NOOSA COUNCIL Capital Schedule
As at 30 June 2020
Report run date: 27-Jul-2020 08:41:33
Total Public Transport Infrastructure 500,000 500,000 500,000 500,000 598,567 0 119.71%
500530 500530 - Whole of Shire Reseal & Rehabilitation Program 0 0 0 0 6,162 08 0.00%
500840 500757 - Black Mountain - Road Priority Sections and Road Reconstruct 1,290,000 1,318,214 1,318,214 1,318,214 1,542,370 7,[email protected]%
500967 500936 - Directional Signage Walter Hay Dr Roundabouts and Reef St 0 26,533 26,533 26,533 173 00 0.65%
500986 500958 - Shire Kerb & Channel Renewal Program Annual 100,000 100,000 100,000 100,000 82,738 [email protected]%
500987 500959 - Shire Reseal & Rehabilitation Renewal Program Annual 3,600,000 3,600,000 3,600,000 3,600,000 4,067,439 3,165,874 & 112.98%
500996 500969 - Boreen Point, Tewah St Gravel Road Seal 250,000 250,000 250,000 250,000 62,533 3,[email protected]%
500997 500970 - Boreen Point, Hector Street Road Widening and Kerb & Channel 97,000 97,000 97,000 97,000 87,054 [email protected]%
500998 500971 - Pomona, Ambulance Street Sealing of Gravel Section 200,000 200,000 200,000 200,000 61,120 3210 30.56%
501014 500982 - Tewantin Beckmans Rd Bypass Forward Design 0 50,000 50,000 50,000 69,112 850 © 138.22%
510017 510017 - Damaged Guardrail Renewals (Various) 0 0 51,800 51,800 26,032 26,[email protected]%
510022 510022 - Sunrise Beach, Tingira Cres Emergent Slip Repair 0 0 0 0 608,284 10,[email protected]%
510025 510025 - Sunshine Beach, Ross Cres Emergent Slip Repair 0 0 0 0 550,607 9,999 © 0.00%
Total Sealed Roads Network 5,537,000 5,641,747 5,693,547 5,693,547 7,163,625 3,224,978 125.82%
510012 510012 - Design Noosa District Sports Road & Pathway Network 0 0 50,000 50,000 63,152 08 126.30%
Total Sports Ground and Facilities 0 0 50,000 50,000 63,152 0 126.30%
500919 500915 - Swan Avenue Drainage 0 20,000 20,000 20,000 19,088 7,[email protected]%
500920 500916 - Gympie Terrace Stormwater 1,200,000 1,184,831 1,184,831 1,184,831 1,419,086 7,[email protected]%
500942 500927 - Stormwater Backflow Vulnerability Assessment 0 5,287 5,287 5,287 0 [email protected]%
500954 500937 - GPT Liner Net Replacement 0 15,000 15,000 15,000 14,965 [email protected]%
500988 500960 - Shire Bioretention Basin Renewals Program Annual 80,000 80,000 80,000 80,000 7,810 2,[email protected]%
500989 500961 - Shire Pit Structure Renewal Program Annual 150,000 150,000 150,000 150,000 107,064 11,[email protected]%
500999 500972 - Noosaville, Project Ave Stormwater Drainage Easement Upgrade 250,000 250,000 50,000 50,000 12,676 4,090 © 25.35%
510014 510014 - Cooroy Apex Park Drainage 0 0 0 0 24,315 08 0.00%
Total Stormwater Drainage 1,680,000 1,705,118 1,505,118 1,505,118 1,605,004 33,285 106.64%
500968 500938 - George Pearce Memorial Bench and Parkyn Hut Sign Renewal 0 14,156 14,156 14,156 11,941 [email protected]%
Total Streetscapes and Road Corridors 0 14,156 14,156 14,156 11,941 0 84.35%
Page 55 of 100See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.