Car Parking
15 The existing carparking area adjacent to the surf club building must be upgraded. The works
must be generally in accordance with drawing number 1006 Revision C prepared by Andrew
Bock Architecture and undertaken in accordance with an Operational Works approval and
must include in particular:
a. detail to demonstrate that sufficient area is provided for delivery/service vehicle
movements including clearances;
b. materials and surface treatments to prioritise pedestrian movements and other
“shared” areas;
c. signage to designate pedestrian paths, shared areas and vehicle movement areas;
d. bollard and seating design and other surface treatments in accordance with Council’s
“look and feel” (Council’s design principles and local colour palette);
e. detail to clearly indicate stormwater drainage paths;
f. a reconfiguration of the carparking access, aisles and spaces to improve performance.
16 Car parking in Webb Road must be upgraded to provide 4 additional on street car park
spaces and include in particular provide:
a. filling, roadworks and drainage works;
b. linemarking;
c. dimensions and grades in accordance with AS/NZS2890.1:2006.
The proposed works are to be undertaken in accordance with an Operational Works
approval. The works must be generally in accordance with drawing number 16636-SK01
Revision A prepared by TOD Noosa.
Paving Treatment of Vehicle Movement Areas
17 Alternative materials, surface patterns, or threshold treatments must be used to articulate the
pavement treatment of vehicle movement areas, shared areas and pedestrian paths.
18 A Construction Management Plan for the development must be submitted to and approved
by Council at least 5 working days prior to the commencement of any Building works or at
least 5 working days prior to the pre-start meeting for Operational Works. The Construction
Management Plan shall include but not be limited to:
a. site working hours;
b. communication and consultation processes with surrounding premises;
c. control and suppression of –
(i) noise
(ii) vibration;
(iii) dust;
(iv) odours and exhausts control; and
(v) site working hours
d. employee and contractor induction and education processes.
19 A Traffic Management Plan for each separate construction phase of the development must
be submitted to and approved by Council at least 5 working days prior to the commencement
of any works or at least 5 working days prior to the pre-start meeting for Operational
Works. The Traffic Management Plan must include but not be limited to:
a. limiting the routes for the heavy vehicles to the major road network and define the route
to the site;
b. indicate provision for on-site and off-site parking and shuttle buses (if required) for the
required workforce;
Page 6 of 11
Document Set ID: 23410782
Version: 3, Version Date: 20/12/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
App A - Existing Approvals.pdfRelated documentApplication case desk ↗
About this file
- File size
- 9.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.