Appendix E - Stormwater Management Plan · MCU12/0133

From the archive Development Application Part 2 of 2, 2 - Forms, Owner's Consent, Charitable Organisation Status, 3 - Town Planning Report (Noosa FLC), Appendix A - Code Ass Tables.,Appendix B - Proposal Plans.Appendix C - Archit Design Statement. File date in the archive: 2012-08-27 16:45.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
Bligh Tanner Consulting Engineers                                                                Page iv
Noosa Flexi Learning Centre Stormwater Management Plan
August 2012




EXECUTIVE SUMMARY

The Noosa Flexi-Learning Centre aims to create a welcoming and distinctly un-institutional
learning environment for disenfranchised and disengaged youth in the Noosa Region. The
design response is to create a beach-house style environment which minimises its impact on
the site, as well as on the planet’s resources.

The young people that will use the centre are approaching life with few privileges. By
creating a learning environment that embodies great sustainability features, the design team
hopes to provide accelerated opportunities for them to understand and interact with the types
of environmental knowledge that we believe will be important to the world they are inheriting.
Such learning opportunities can help build their pride, self-confidence and a sense of
purpose.

The stormwater management strategy helps create such a place by:
   • Preserving the natural hydrology across most of the site by building lightweight
       structures on piers, and minimizing soil compaction during construction
   • Harvesting rainwater and using a prominent elevated rainwater tank that both
       symbolizes the responsible use of water and reduces the electricity needed for
       pumping.

This report complies with the format for site-based stormwater management plans as set out
in the Urban Stormwater Planning Guidelines (DERM 2010) as referenced under the State
Planning Policy 4/10 Healthy Waters.

The site is low risk from an erosion and sediment control perspective, and accordingly a
minor erosion and sediment control plan will be provided as part of the operational works
application. Moving away from slab-on-ground construction significantly reduces earthworks
and hence the risk of sediment moving off the site during construction.

The stormwater quality management strategy is compliant with the requirements of the SEQ
Regional Plan Implementation Guideline No. 7—as referenced in the Noosa Plan.
Significantly, because the ground-level impervious area is kept at 10% of the site area, the
stormwater quality objective is satisfied by capturing and managing the first 10 mm of runoff.

For major storm events, runoff will continue to discharge across the front boundary of the site
as sheet flow. The design of the site, with limited ground level impervious surfaces, has a
minor impact on peak flows. A small area of depressed landscape at the front of the lot can
provide the 1 m³ of flood detention needed to avoid any increase in peak flows leaving the
site.

Used in these records

About this file

File size
1.1 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Appendix E - Stormwater Management Plan.pdf · 1.1 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.