared                        An Erosion and Sedimentation Control
appropriate controls to avoid entry and            in accordance with the International Erosion                         Plan shall be prepared (prior to
transport of litter, sediment, and associated      Control Association Best Practice Books                              commencement of construction) and
prescribed water contaminants into receiving       demonstrates that the capture and release of                         maintained for the management of the
waters.                                            stormwater achieves the design objectives                            sediment laden stormwater during the
                                                   listed in Table A: Construction phase –                              construction phase in accordance with
Editor's note— Water contaminants are              stormwater management design objectives                              IECAs Best Practice guidelines.
prescribed in the                                  of the State Planning Policy (Appendix 2).                 ✓
Environmental Protection Act 1994
                                                   Editor’s note— PSP6 Engineering Design
                                                   Standards - Roads, drainage and earthworks
                                                   provides guidance on requirements for
                                                   preparing an Erosion Management Plan.
                                                   AO14.2                                                               RO14.2
                                                   Construction works are designed and                                  Unnecessary disturbance to soil shall
                                                   managed to restrict the extent of clearing and                       be avoided and soil surfaces shall
                                                   soil exposure to the minimum necessary for
                                                   access, and safe construction at any one time
                                                                                                              ✓         remain stabilized.


                                                   AO14.3                                                               RO14.3
                                                   For buildings:                                                       The proposal complies. Refer to
                                                  (a) upstream runoff is diverted around the                            RO14.1.
                                                       construction site;
                                                  (b) sediment barriers are provided downslope
                                                       of disturbed areas to prevent sediment
                                                       washing into gutters, drains and

1
    Solution:   ✓      Acceptable Solution                                                                                                                                                       Page 8 of 10
                A/S    Alternative Solution                        \\mcedc01\DATA\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\SBSMP\Working\Appendices\NSC Water Quality and Drainage Code 2020.docx
                N/A    Not applicable to this proposal                                                                                                                                                  Job: 23098
                                                                                                                                                                                                       Rev:      1
Site Address: 5 Pearl Street, Cooroy                                                                                                                                                                 18/03/2024

Page 38

Water Quality and Drainage Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: 2020

Performance Outcomes                              Acceptable Outcomes                                   Solution1                     Comments                                      Council Use

                                                      waterways , wetlands or drainage lines
                                                      either on or off the site; and
                                                 (c) temporary or permanent downpipes are                   ✓
                                                      connected to the stormwater system
                                                      before laying the roof; or
                                                 (d) localised erosion is avoided by directing
                                                      flow from downpipes over non-erosive
                                                      areas.
                                                  AO14.4                                                              RO14.4
                                                  Chemical flocculants used as part of an                             The proposal complies. Refer to
                                                  erosion and sediment control plan do not harm             ✓         RO14.1.
                                                  the environmental values within receiving
                                                  waters.
                                                  AO14.5                                                              RO14.4
                                                  Appropriately sized litter containment areas,                       The proposal complies. Refer to
                                                  with provision for sorting recyclables are                ✓         RO14.1.
                                                  provided for the type of litter expected to be
                                                  generated onsite.
Wastewater management and effluent disposal
PO15                                              AO15
Development does not discharge                    Wastewater (non-sewage) generated from the
wastewater unless it can be demonstrated to       development is collected and contained on-
not compromise environmental values of            site, and is;
waters and water quality objectives.             (a) lawfully disposed to sewer; or
                                                 (b) transferred off-site for treatment/disposal
Editor’s Note—Environmental values of                  to an appropriately
waters and water quality objectives are                licenced facility;
prescribed in Schedule 1 of the                  (c) reused on-site in a closed-cycle irrigation
Environmental Protection (Water) Policy                scheme, industrial processes, washing or
2009.                                                  cleaning or other purpose; or                       N/A
                                                 (d) treated to meet the drinking water supply
                                                       environmental values prior to release.

                                                  Editor’s Note—The Plumbing and Drainage
                                                  Act 2003 sets out requirements for wastewater

1
    Solution:   ✓     Acceptable Solution                                                                                                                                                      Page 9 of 10
                A/S   Alternative Solution                       \\mcedc01\DATA\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\SBSMP\Working\Appendices\NSC Water Quality and Drainage Code 2020.docx
                N/A   Not applicable to this proposal                                                                                                                                                 Job: 23098
                                                                                                                                                                                                     Rev:      1
Site Address: 5 Pearl Street, Cooroy                                                                                                                                                               18/03/2024

Page 39

Water Quality and Drainage Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: 2020

Performance Outcomes                              Acceptable Outcomes                                     Solution1                     Comments                                      Council Use

                                                  management.

PO16                                              AO16
On-site effluent treatment and disposal           An onsite effluent system and disposal area is:
systems are designed, constructed and            (a) not located on a slope greater than 1 in
managed to not compromise the                         (10%);
environmental values of waters and water         (b) not located at or below the 1% annual
quality objectives.                                   exceedance probability (AEP flood event);
                                                 (c) not located within a riparian buffer area
                                                      mapped on a Biodiversity, Waterways and
                                                      Wetlands Overlay Map; and
                                                 (d) setback 400 metres minimum from the full
                                                      supply level of Lake Macdonald.

                                                  Editor’s Note—The Plumbing and Drainage
                                                  Act 2003 sets out requirements for on-site                 N/A
                                                  effluent treatment and disposal. The
                                                  Queensland Plumbing and Wastewater Code
                                                  and associated
                                                  guidelines are used to confirm the suitability of
                                                  each site to accommodate an on-site
                                                  sewerage facility; or where a centrally located
                                                  group collection treatment system is proposed,
                                                  confirmation as to the suitability of the
                                                  designated site to accommodate the onsite
                                                  sewerage facility. Additionally, where the
                                                  combined total peak design capacity of effluent
                                                  treatment is less than 21 equivalent persons,
                                                  the design of the system achieves a low to
                                                  medium risk classification in accordance with
                                                  Seqwater’s Land Use Risk Tool for onsite
                                                  sewerage facilities




1
    Solution:   ✓     Acceptable Solution                                                                                                                                                       Page 10 of 10
                A/S   Alternative Solution                         \\mcedc01\DATA\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\SBSMP\Working\Appendices\NSC Water Quality and Drainage Code 2020.docx
                N/A   Not applicable to this proposal                                                                                                                                                   Job: 23098
                                                                                                                                                                                                       Rev:      1
Site Address: 5 Pearl Street, Cooroy                                                                                                                                                                 18/03/2024

Page 40

                                                           23098 - SBSMP/4
                                                                 Page 27




                                             APPENDIX E


                           RATIONAL METHOD CALCULATIONS




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 41

                                                            Rational Method Peak Flow Calculations
Job No:            23098                                                                                                                                                    MORGAN CONSULTING
Job Type:          Proposed Townhouse Development                                                                                                                            ENGINEERS PTY LTD
Address:           5 Pearl Street, Cooroy                                                                                                                                1 GREAT GEORGE STREET
Council:           NSC                                                                                                                                                     PADDINGTON QLD 4064


IFD Data:          26.4125 (S),152.9125 (E)                               Minor Storm:      Q10                                                                             Designed:          WB
1
I10                70mm/hr                                                Major Storm:     Q100                                                                                 Checked:       HM

Pre Development                                                                                        Post Development

Time of Concentration

Standard Inlet Time                                                                                    Standard Inlet Time
     Standard Inlet Time                          mins                                                        Standard Inlet Time               5   mins

Sheet Flow (Friends Equation)                                                                          Sheet Flow (Friends Equation)
    Sheet flow length (L)                   57      m                                                        Sheet flow length (L)                    m
           roughness (n)                  0.03             short grass                                             roughness (n)     0.014                  Concrete
              Fall of NSL                 1.89     m                                                                  Fall of NSL     0.29           m
     Slope of Surface (S)                  3.3     %                                                         Slope of Surface (S)                    %
                      total                9.7    mins                                                                        total    0.0          mins
Concentrated Overland Flow                                                                             Concentrated Overland Flow
           Flow distance                      0    m                                                               Flow distance                     m
                 velocity                   0.7   m/s                                                                    velocity            0.7    m/s
                    mins                    0.0   mins                                                                      mins             0.0    mins
   Surface type multiplier                  3.0                                                            Surface type multiplier           4.0
                     total                  0.0   mins                                                                       total           0.0    mins

Total tc                                    9.7   mins                                                                  Total tc             5.0    mins



Runoff Volume Calculations


      Name          Area (ha)        tc              fi     C10                                            Name          Area (ha)      tc             fi    C10
                     0.228                         0.27     0.75                                                          0.228                      0.76    0.85

           Total      0.228         9.7                     0.75                                                Total      0.228       5.0                   0.85

                   Frequency                                                                                            Frequency
      ARI                            Cy             Iy                     Qy                               ARI                         Cy            Iy                 Qy
                     Factor                                A (Ha)                                                         Factor                           A (Ha)
    (years)                       (Fy*C10)        (mm/h)                 (m3/s)                           (years)                    (Fy*C10)       (mm/h)             (m3/s)
                      (Fy)                                                                                                 (Fy)
      3 mth                                                              0.019                             3 mth                                                       0.026
        1             0.800        0.603           99       0.228        0.038                               1             0.800      0.682          120    0.228      0.052
        2             0.850        0.641           111      0.228        0.045                               2             0.850      0.724          135    0.228      0.062
        5             0.950        0.716           150      0.228        0.068                               5             0.950      0.809          183    0.228      0.094
       10             1.000        0.754           174      0.228        0.083                              10             1.000      0.852          215    0.228      0.116
       20             1.050        0.792           199      0.228        0.099                              20             1.050      0.895          245    0.228      0.139
       50             1.150        0.867           228      0.228        0.125                              50             1.150      0.980          285    0.228      0.176
       100            1.200        0.905           251      0.228        0.143                              100            1.200      1.000          315    0.228      0.199




                                                                                         Page 1 of 1                                                                                       14/05/2024

Page 42

                                                           23098 - SBSMP/4
                                                                 Page 28




                                             APPENDIX F


                   CONCEPT SITE LEVELS AND DRAINAGE PLAN




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 43

                          P:             (07) 3369 8411
                          F:             (07) 3369 1893
                          E : [email protected]
                          © Morgan Consulting Engineers
                          This drawing is not to be copied,
                          reta ined o r used wi tho ut the
                          permission of the copyright holder.


1 GREAT GEORGE STREET
PADDINGTON Q LD 4 0 6 4

Page 44

                                                            23098 - SBSMP/4
                                                                  Page 29




                                             Appendix G


                                                  BOM IFD




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 45

Copyright Commonwealth of Australia 2016 Bureau of Meteorology (ABN 92 637 533 532)

IFD Design Rainfall Intensity (mm/h)
29-Aug-23

Issued:

Location La5 Pearl Stre Cooroy
Requested Latitude
Nearest gri Latitude

Duration
1 min

2 min

3 min

4 min

5 min

10 min
15 min
20 min
25 min
30 min
45 min

1 hour
1.5 hour
2 hour

3 hour
4.5 hour
6 hour

9 hour
12 hour
18 hour
24 hour
30 hour
36 hour
48 hour
72 hour
96 hour
120 hour
144 hour
168 hour

Duration in

UO BWN PR

10
15
20
25
30
45
60
90
120
180
270
360
540
720
1080
1440
1800
2160
2880
4320
5760
7200
8640

10080

63.20%
165
141
132
126
120

97.3
82.3
71.8

64

58

46
38.7
30.2
25.3
19.8
15.4

13
10.2
8.54
6.63
5.51
4.75
4.19
3.42
2.53
2.04
1.71
1.49
1.33

-26.4181 Longitude
26.4125 (S)Longitude 152.9125 (E)

50%
186
159
149
142
135
110

92.9

81

72.2

65.4

51.9

43.8

34.3

28.8

22.6

17.7

15

11.8

9.95

7.78

6.48

5.6

4.95

4.04

2.99

2.4

2.02

1.75

1.56

152.9128

Annual Exceedance Probability (AEP)

20%
250
216
203
192
183
148
125
109

97.1

88.1

70.3

59.5

47

39.8

31.5

25.1

21.4

17.1

14.6

11.5

9.7

8.43

7.48

6.15

4.58

3.67

3.08

2.66

2.35

10%
293
256
239
226
215
172
145
127
113
103

82.6

70.2

55.8

47.4

37.8

30.3

26

20.9

17.9

14.2

12

10.5

9.35

7.72

5.78

4.64

3.89

3.36

2.97

5%
333
295
275
259
245
196
165
144
129
117

94.5
80.7
64.4

55
44.1
35.5
30.5
24.7
21.2

17
14.4
12.6
11.3
9.37
7.06
5.69
4.78
4.12
3.63

2%
385
348
323
303
285
225
190
166
149
136
110

94.5
76.1
65.3
52.7
42.7
36.8
29.9
25.8
20.8
17.7
15.6

14
11.7
8.86
7.17
6.02
5.19
4.55

1%
424
390
360
336
315
247
208
182
164
150
122
105

85.1
73.3
59.4
48.3
41.8

34
29.4
23.8
20.4

18
16.2
13.6
10.4
8.41
7.06
6.08
5.32

Page 46

                                                           23098 - SBSMP/4
                                                                 Page 30




                                             Appendix H


                    DRAINS PRE & POST DEVELOPMENT RESULTS




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 47

DRAINS results prepared from Version 2023.11.8718.30178                                                                                                                                                          DRAINS results prepared from Version 2023.11.8718.30178

PIT / NODE DETAILS                                                                                   Version 8                                                                                                   PIT / NODE DETAILS                                                             Version 8
Name               Max HGL                            Max Pond                   Max Surface         Max Pond          Min       Overflow Constraint                                                             Name                    Max HGL               Max Pond         Max Surface     Max Pond        Min                Overflow Constraint
                                                      HGL                        Flow Arriving       Volume            Freeboard (cu.m/s)                                                                                                                      HGL              Flow Arriving   Volume          Freeboard          (cu.m/s)
                                                                                 (cu.m/s)            (cu.m)            (m)                                                                                                                                                      (cu.m/s)        (cu.m)          (m)

SUB-CATCHMENT DETAILS                                                                                                                                                                                            SUB-CATCHMENT DETAILS
Name           Max                                    EIA                        Remaining           EIA               RIA          PA          Due to Storm                                                     Name                Max                       EIA              Remaining      EIA              RIA                PA          Due to Storm
               Flow Q                                 Max Q                      Max Q               Tc                Tc           Tc                                                                                               Flow Q                    Max Q            Max Q          Tc               Tc                 Tc
               (cu.m/s)                               (cu.m/s)                   (cu.m/s)            (cu.m/s)          (min)        (min)       (min)                                                                                (cu.m/s)                  (cu.m/s)         (cu.m/s)       (cu.m/s)         (min)              (min)       (min)
Pre-Dev                                       0.035                          0               0.035                 5            2           9.7 50% AEP, 1.5 hour burst, Storm 1                                 Pre-Dev                               0.084                  0          0.084              5                  2           9.7 5% AEP, 30 min burst, Storm 8
Post-Dev                                      0.055                      0.029               0.026                 5            5             5 50% AEP, 30 min burst, Storm 9                                   Post-Dev                               0.11              0.064          0.053              5                  5             5 5% AEP, 10 min burst, Storm 6


PIPE DETAILS                                                                                                                                                                                                     PIPE DETAILS
Name               Max Q                              Max V                      Max U/S             Max D/S           Due to Storm                                                                              Name                    Max Q                 Max V            Max U/S         Max D/S         Due to Storm
                   (cu.m/s)                           (m/s)                      HGL (m)             HGL (m)                                                                                                                             (cu.m/s)              (m/s)            HGL (m)         HGL (m)

CHANNEL DETAILS                                                                                                                                                                                                  CHANNEL DETAILS
Name            Max Q                                 Max V                                                            Due to Storm                                                                              Name                    Max Q                 Max V                                            Due to Storm
                (cu.m/s)                              (m/s)                                                                                                                                                                              (cu.m/s)              (m/s)

DETENTION BASIN DETAILS                                                                                                                                                                                          DETENTION BASIN DETAILS
Name             Max WL                               MaxVol                     Max Q               Max Q             Max Q                                                                                     Name                 Max WL                   MaxVol           Max Q           Max Q           Max Q
                                                                                 Total               Low Level         High Level                                                                                                                                               Total           Low Level       High Level

Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Pre-Post ONLY (results)                                                                                                                                           Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Pre-Post ONLY (results)
{\colortbl;\red0\green0\blue0;\red192\green0\blue0;}Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Pre-Post ONLY (results).drn - DRAINS run at 16:46:07 on 14/5/2024 using Watercom Drains v2023.11.8718.30178   {\colortbl;\red0\green0\blue0;\red192\green0\blue0;}Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Pre-Post ONLY (results).drn - DRAINS run at 16:47:01 on 14/5/2024 using Watercom Drains v2023.11.8718.30178

DRAINS results prepared from Version 2023.11.8718.30178                                                                                                                                                          DRAINS results prepared from Version 2023.11.8718.30178

PIT / NODE DETAILS                                                                                   Version 8                                                                                                   PIT / NODE DETAILS                                                             Version 8
Name               Max HGL                            Max Pond                   Max Surface         Max Pond          Min       Overflow Constraint                                                             Name                    Max HGL               Max Pond         Max Surface     Max Pond        Min                Overflow Constraint
                                                      HGL                        Flow Arriving       Volume            Freeboard (cu.m/s)                                                                                                                      HGL              Flow Arriving   Volume          Freeboard          (cu.m/s)
                                                                                 (cu.m/s)            (cu.m)            (m)                                                                                                                                                      (cu.m/s)        (cu.m)          (m)

SUB-CATCHMENT DETAILS                                                                                                                                                                                            SUB-CATCHMENT DETAILS
Name           Max                                    EIA                        Remaining           EIA               RIA          PA          Due to Storm                                                     Name                Max                       EIA              Remaining      EIA              RIA                PA          Due to Storm
               Flow Q                                 Max Q                      Max Q               Tc                Tc           Tc                                                                                               Flow Q                    Max Q            Max Q          Tc               Tc                 Tc
               (cu.m/s)                               (cu.m/s)                   (cu.m/s)            (cu.m/s)          (min)        (min)       (min)                                                                                (cu.m/s)                  (cu.m/s)         (cu.m/s)       (cu.m/s)         (min)              (min)       (min)
Pre-Dev                                       0.058                          0               0.058                 5            2           9.7 20% AEP, 1.5 hour burst, Storm 2                                 Pre-Dev                               0.102                  0          0.102              5                  2           9.7 2% AEP, 25 min burst, Storm 4
Post-Dev                                      0.084                      0.045               0.039                 5            5             5 20% AEP, 30 min burst, Storm 10                                  Post-Dev                              0.135              0.073          0.066              5                  5             5 2% AEP, 10 min burst, Storm 7


PIPE DETAILS                                                                                                                                                                                                     PIPE DETAILS
Name               Max Q                              Max V                      Max U/S             Max D/S           Due to Storm                                                                              Name                    Max Q                 Max V            Max U/S         Max D/S         Due to Storm
                   (cu.m/s)                           (m/s)                      HGL (m)             HGL (m)                                                                                                                             (cu.m/s)              (m/s)            HGL (m)         HGL (m)

CHANNEL DETAILS                                                                                                                                                                                                  CHANNEL DETAILS
Name            Max Q                                 Max V                                                            Due to Storm                                                                              Name                    Max Q                 Max V                                            Due to Storm
                (cu.m/s)                              (m/s)                                                                                                                                                                              (cu.m/s)              (m/s)

DETENTION BASIN DETAILS                                                                                                                                                                                          DETENTION BASIN DETAILS
Name             Max WL                               MaxVol                     Max Q               Max Q             Max Q                                                                                     Name                 Max WL                   MaxVol           Max Q           Max Q           Max Q
                                                                                 Total               Low Level         High Level                                                                                                                                               Total           Low Level       High Level

Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Pre-Post ONLY (results)                                                                                                                                           Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Pre-Post ONLY (results)
{\colortbl;\red0\green0\blue0;\red192\green0\blue0;}Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Pre-Post ONLY (results).drn - DRAINS run at 16:46:15 on 14/5/2024 using Watercom Drains v2023.11.8718.30178   {\colortbl;\red0\green0\blue0;\red192\green0\blue0;}Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Pre-Post ONLY (results).drn - DRAINS run at 16:48:06 on 14/5/2024 using Watercom Drains v2023.11.8718.30178

DRAINS results prepared from Version 2023.11.8718.30178                                                                                                                                                          DRAINS results prepared from Version 2023.11.8718.30178

PIT / NODE DETAILS                                                                                   Version 8                                                                                                   PIT / NODE DETAILS                                                             Version 8
Name               Max HGL                            Max Pond                   Max Surface         Max Pond          Min       Overflow Constraint                                                             Name                    Max HGL               Max Pond         Max Surface     Max Pond        Min                Overflow Constraint
                                                      HGL                        Flow Arriving       Volume            Freeboard (cu.m/s)                                                                                                                      HGL              Flow Arriving   Volume          Freeboard          (cu.m/s)
                                                                                 (cu.m/s)            (cu.m)            (m)                                                                                                                                                      (cu.m/s)        (cu.m)          (m)

SUB-CATCHMENT DETAILS                                                                                                                                                                                            SUB-CATCHMENT DETAILS
Name           Max                                    EIA                        Remaining           EIA               RIA          PA          Due to Storm                                                     Name                Max                       EIA              Remaining      EIA              RIA                PA          Due to Storm
               Flow Q                                 Max Q                      Max Q               Tc                Tc           Tc                                                                                               Flow Q                    Max Q            Max Q          Tc               Tc                 Tc
               (cu.m/s)                               (cu.m/s)                   (cu.m/s)            (cu.m/s)          (min)        (min)       (min)                                                                                (cu.m/s)                  (cu.m/s)         (cu.m/s)       (cu.m/s)         (min)              (min)       (min)
Pre-Dev                                       0.065                          0               0.065                 5            2           9.7 10% AEP, 25 min burst, Storm 8                                   Pre-Dev                               0.115                  0          0.115              5                  2           9.7 1% AEP, 25 min burst, Storm 4
Post-Dev                                      0.094                      0.049               0.045                 5            5             5 10% AEP, 15 min burst, Storm 5                                   Post-Dev                              0.155               0.08          0.075              5                  5             5 1% AEP, 10 min burst, Storm 7


PIPE DETAILS                                                                                                                                                                                                     PIPE DETAILS
Name               Max Q                              Max V                      Max U/S             Max D/S           Due to Storm                                                                              Name                    Max Q                 Max V            Max U/S         Max D/S         Due to Storm
                   (cu.m/s)                           (m/s)                      HGL (m)             HGL (m)                                                                                                                             (cu.m/s)              (m/s)            HGL (m)         HGL (m)

CHANNEL DETAILS                                                                                                                                                                                                  CHANNEL DETAILS
Name            Max Q                                 Max V                                                            Due to Storm                                                                              Name                    Max Q                 Max V                                            Due to Storm
                (cu.m/s)                              (m/s)                                                                                                                                                                              (cu.m/s)              (m/s)

DETENTION BASIN DETAILS                                                                                                                                                                                          DETENTION BASIN DETAILS
Name             Max WL                               MaxVol                     Max Q               Max Q             Max Q                                                                                     Name                 Max WL                   MaxVol           Max Q           Max Q           Max Q
                                                                                 Total               Low Level         High Level                                                                                                                                               Total           Low Level       High Level

Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Pre-Post ONLY (results)                                                                                                                                           Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Pre-Post ONLY (results)
{\colortbl;\red0\green0\blue0;\red192\green0\blue0;}Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Pre-Post ONLY (results).drn - DRAINS run at 16:46:45 on 14/5/2024 using Watercom Drains v2023.11.8718.30178   {\colortbl;\red0\green0\blue0;\red192\green0\blue0;}Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Pre-Post ONLY (results).drn - DRAINS run at 16:48:22 on 14/5/2024 using Watercom Drains v2023.11.8718.30178

Page 48

                                                           23098 - SBSMP/4
                                                                 Page 31




                                             Appendix I


                DRAINS POST DEVELOPMENT MITIGATED RESULTS




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 49

DRAINS results prepared from Version 2023.11.8718.30178                                                                                                                                                          DRAINS results prepared from Version 2023.11.8718.30178

PIT / NODE DETAILS                                                                                  Version 8                                                                                                    PIT / NODE DETAILS                                                                       Version 8
Name                   Max HGL                          Max Pond                   Max Surface      Max Pond               Min       Overflow Constraint                                                         Name                             Max HGL              Max Pond            Max Surface    Max Pond              Min                 Overflow Constraint
                                                        HGL                        Flow Arriving    Volume                 Freeboard (cu.m/s)                                                                                                                          HGL                 Flow Arriving Volume                 Freeboard           (cu.m/s)
                                                                                   (cu.m/s)         (cu.m)                 (m)                                                                                                                                                             (cu.m/s)       (cu.m)                (m)
Bypass                                         107.06                                         0.039                                                                                                              Bypass                                       107.07                                0.071
N4                                             105.59                                             0                                                                                                              N4                                           105.65                                    0
N5                                             105.22                                         0.038                                                                                                              N5                                           105.22                                0.071
N3                                             105.99                                             0                                                                                                              N3                                           106.08                                    0
LPD                                            105.64                                             0                                                                                                              LPD                                          105.69                                    0

SUB-CATCHMENT DETAILS                                                                                                                                                                                            SUB-CATCHMENT DETAILS
Name              Max                                   EIA                        Remaining           EIA                 RIA            PA          Due to Storm                                               Name                             Max                  EIA                 Remaining      EIA                   RIA                 PA          Due to Storm
                  Flow Q                                Max Q                      Max Q               Tc                  Tc             Tc                                                                                                      Flow Q               Max Q               Max Q          Tc                    Tc                  Tc
                  (cu.m/s)                              (cu.m/s)                   (cu.m/s)            (cu.m/s)            (min)          (min)     (min)                                                                                         (cu.m/s)             (cu.m/s)            (cu.m/s)       (cu.m/s)              (min)               (min)     (min)
Ground Bypass                                   0.032                          0               0.032                  0              5            5 50% AEP, 15 min burst, Storm 6                               Ground Bypass                                 0.066                   0            0.066                  0                   5            5 5% AEP, 10 min burst, Storm 6
Building 1                                      0.015                      0.015                   0                  5              0            0 50% AEP, 5 min burst, Storm 1                                Building 1                                    0.027               0.027                0                  5                   0            0 5% AEP, 5 min burst, Storm 1
Building 2                                       0.01                       0.01                   0                  5              0            0 50% AEP, 5 min burst, Storm 1                                Building 2                                    0.017               0.017                0                  5                   0            0 5% AEP, 5 min burst, Storm 1
Building 3                                      0.012                      0.012                   0                  5              1            1 50% AEP, 5 min burst, Storm 1                                Building 3                                    0.021               0.021                0                  5                   1            1 5% AEP, 5 min burst, Storm 1


PIPE DETAILS                                                                                                                                                                                                     PIPE DETAILS
Name                   Max Q                            Max V                      Max U/S         Max D/S         Due to Storm                                                                                  Name                             Max Q                Max V               Max U/S      Max D/S        Due to Storm
                       (cu.m/s)                         (m/s)                      HGL (m)         HGL (m)                                                                                                                                        (cu.m/s)             (m/s)               HGL (m)      HGL (m)
150mm (3)                                       0.002                       0.68           105.587          105.23 50% AEP, 1 hour burst, Storm 1                                                                150mm (3)                                     0.012                1.05        105.654         105.29 5% AEP, 2 hour burst, Storm 10
150mm (1)                                       0.002                       0.73            105.99         105.232 50% AEP, 2 hour burst, Storm 8                                                                150mm (1)                                     0.015                1.12        106.078       105.304 5% AEP, 2 hour burst, Storm 10
150mm (2)                                       0.002                        0.8           105.636          105.23 50% AEP, 1 hour burst, Storm 4                                                                150mm (2)                                     0.011                1.19        105.693         105.28 5% AEP, 30 min burst, Storm 9

CHANNEL DETAILS                                                                                                                                                                                                  CHANNEL DETAILS
Name                   Max Q                            Max V                                                              Due to Storm                                                                          Name                             Max Q                Max V                                                    Due to Storm
                       (cu.m/s)                         (m/s)                                                                                                                                                                                     (cu.m/s)             (m/s)

OVERFLOW ROUTE DETAILS                                                                                                                                                                                           OVERFLOW ROUTE DETAILS
Name               Max Q U/S                            Max Q D/S                  Safe Q              Max D               Max DxV Max Width Max V    Due to Storm                                               Name                             Max Q U/S            Max Q D/S           Safe Q           Max D               Max DxV             Max Width Max V            Due to Storm
Bypass to LPD                                   0.031                       0.03               1.434               0.028       0.03       4      1.97 50% AEP, 15 min burst, Storm 6                             Bypass to LPD                                 0.063               0.062            1.434               0.035                0.04          4              1.32 5% AEP, 10 min burst, Storm 6
High Flow (1)                                                                                                                                                                                                    High Flow (1)                                 0.013               0.013                                                                                       5% AEP, 20 min burst, Storm 6
Low Flow (1)                                    0.002                      0.002                                                                                50% AEP, 2 hour burst, Storm 8                   Low Flow (1)                                  0.002               0.002                                                                                       5% AEP, 20 min burst, Storm 6
Low Flow (2)                                    0.002                      0.002                                                                                50% AEP, 1 hour burst, Storm 4                   Low Flow (2)                                  0.002               0.002                                                                                       5% AEP, 30 min burst, Storm 9
High Flow (2)                                                                                                                                                                                                    High Flow (2)                                 0.009               0.009                                                                                       5% AEP, 30 min burst, Storm 9
High Flow (3)                                                                                                                                                                                                    High Flow (3)                                 0.009               0.009                                                                                       5% AEP, 2 hour burst, Storm 10
Low Flow (3)                                    0.002                      0.002                                                                               50% AEP, 1 hour burst, Storm 7                    Low Flow (3)                                  0.002               0.002                                                                                       5% AEP, 2 hour burst, Storm 10
Total Post-Dev Mit                              0.035                      0.035               1.479               0.026           0.02           4       0.79 50% AEP, 30 min burst, Storm 6                    Total Post-Dev Mit                            0.078               0.078            0.908               0.034                0.03           4             1.02 5% AEP, 30 min burst, Storm 2


DETENTION BASIN DETAILS                                                                                                                                                                                          DETENTION BASIN DETAILS
Name               Max WL                               MaxVol                     Max Q               Max Q               Max Q                                                                                 Name                             Max WL               MaxVol              Max Q            Max Q               Max Q
                                                                                   Total               Low Level           High Level                                                                                                                                                      Total            Low Level           High Level
2x10kL (1)                                     108.74                       12.9               0.002                  0        0.002                                                                             2x10kL (1)                                    108.9                14.3            0.015                  0             0.015
10kL                                           108.35                        6.2               0.002                  0        0.002                                                                             10kL                                         108.53                   7            0.011                  0             0.011
2x10kL (2)                                     107.92                        9.2               0.002                  0        0.002                                                                             2x10kL (2)                                   108.48                14.1            0.012                  0             0.012

Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Post-Mit ONLY (results)                                                                                                                                           Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Post-Mit ONLY (results)
{\colortbl;\red0\green0\blue0;\red192\green0\blue0;}Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Post-Mit ONLY (results).drn - DRAINS run at 16:53:13 on 14/5/2024 using Watercom Drains v2023.11.8718.30178   {\colortbl;\red0\green0\blue0;\red192\green0\blue0;}Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Post-Mit ONLY (results).drn - DRAINS run at 16:55:31 on 14/5/2024 using Watercom Drains v2023.11.8718.30178

Flows were safe in all overflow routes.                                                                                                                                                                          Flows were safe in all overflow routes.

DRAINS results prepared from Version 2023.11.8718.30178                                                                                                                                                          DRAINS results prepared from Version 2023.11.8718.30178

PIT / NODE DETAILS                                                                                  Version 8                                                                                                    PIT / NODE DETAILS                                                                       Version 8
Name                   Max HGL                          Max Pond                   Max Surface      Max Pond               Min       Overflow Constraint                                                         Name                             Max HGL              Max Pond            Max Surface    Max Pond              Min                 Overflow Constraint
                                                        HGL                        Flow Arriving    Volume                 Freeboard (cu.m/s)                                                                                                                          HGL                 Flow Arriving Volume                 Freeboard           (cu.m/s)
                                                                                   (cu.m/s)         (cu.m)                 (m)                                                                                                                                                             (cu.m/s)       (cu.m)                (m)
Bypass                                         107.06                                         0.055                                                                                                              Bypass                                       107.07                                0.084
N4                                              105.6                                             0                                                                                                              N4                                           105.67                                    0
N5                                             105.22                                         0.053                                                                                                              N5                                           105.23                                0.082
N3                                             106.04                                             0                                                                                                              N3                                           106.17                                    0
LPD                                            105.67                                             0                                                                                                              LPD                                          105.71                                    0

SUB-CATCHMENT DETAILS                                                                                                                                                                                            SUB-CATCHMENT DETAILS
Name              Max                                   EIA                        Remaining           EIA                 RIA            PA          Due to Storm                                               Name                             Max                  EIA               Remaining      EIA                     RIA                 PA          Due to Storm
                  Flow Q                                Max Q                      Max Q               Tc                  Tc             Tc                                                                                                      Flow Q               Max Q             Max Q          Tc                      Tc                  Tc
                  (cu.m/s)                              (cu.m/s)                   (cu.m/s)            (cu.m/s)            (min)          (min)     (min)                                                                                         (cu.m/s)             (cu.m/s)          (cu.m/s)       (cu.m/s)                (min)               (min)     (min)
Ground Bypass                                   0.044                          0               0.044                  0              5            5 20% AEP, 15 min burst, Storm 1                               Ground Bypass                                 0.077                   0          0.077                    0                   5            5 2% AEP, 10 min burst, Storm 7
Building 1                                       0.02                       0.02                   0                  5              0            0 20% AEP, 5 min burst, Storm 1                                Building 1                                    0.032               0.032              0                    5                   0            0 2% AEP, 5 min burst, Storm 1
Building 2                                      0.013                      0.013                   0                  5              0            0 20% AEP, 5 min burst, Storm 1                                Building 2                                     0.02                0.02              0                    5                   0            0 2% AEP, 5 min burst, Storm 1
Building 3                                      0.016                      0.016                   0                  5              1            1 20% AEP, 5 min burst, Storm 1                                Building 3                                    0.025               0.025              0                    5                   1            1 2% AEP, 5 min burst, Storm 1


PIPE DETAILS                                                                                                                                                                                                     PIPE DETAILS
Name                   Max Q                            Max V                      Max U/S         Max D/S         Due to Storm                                                                                  Name                             Max Q                Max V               Max U/S      Max D/S       Due to Storm
                       (cu.m/s)                         (m/s)                      HGL (m)         HGL (m)                                                                                                                                        (cu.m/s)             (m/s)               HGL (m)      HGL (m)
150mm (3)                                       0.003                       0.76           105.602         105.245 20% AEP, 2 hour burst, Storm 8                                                                150mm (3)                                     0.014                1.06        105.668       105.303 2% AEP, 30 min burst, Storm 7
150mm (1)                                       0.009                       1.03           106.041         105.277 20% AEP, 1.5 hour burst, Storm 1                                                              150mm (1)                                     0.018                1.15        106.172       105.322 2% AEP, 30 min burst, Storm 7
150mm (2)                                       0.007                       1.02           105.669         105.261 20% AEP, 30 min burst, Storm 5                                                                150mm (2)                                     0.015                1.25        105.709       105.295 2% AEP, 15 min burst, Storm 2

CHANNEL DETAILS                                                                                                                                                                                                  CHANNEL DETAILS
Name                   Max Q                            Max V                                                              Due to Storm                                                                          Name                             Max Q                Max V                                                    Due to Storm
                       (cu.m/s)                         (m/s)                                                                                                                                                                                     (cu.m/s)             (m/s)

OVERFLOW ROUTE DETAILS                                                                                                                                                                                           OVERFLOW ROUTE DETAILS
Name               Max Q U/S                            Max Q D/S                  Safe Q              Max D             Max DxV Max Width Max V    Due to Storm                                                 Name                             Max Q U/S            Max Q D/S           Safe Q           Max D               Max DxV             Max Width Max V            Due to Storm
Bypass to LPD                                   0.044                      0.044               1.434               0.031     0.04       4      1.68 20% AEP, 15 min burst, Storm 7                               Bypass to LPD                                 0.075               0.074            1.434               0.037                0.04          4              1.28 2% AEP, 10 min burst, Storm 7
High Flow (1)                                   0.007                      0.007                                                                    20% AEP, 1.5 hour burst, Storm 1                             High Flow (1)                                 0.016               0.016                                                                                       2% AEP, 30 min burst, Storm 7
Low Flow (1)                                    0.002                      0.002                                                                    20% AEP, 1.5 hour burst, Storm 1                             Low Flow (1)                                  0.002               0.002                                                                                       2% AEP, 30 min burst, Storm 7
Low Flow (2)                                    0.002                      0.002                                                                    20% AEP, 30 min burst, Storm 5                               Low Flow (2)                                  0.002               0.002                                                                                       2% AEP, 15 min burst, Storm 2
High Flow (2)                                   0.005                      0.005                                                                    20% AEP, 30 min burst, Storm 5                               High Flow (2)                                 0.013               0.013                                                                                       2% AEP, 15 min burst, Storm 2
High Flow (3)                                   0.001                      0.001                                                                    20% AEP, 2 hour burst, Storm 8                               High Flow (3)                                 0.012               0.012                                                                                       2% AEP, 30 min burst, Storm 7
Low Flow (3)                                    0.002                      0.002                                                                    20% AEP, 2 hour burst, Storm 8                               Low Flow (3)                                  0.002               0.002                                                                                       2% AEP, 30 min burst, Storm 7
Total Post-Dev Mit                               0.05                       0.05               0.908               0.029     0.03       4      0.89 20% AEP, 30 min burst, Storm 6                               Total Post-Dev Mit                            0.098               0.098            1.479               0.036                0.04           4             1.17 2% AEP, 30 min burst, Storm 8


DETENTION BASIN DETAILS                                                                                                                                                                                          DETENTION BASIN DETAILS
Name               Max WL                               MaxVol                     Max Q               Max Q               Max Q                                                                                 Name                             Max WL               MaxVol              Max Q            Max Q               Max Q
                                                                                   Total               Low Level           High Level                                                                                                                                                      Total            Low Level           High Level
2x10kL (1)                                     108.87                        14                0.009                  0        0.009                                                                             2x10kL (1)                                   108.93                14.5            0.018                  0             0.018
10kL                                           108.51                        6.9               0.007                  0        0.007                                                                             10kL                                         108.55                 7.1            0.015                  0             0.015
2x10kL (2)                                     108.43                       13.6               0.003                  0        0.003                                                                             2x10kL (2)                                    108.5                14.2            0.014                  0             0.014

Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Post-Mit ONLY (results)                                                                                                                                           Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Post-Mit ONLY (results)
{\colortbl;\red0\green0\blue0;\red192\green0\blue0;}Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Post-Mit ONLY (results).drn - DRAINS run at 16:54:15 on 14/5/2024 using Watercom Drains v2023.11.8718.30178   {\colortbl;\red0\green0\blue0;\red192\green0\blue0;}Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Post-Mit ONLY (results).drn - DRAINS run at 16:56:39 on 14/5/2024 using Watercom Drains v2023.11.8718.30178

Flows were safe in all overflow routes.                                                                                                                                                                          Flows were safe in all overflow routes.

DRAINS results prepared from Version 2023.11.8718.30178                                                                                                                                                          DRAINS results prepared from Version 2023.11.8718.30178

PIT / NODE DETAILS                                                                                  Version 8                                                                                                    PIT / NODE DETAILS                                                                       Version 8
Name                   Max HGL                          Max Pond                   Max Surface      Max Pond               Min       Overflow Constraint                                                         Name                             Max HGL              Max Pond            Max Surface    Max Pond              Min                 Overflow Constraint
                                                        HGL                        Flow Arriving    Volume                 Freeboard (cu.m/s)                                                                                                                          HGL                 Flow Arriving Volume                 Freeboard           (cu.m/s)
                                                                                   (cu.m/s)         (cu.m)                 (m)                                                                                                                                                             (cu.m/s)       (cu.m)                (m)
Bypass                                         107.06                                         0.062                                                                                                              Bypass                                       107.07                                0.093
N4                                             105.64                                             0                                                                                                              N4                                           105.68                                    0
N5                                             105.22                                         0.062                                                                                                              N5                                           105.23                                0.092
N3                                             106.06                                             0                                                                                                              N3                                           106.35                                    0
LPD                                            105.68                                             0                                                                                                              LPD                                          105.72                                    0

SUB-CATCHMENT DETAILS                                                                                                                                                                                            SUB-CATCHMENT DETAILS
Name              Max                                   EIA                        Remaining           EIA                 RIA            PA          Due to Storm                                               Name                             Max                  EIA                 Remaining      EIA                   RIA                 PA          Due to Storm
                  Flow Q                                Max Q                      Max Q               Tc                  Tc             Tc                                                                                                      Flow Q               Max Q               Max Q          Tc                    Tc                  Tc
                  (cu.m/s)                              (cu.m/s)                   (cu.m/s)            (cu.m/s)            (min)          (min)     (min)                                                                                         (cu.m/s)             (cu.m/s)            (cu.m/s)       (cu.m/s)              (min)               (min)     (min)
Ground Bypass                                   0.055                          0               0.055                  0              5            5 10% AEP, 10 min burst, Storm 6                               Ground Bypass                                 0.084                   0            0.084                  0                   5            5 1% AEP, 10 min burst, Storm 7
Building 1                                      0.024                      0.024                   0                  5              0            0 10% AEP, 5 min burst, Storm 1                                Building 1                                    0.035               0.035                0                  5                   0            0 1% AEP, 5 min burst, Storm 1
Building 2                                      0.015                      0.015                   0                  5              0            0 10% AEP, 5 min burst, Storm 1                                Building 2                                    0.023               0.023                0                  5                   0            0 1% AEP, 5 min burst, Storm 1
Building 3                                      0.018                      0.018                   0                  5              1            1 10% AEP, 5 min burst, Storm 1                                Building 3                                    0.027               0.027                0                  5                   1            1 1% AEP, 5 min burst, Storm 1


PIPE DETAILS                                                                                                                                                                                                     PIPE DETAILS
Name                   Max Q                            Max V                      Max U/S         Max D/S         Due to Storm                                                                                  Name                             Max Q                Max V               Max U/S      Max D/S       Due to Storm
                       (cu.m/s)                         (m/s)                      HGL (m)         HGL (m)                                                                                                                                        (cu.m/s)             (m/s)               HGL (m)      HGL (m)
150mm (3)                                       0.009                       0.97           105.637         105.276 10% AEP, 2 hour burst, Storm 3                                                                150mm (3)                                     0.015                1.07        105.679       105.312 1% AEP, 30 min burst, Storm 7
150mm (1)                                       0.012                        1.1            106.06         105.291 10% AEP, 45 min burst, Storm 5                                                                150mm (1)                                     0.019                1.22        106.353       105.327 1% AEP, 25 min burst, Storm 5
150mm (2)                                       0.009                       1.11           105.681         105.271 10% AEP, 20 min burst, Storm 5                                                                150mm (2)                                     0.016                1.26        105.719       105.304 1% AEP, 15 min burst, Storm 5

CHANNEL DETAILS                                                                                                                                                                                                  CHANNEL DETAILS
Name                   Max Q                            Max V                                                              Due to Storm                                                                          Name                             Max Q                Max V                                                    Due to Storm
                       (cu.m/s)                         (m/s)                                                                                                                                                                                     (cu.m/s)             (m/s)

OVERFLOW ROUTE DETAILS                                                                                                                                                                                           OVERFLOW ROUTE DETAILS
Name               Max Q U/S                            Max Q D/S                  Safe Q              Max D             Max DxV Max Width Max V    Due to Storm                                                 Name                             Max Q U/S            Max Q D/S           Safe Q           Max D               Max DxV             Max Width Max V            Due to Storm
Bypass to LPD                                   0.053                      0.052               1.434               0.033     0.03       4      1.42 10% AEP, 10 min burst, Storm 6                               Bypass to LPD                                 0.083               0.083            1.434               0.039                0.04          4              1.28 1% AEP, 10 min burst, Storm 7
High Flow (1)                                    0.01                       0.01                                                                    10% AEP, 45 min burst, Storm 4                               High Flow (1)                                 0.018               0.018                                                                                       1% AEP, 45 min burst, Storm 5
Low Flow (1)                                    0.002                      0.002                                                                    10% AEP, 45 min burst, Storm 4                               Low Flow (1)                                  0.002               0.002                                                                                       1% AEP, 45 min burst, Storm 5
Low Flow (2)                                    0.002                      0.002                                                                    10% AEP, 20 min burst, Storm 5                               Low Flow (2)                                  0.002               0.002                                                                                       1% AEP, 15 min burst, Storm 5
High Flow (2)                                   0.007                      0.007                                                                    10% AEP, 20 min burst, Storm 5                               High Flow (2)                                 0.014               0.014                                                                                       1% AEP, 15 min burst, Storm 5
High Flow (3)                                   0.007                      0.007                                                                    10% AEP, 2 hour burst, Storm 3                               High Flow (3)                                 0.013               0.013                                                                                       1% AEP, 30 min burst, Storm 7
Low Flow (3)                                    0.002                      0.002                                                                    10% AEP, 2 hour burst, Storm 3                               Low Flow (3)                                  0.002               0.002                                                                                       1% AEP, 30 min burst, Storm 7
Total Post-Dev Mit                              0.061                      0.061               1.479               0.031     0.03       4      0.95 10% AEP, 45 min burst, Storm 7                               Total Post-Dev Mit                            0.109               0.109            0.908               0.038                0.05           4             1.19 1% AEP, 30 min burst, Storm 8


DETENTION BASIN DETAILS                                                                                                                                                                                          DETENTION BASIN DETAILS
Name               Max WL                               MaxVol                     Max Q               Max Q               Max Q                                                                                 Name                             Max WL               MaxVol              Max Q            Max Q               Max Q
                                                                                   Total               Low Level           High Level                                                                                                                                                      Total            Low Level           High Level
2x10kL (1)                                     108.89                       14.1               0.012                  0        0.012                                                                             2x10kL (1)                                   108.97                14.9             0.02                  0               0.02
10kL                                           108.52                          7               0.009                  0        0.009                                                                             10kL                                         108.56                 7.2            0.016                  0              0.016
2x10kL (2)                                     108.47                       13.9               0.009                  0        0.009                                                                             2x10kL (2)                                   108.51                14.3            0.015                  0              0.015

Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Post-Mit ONLY (results)                                                                                                                                           Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Post-Mit ONLY (results)
{\colortbl;\red0\green0\blue0;\red192\green0\blue0;}Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Post-Mit ONLY (results).drn - DRAINS run at 16:55:16 on 14/5/2024 using Watercom Drains v2023.11.8718.30178   {\colortbl;\red0\green0\blue0;\red192\green0\blue0;}Run Log for 24-05-13 - 23098 - Rev 2 - FINAL - Post-Mit ONLY (results).drn - DRAINS run at 16:57:02 on 14/5/2024 using Watercom Drains v2023.11.8718.30178

Flows were safe in all overflow routes.                                                                                                                                                                          Flows were safe in all overflow routes.

Page 50

                                                           23098 - SBSMP/4
                                                                 Page 32




                                             Appendix J


  STORMWATER QUALITY OPERATION AND MAINTENANCE GUIDELINES




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 51

                                                          BIO-RETENTION
                                            OPERATIONAL MANAGEMENT AND
                                                  MAINTENANCE GUIDELINE




                                                  PROPOSED TOWNHOUSE DEVELOPMENT

                                                                            5 PEARL STREET, COOROY

                                                                                                              COOROY

                                                                                                            23098 - O&MG




D:\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\SBSMP\Working\Appendices\MCE Bio Retention Operational
Management & Maintenance Guideline - 21209 - Rev 0.doc

Page 52

                                                                                                         Page 2




                                          Table of Contents
1   INTRODUCTION .......................................................................................... 3
2   GENERAL .................................................................................................. 3
3   RESPONSIBILITY FOR INSPECTION ..................................................................... 3
4   DATA COLLECTION / STORAGE REQUIREMENTS ..................................................... 3
5   MAINTENANCE PROCEDURE............................................................................. 3
  5.1   General .............................................................................................. 3
  5.2   Inspections .......................................................................................... 4
  5.3   Watering ............................................................................................ 5
  5.4   Vegetation Management and Weed Control .................................................... 6
  5.5   Validation Water Quality Testing ................................................................ 6
  5.6   Equipment Needs .................................................................................. 6
  5.7   Occupational Health and Safety ................................................................. 6
  5.8   Public Safety ........................................................................................ 7
  5.9   Disposal Requirements ............................................................................ 7
  5.10 Access Issues ........................................................................................ 7
  5.11 Bio-Retention Basin Resetting .................................................................... 7
Appendix A     BIO-RETENTION BASIN MAINTENANCE CHECKLIST ..................................... 8




Bio-Retention Basin Operational Management and Maintenance Guideline

Page 53

                                                                                           Page 3




1 INTRODUCTION
The water quality treatment for the proposed development includes a proposed bio-retention
basin. This document provides an overview of the maintenance requirements for the bio-
retention water quality device(s) on site to ensure that they are properly maintained.


2 GENERAL
Bio-retention basins are vegetated areas where runoff is filtered through a filter media layer
(e.g. sandy loam) as it percolates downwards. It is then collected via perforated underground
drains and flows to downstream waterways or to storages for reuse. Bio-retention basins
operate by filtering stormwater runoff through densely planted surface vegetation and then
percolating runoff through a prescribed filter media. During percolation, pollutants are
retained through fine filtration, adsorption and some biological uptake. The vegetation in a bio-
retention system is a vital functional element of the system providing a substrate for biofilm
growth within the upper layer of the filter media. The proposed bio-retention basin within the
site will do much of the same. It has been designed to reduce the impact of the development
on the downstream waterway environment.


3 RESPONSIBILITY FOR INSPECTION
The principal involved consultancy will be required to appoint an appropriately qualified
consultant maintenance contractor to carry out the inspections of the bio-retention basin
during the construction and on-maintenance period. At the completion of the maintenance
period the responsibility to undertake the inspections and generally maintain the basin will be
shifted to Body Corporate.


4 DATA COLLECTION / STORAGE REQUIREMENTS
Inspection records will be required for comparison of the performance of the system. In order
to assist this process it is proposed that the Bio-retention Basin Maintenance Checklist prepared
by Healthy Waterways (2006) be adopted for the site. Refer Appendix A for a copy of the
checklist.

Copies of the completed checklist are to be forwarded to the Morgan Consulting Engineers (or
other consultant nominated by the Principal) and to be provided to Council at the expiry of the
maintenance period and on request thereafter.


5 MAINTENANCE PROCEDURE
5.1     General
Vegetation plays a key role in maintaining the porosity of the filter media of a bio-retention
basin and a strong healthy growth of vegetation is critical to its performance. Therefore the
most intensive period of maintenance is during the plant establishment period (i.e. first two
years) when weed removal and replanting may be required.



Bio-Retention Basin Operational Management and Maintenance Guideline

Page 54

                                                                                            Page 4




It is also the time when high sediment loads may impact on plant growth and infiltration rates.
For this reason, the bio-retention systems are to be initially turfed. Vegetation can be
introduced when construction has been completed on an appropriate percentage of the lots
draining to each bio-retention system.

Inflow systems and overflow systems require careful monitoring, as these can be prone to scour
and litter build up. Debris can block inlets or outlets and can be unsightly, particularly in high
visibility areas. Inspection and removal of debris should be done regularly, and debris should be
removed whenever it is observed on a site.


5.2     Inspections
5.2.1 General
The bio-retention basins treat stormwater runoff through the principles of sedimentation,
filtration and percolation. These devices do not incorporate the use of screens and require
minimal maintenance during their operation. However, the systems are subject to deposition of
sediment that is filtered through the media.

Routine inspections shall be undertaken on the bio-retention basins after every significant
rainfall event (30mm of rainfall in a 24 hour period) or on a three (3) monthly basis within the
first twelve (12) months and on a six (6) monthly basis thereafter. The requirements of the
inspection for the bio-retention basin shall include the following:

    1. Check for build up of sediment at pipe inlet structures;

    2. Check for sediment within sub-soil drainage lines;

    3. Check all concrete structures for damage and deterioration;

    4. Check for the build up of vegetation matter on the bed surface and removal of
       vegetation matter to ensure minimal blockage to media;

    5. Check achieved flow rate through the media is maintained in accordance with the design
       requirements and anticipated compaction;

    6. Check inflow systems, outlets and the under drainage pipe elements to identify and
       remove any blockages such as litter build up.

5.2.2 Filter Media
The filter media will be inspected for sediment deposition of the bed of the bio-retention
basins and removed as required.




Bio-Retention Basin Operational Management and Maintenance Guideline

Page 55

                                                                                           Page 5




Inspect for the accumulation of an impermeable layer (such as oily or clayey sediment) that
may have formed on the surface of the filter media. A symptom may be that water remains
ponded in the bio-retention basin for more than a few hours after a rain event. Repair minor
accumulations by raking away any mulch on the surface and scarifying the surface of the filter
media between plants. Any leaf litter should be removed to help maintain the surface porosity
of the filter media.

Ensure the perforated pipes are not blocked to prevent filter media and plants from becoming
waterlogged. A small steady clear flow of water may be observed discharging from the
perforated pipe at its connection into the downstream pit some hours after rainfall.

Note that smaller rainfall events after dry weather may be completely absorbed by the filter
media and not result in flow. Sub-soil drainage lines are to be flushed with clean water as
required to remove and blockage.

Sediment should be removed where it has smothered vegetation or caused blockages to the
inlets our outlet systems.

Any holes and or scouring apparent on the filter media will be repaired. Ensure no damage has
occurred to the inlet and outlet systems, if this has occurred repair as required.

5.2.3 Repair of Damage
Any accumulation of an impermeable layer, (such as oily or clayey sediment) that may have
formed on the surface of the filter media will be repaired. A symptom may be that water
remains ponded in the bio-retention basin for more than a few hours after a rain event. Repair
these minor accumulations by raking away any mulch on the surface and scarifying the surface
of the filter media between plants. Any leaf litter should be removed to help maintain the
surface porosity of the filter media.


5.3     Watering
Regular watering of the bio-retention basin vegetation is essential for successful establishment
and healthy growth. The frequency of watering to achieve successful establishment will depend
upon rainfall, maturity of planting stock and the water holding capacity of the soil.

The following watering program should be adequate following the installation of vegetation:

    1. Week 1-2, 3 visits/week

    2. Week 3-6, 2 visits/week

    3. Week 7-12, 1 visit/week

After the first three month period, watering may still be required, particularly during the first
winter (dry period). Irrigation shall be undertaken in consultation with the Landscape Architect.



Bio-Retention Basin Operational Management and Maintenance Guideline

Page 56

                                                                                          Page 6




5.4     Vegetation Management and Weed Control
Conventional surface mulching of the bio-retention basins with organic material like tanbark,
should not be undertaken. Most organic mulch floats and runoff typically causes this material to
be washed away with a risk of blocking drains.

If weeds are observed within the bio-retention basin they shall be removed. Weeding will
generally involve manual removal of the species.

Vegetation planting densities are to be in accordance with the Landscape Architect’s design.
Where necessary a biodegradable erosion mat can be applied the basin batters to help combat
weed invasion and reduce the labour intensive maintenance requirements for weed removal.

Herbicides are not recommended as a means of weed control. If required, however, their
application is to be managed to avoid unintentional destruction of other vegetation or the
introduction of chemicals that may contaminate the stormwater runoff.

Where necessary, in areas that have been extensively weeded, the bio-retention basin shall be
replanted with similar planting densities using suitable native species in accordance with the
Landscape Architects design.

Inspection of the existing vegetation is to take place and any dead or diseased vegetation shall
be removed and replaced with suitable native species in accordance with the Landscape
Architects design.

The removal of plants, dead or diseased vegetation or weeds shall be disposed offsite at an
appropriate waste management facility.

All litter and debris present on the surface or batters of the bio-retention basins shall be
removed and disposed offsite at an appropriate waste management facility.


5.5     Validation Water Quality Testing
Validation water quality testing is not proposed for the site.


5.6     Equipment Needs
The equipment required to undertake regular maintenance to the bio-retention basins will be
standard hand held landscaping tools. No specific mechanical equipment is expected to be
required for the maintenance of the basins unless resetting is required (refer Section 5.11).


5.7     Occupational Health and Safety
The maintenance activities are to be undertaken in accordance with all current occupational
and workplace health and safety legislation, regulations, codes of practice or manufacturers
guidelines.




Bio-Retention Basin Operational Management and Maintenance Guideline

Page 57

                                                                                           Page 7




For maintenance access the shallow nature of the bio-retention systems enables pedestrian
ingress. As noted above no mechanical equipment is required unless resetting is required. The
batter grades are considered to be acceptable and do not pose an occupational health and
safety issue given proper training to maintenance personnel.

The application of pesticides or herbicides in response to any weed outbreak, which cannot be
controlled via manual removal, is to be undertaken by maintenance personnel in accordance
with manufacturer’s guidelines in consultation with the Landscape Architect. Protective
measures are to be implemented so as to minimise exposure to personnel, with personal
protective measures to be the final hierarchical option.


5.8     Public Safety
While maintenance is being undertaken consideration of pedestrians and cyclists is to be made
due to the close proximity of the footpaths. To avoid any safety concerns it is recommended
that temporary warning signs be placed at a sufficient distance to allow pedestrians and cyclists
to become aware of possible maintenance vehicles/personnel when maintenance is being
undertaken.


5.9     Disposal Requirements
The removal of litter and debris, plants, dead or diseased vegetation or weeds are to be
disposed offsite at an appropriate waste management facility.


5.10 Access Issues
Suitable access to the bio-retention basins can be achieved directly from the internal road
network within the site.


5.11 Bio-Retention Basin Resetting
Resetting (i.e. complete reconstruction) of the bio-retention basins will be required if the
system fails to drain adequately after tilling of the surface. Replacement of the filter media is
required when it becomes 50% blocked, which is estimated to occur approximately every 8 to
10 years.

This can be assessed via a review of sediment build up and the time necessary for the system to
drain or by in-situ falling head permeability tests of the filter media.




Bio-Retention Basin Operational Management and Maintenance Guideline

Page 58

                                                                       Page 8




                                              Appendix A


               BIO-RETENTION BASIN MAINTENANCE CHECKLIST




Bio-Retention Basin Operational Management and Maintenance Guideline

Page 59

                                                           23098 - SBSMP/4
                                                                 Page 33




                                             Appendix K


                            NSC FLOOD HAZARD OVERLAY MAP




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy

Page 60

Noosa Shire Council does not warrant the accuracy of information in this publication and any person using or relying   20/09/2023
upon such information does so on the basis that Noosa Shire Council shall bear no responsibility or liability
whatsoever for any errors, faults, defects or omissions in the information.
                                                                                                                        1:1129

Used in these records

About this file

File size
5.6 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Reference Document - Site Based Stormwater Management Plan.pdf · 5.6 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.