SPECIFICATION FOR LANDSCAPE WORKS element design TM
PLANT SCHEDULE element design
(ground level) SCOPE PERFORMANCE
GENERAL CONDITIONS ALL LANDSCAPE CONSTRUCTION WORK IS TO BE CARRIED OUT IN COMPLIANCE WITH RELEVANT COUNCIL APPROVALS AND TO
TREE SPECIES INDUSTRY BEST PRACTICE. ANY CHANGES FROM DESIGN DOCUMENTATION MUST BE APPROVED BY PROJECT LANDSCAPE ARCHITECT
PRIOR TO CONSTRUCTION ON SITE.
EROSION AND SEDIMENT CONTROL MEASURES ARE TO BE UNDERTAKEN WHERE NECESSARY TO ENSURE NO DETRIMENTAL EFFECT
Code Botanical Name Common Name Size Quantity TO DOWNSTREAM WATERWAYS OR NEIGHBOURING SITES.
SITE PREPARATION / PRIOR TO COMMENCEMENT OF WORKS, EXISTING SITE CONDITION IS TO BE DOCUMENTED BY CONTRACTOR. ALL EXISTING AND
PROPOSED SERVICES ON SITE ARE TO BE LOCATED AND CLEARLY IDENTIFIED. ALL BUILDING RUBBISH AND DELETERIOUS MATERIALS
EARTHWORKS
* CUP ana
ELA ret
Cupaniopsis anacardioides Tuckeroo
Elaeocarpus reticulatis ‘Prima Donna’ Blueberry Ash
45 ltr
45 ltr
2
1
ARE TO BE REMOVED FROM SITE TO APPROVED WASTE LOCATION.
LANDSCAPE AREAS SHALL BE SCARIFIED TO A DEPTH OF 150mm TO PROMOTE GOOD GROWTH FOR TURF AND PLANTING.
PAN pen Pandanus pendunculatus Screw Pine EX GROUND 2 MATERIALS / SERVICES ALL MATERIALS TO BE USED IN THE CONSTRUCTION OF THE DESIGNED LANDSCAPE ARE TO BE OF AND INDUSTRY STANDARD QUALITY
AND FROM A SUSTAINABLE SOURCE WHERE POSSIBLE. NO MATERIALS USED ON SITE SHALL BE TOXIC TO HUMANS, ANIMALS OR
PLANTS.
* PROVIDE AS 2303:2018 CERTIFICATION FOR TREES ALL SELECT ITEM MATERIALS ARE TO BE APPROVED BY CLIENT PRIOR TO CONSTRUCTION ON SITE.
PROVIDE SERVICE CONDUITS TO ALL GARDEN BEDS FOR IRRIGATION AND DRAINAGE PURPOSE. PROVIDE CONDUITS FOR LIGHTING
WHERE REQUIRED.
ENSURE ADEQUATE DRAINAGE TO PLANTING AREAS FOR SPECIFIC SITE SOIL CONDITIONS VIA THE USE OF SLOTTED AGRICULTURAL
DRAIN (SELECT TYPE FOR APPLICATION), OVERLAND FLOW PATHS WITHIN GARDENS (SELECT RIVER GRAVEL ON GEOFABRIC
SHRUB SPECIES MATERIAL) AND SURFACE STORMWATER PITS (LOCATED IN GENERALLY CONCEALED POSITIONS).
Code Botanical Name Common Name Size Quantity PROPOSED HARDSCAPE ITEMS ARE TO BE CONSTRUCTED TO AUSTRALIAN STANDARDS AND RELEVANT COUNCIL CODES BY A
HARDSCAPE SUITABLY LICENCED CONTRACTOR. WORKPLACE HEALTH AND SAFETY REGULATIONS MUST BE IMPLEMENTED DURING CONSTRUCTION
PHASE.
ALP cae Alpinea caerulea Native Ginger PLANT MANAGEMENT
200 pot 30 ALL PLANT SPECIES ARE DETAILED WITHIN THE PLANT SCHEDULE . NO SUBSTITUTIONS ALLOWED WITHOUT PRIOR ACCEPTANCE BY
AS 2303-2015 TREE STOCK COUNCIL AND PROJECT LANDSCAPE ARCHITECT.
BAN rob Banksia robur Swamp Banksia 200 pot 5 FOR LANDSCAPE USE
THE CONTRACTOR SHALL OBTAIN ALL PLANTS AS SPECIFIED FROM AN ACCREDITED NURSERY OR OTHER APPROVED SOURCE. PLANTS
SHALL BE PRE-WATERED PRIOR TO ARRIVING ON SITE.
BAN spi Banksia spinulosa Hairpin Banksia 200 pot 3 PLANTS SHALL BE HEALTHY, HARDY AND OF GOOD FORM. THE ROOT SYSTEM OF EACH PLANT SHOULD NOT BE ROOTBOUND AND BE
CONDUCIVE TO SUCCESSFUL TRANSPLANTATION. ALL PLANTS TO BE PEST AND DISEASE FREE WITH CONTAINERS FREE FROM WEEDS.
STREET TREE SPECIES ARE TO COMPLY WITH NATSPEC AND RELEVANT COUNCIL CONDITIONS.
CAL GBF Callistemon ‘Great Balls of Fire’ Great Balls of Fire 200 pot 6 STAKE TREES WITH A MIN. OF TWO 50x50 HWD STAKES AND HESSION STRAP OR SIMILAR AS NOT TO DAMAGE TREE. FIGURE '8' DETAIL
RECOMMENDED.
COR Rub Cordyline fruticosa 'Rubra' Cordyline Rubra 200 pot 10 NO TYPE OF STAKE TO BE PLACED THROUGH ROOTBALL OF PLANT AT ANY TIME.
CRI pen Crinum pedunculatum Swamp Lily EACH PLANT TO HAVE ADDED WATER CRYSTALS TO PLANTING HOLE AND WATERED IN AFTER PLANTING AS REQUIRED.
200 pot 6 PLANT STOCK MAY BE REJECTED IF NOT CONFORMING WITH ABOVE SPECIFICATIONS.
LOM hys Lomandra hystrix Matt Rush 200 pot 21
SOFTSCAPE SETOUT OF ALL SOFTSCAPE AREAS TO BE IN ACCORDANCE WITH APPROVED PLANS. PLANTING AREAS TO BE MOUNDED TO ACHIEVE
PHI Xan Philodendron ‘xanadu’ Dwarf Philodendron 200 pot 16 ADEQUATE DRAINAGE AND AESTHETIC PRESENTATION.
AS 4419-2003, SOILS FOR SOIL: A GOOD QUALITY FRIABLE, MODERATELY DRAINING, ORGANIC ENRICHED LANDSCAPING SOIL MIX SHALL BE IMPORTED FROM AN
SYZ Cas Syzygium ‘Cascade’ Weeping Lily Pilly 300 pot 3 LANDSCAPING AND APPROVED SOURCE. THE SOIL SHOULD NOT CONTAIN ANY CLAY AND BE FREE FROM CONTAMINANTS SUCH AS WEEDS, STICKS AND
ROCKS. IMPLEMENTATION WITHIN GARDEN AREAS TO A MIN. OF 300mm DEPTH.
SYZ Pin Syzygium 'Pinnacle' Pinnacle 300 pot 3 GARDEN USE ORGANIC MULCH: HOOP PINE MULCH IN ITS VARIETY OF FORMS IS TO BE SUPPLIED AND INSTALLED TO A MIN. DEPTH OF 100mm. MULCH
IS TO BE FREE OF FOREIGN MATTER INCLUDING WEEDS, SOIL, STICKS AND ROCKS. AVOID PLACEMENT OF MULCH AGAINST STEM OR
SYZ Res Syzygium 'Resilience' Resilience 300 pot 34 AS 4454-2003, COMPOSTS, TRUNK OF PLANTS. GRADE MULCH TO BE SELF RETAINED WITHIN GARDEN EDGING.
SOIL CONDITIONERS AND GRAVEL MULCH: SELECTED WASHED RIVER MULCH GRADED IN SIZE AND COLOUR. USE IN AREAS AS SPECIFIED ON PLANS. TO BE USED
MULCHES TO SEPARATE ORGANIC MULCH FROM THE WALLS OF BUILDINGS, ADJACENT PATHS AND TOO FACILITATE DRAINAGE WITHIN GARDEN
BEDS. MIN. DEPTH TO BE TWICE THE DIAMETER OF THE LARGEST PEBBLE.
GROUNDCOVER SPECIES TURF SHALL CONSIST OF A DENSE, WELL ROOTED, VIGOROUS GRASS GROWTH WITH MIN. 25mm OF TOPSOIL. TURF IS TO BE
TURF DELIVERED TO SITE WITHIN 24 HOURS OF BEING CUT. TURF SHOULD BE FREE FROM DELETERIOUS MATERIAL INCLUDING WEEDS,
Code Botanical Name Common Name Size Quantity (SAPPHIRE) SEEDS OR ROOTS INCLUDING NUT GRASS AND OXALIS. TURF SHALL BE SUPPLIED IN UNIFORM SIZE IN UNBROKEN CONDITION.
MOISTURE LEVEL OF TURF TO REMAIN CONSISTENT DURING LAYING. TURF TO BE LAID ALONG CONTOUR AND PINNED IF GREATER
THAN 1:4 SLOPE.
PREPARE SUBGRADE TO A LEVEL BASE WITH AN APPROVED TOPSOIL AND SPREAD UNDER TURF FERTILIZER AT RECOMMENDED RATE.
AUS dul Austromyrtus dulcis Midyim 140 pot 3 TURF TO FINISH LEVEL WITH PATHS, EDGES AND KERBS AFTER ROLLING AND SETTLEMENT.
BAN pro Banksia integrifolia prostrate Roller Coaster 140 pot 4 IRRIGATION TO BE INSTALLED BY A SUITABLY QUALIFIED CONTRACTOR AND BE INSTALLED IN ACCORDANCE WITH ALL COUNCIL WATER
IRRIGATION
CAR AR Carpobrotus glaucescens Aussie Rambler 140 pot 5 REGULATIONS.
(TO ALL GARDENS THE MOST WATER EFFICIENT METHOD OF IRRIGATION IS TO BE USED, CONNECTED TO TANK SUPPLY WHERE POSSIBLE.
CAS CI Casuarina glauca "Cousin It" Cousin It 140 pot 12 INCLUDING PLANTERS & CONDUITS TO BE LAID TO ALL GARDEN AREAS TO PROVIDE A REGULATED COVERAGE. FLUSH AND PRESSURE TEST PRIOR TO
COMMISSIONING.
DIA con Dianella congesta Beach Flax Lilly 140 pot 10 UNDERCROFT AREAS) PROVIDE AS CONSTRUCTED DRAWINGS CLEARLY SHOWING LOCATION OF ALL IRRIGATION COMPONENTRY.
FIC nod Ficina nodosa Knobby Club-rush 140 pot 18 THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE CARE AND MAINTENANCE OF ALL LANDSCAPE WORKS FOR A PERIOD OF 13
LANDSCAPE WEEKS AFTER COMPLETION.
VIO hed Viola hederacea Native Violet 140 pot 19 ESTABLISHMENT PERIOD MAINTENANCE IS TO INCLUDE MOWING OF TURF, REMOVAL AND SPRAYING OF WEEDS, PRUNING AND TRIMMING OF SHRUBS WHERE
REQUIRED, REPLACEMENT OF DEAD OR DISEASED PLANT STOCK AND CORRECT WORKING OF IRRIGATION SYSTEM.
WATER IS TO BE PROVIDED TO ALL SOFT LANDSCAPING AT A REQUIRED RATE DURING THE ESTABLISHMENT PERIOD TO ENSURE
HEALTHY AND VIGOROUS GROWTH.
NOTE : ALL PLANTS TO HAVE NATIVE SLOW RELEASE FERTILISER AND WATER CRYSTALS
SHEET 05 - PLANT LISTS & SPECIFICATION PLAN - OPW FOR COUNCIL APPROVAL
AMENDMENTS PROJECT
PROPOSED DUPLEX
element design
issue date description
A 05.04.23 ISSUE FOR COUNCIL APPROVAL
CONTRACTOR TO : ADDITIONAL NOTES DIAL BEFORE 73 SOUTHERN CROSS PARADE
· CONFIRM LOCATION OF
YOU DIG
LEGEND
FIELD GULLY
BOUNDARIES & SERVICES
FIELD GULLY LOCATIONS TO BE DETERMINED ON landscape architecture SUNSHINE BEACH
PRIOR TO COMMENCING
LANDSCAPE WORKS
SITE IN ACCORDANCE WITH HYDRAULIC DRAWINGS.
ENSURE PONDING DOES NOT OCCUR. ALL
WWW. 1100.com.au MASTER PLANNING SUBDIVISIONS
COMMERCIAL DEVELOPMENTS RESORTS
QLD 4567 Date APRIL 2023
· ENSURE ALL FALLS TO STORMWATER PITS AND SUB SOIL DRAINS TO PARKLANDS REVEGETATION MULTI-UNITS
STORMWATER PITS ARE TO EXISTING STORMWATER SYSTEM.
151 Brisbane Rd. Mooloolaba
CLIENT
IZAROX QLD PTY LTD Scale 1: 200 @ A3
INDUSTRY STANDARDS ROOT BARRIER Phone 07 5444 6155 Fax 07 5444 6055 DWG
Design JRV Drawn JRV
Copyright in the whole and every part of this document belongs to
ELEMENT DESIGN QLD PTY LTD and may not be used, sold,
· CHECK ALL LEVELS PRIOR TO PROVIDE ROOT BARRIER TO BACK OF KERB AND PO Box 1546, Buderim QLD 4556
[email protected]
TITLE
PLANT LIST & SPECIFICATION Sheet 04 OF 04
transferred, copied or reproduced in whole or in part in any manner or CONSTRUCTION EDGE OF FOOTPATH TO MANUFACTURERS
TM issue
form or in or on any media to any person without the prior written
consent of ELEMENT DESIGN QLD PTY LTD.
SPECIFICATIONS.
ED 23114 OPW - 05 A
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
RFI - landscaping plans.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.