Attached to the e-mail MCU16/0084.02 - Permissible change -140-142 Eumundi Noosa Rd Noosaville.
27 April 2017 The Assessment Manager Noosa Shire Council PO Box 141 Tewantin QLD 4565 Dear Sir / Madam, In accordance with Section 369 of the Sustainable Planning Act 2009 (‘SPA’) and on behalf of Denmac Nominees Pty Ltd, Urbis seeks to undertake a Permissible Change to an existing approval at 140-142 Eumundi Noosa Road, Noosaville QLD, 4566, formally described as Lot 2 on RP173876. The approval (Development Permit for Material Change of Use for Retail Business (Type 5 Vehicle Uses (Service Station) and Type 2 Shop & Salon (Shop)) and Entertainment & Business (Type 1 Food & Beverages (Food Outlet))), was issued to the applicant, being Denmac Nominees Pty Ltd, by Council on 12 January 2017 via a Negotiated Decision Notice. Denmac Nominees Pty Ltd has since undertaken the operational works application (Council Reference: OPW17/0068) for the stormwater quality treatment system for the development. The Stomwater360 system is proposed to be the stormwater quality treatment system for the development. The system was assessed and approved by Noosa Shire Council in the development application process (Council Reference: MCU0016/0084). The development has progressed and the operational works application has been lodged (Council Reference: OPW17/0068). Noosa Shire Council has advised that the operational works application cannot be approved because it conflicts with two conditions (conditions 26 and 27). It was recommended by Council that we lodge a Permissible Change application to rectify the inconsistent conditions.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 5 pages
Page 2
In discussions with Council’s Stormwater Engineer throughout the operational works process it was
confirmed that conditions 26 and 27 conflict with the approved Stormwater360 system. The conflict
arose because conditions 26 and 27 relate to State Planning Policy (SPP) objectives. It is our
understanding that Noosa Shire Council does not endorse Stormwater360 systems in the local
government area because, they cannot guarantee that the stormwater treatment system will achieve
the water quality objectives of the SPP. However, as the development site is less than 2,500m 2 (site
area: 2,428m2) the development does not require assessment against the SPP and therefore is not
required to be conditioned in this regard.
Noosa Shire Council have their own stormwater quality objectives, which prompt the need for the
Stormwater360 system in this circumstance. Therefore, Council recommended that conditions 26 and
27 be deleted to be removed the conflict. The conditions state:
26 - A stormwater quality treatment system must be provided for the development to achieve
pollutant reduction targets of 90% reduction in gross pollutants, 80% reduction in Total
Suspended Solids, 60% reduction in Total Phosphorous and 45% reduction in Total Nitrogen.
27 - The Operational Works application must be supported by a MUSIC model that includes
water quality treatment nodes endorsed by Stormwater Australia or their delegate to meet the
Stormwater Quality Improvement Devices Evaluation Protocol. Evidence of the endorsement
of the product must be provided with the Application for Operational Works.
We note that the proposal has not altered the approved built form and scale. There are no physical
changes proposed, merely an administrative change to reflect the Stormwater Management Plan.
Section 367 of SPA, outlines what criteria are applicable in determining if a change to a development
application is a Permissible Change to a development approval. Each of the proposed changes as
outlined above have been assessed against these criteria, as follows:
367 What is a permissible change for a development approval
(1) A permissible change, for a development approval, is a change to the approval that
would not, because of the change –
(a) Result in a substantially different development;
Response:
In respect to section 367(1)(a) of SPA, which determines what constitutes a substantially different
development, it is appropriate to have regard to the guidelines made by the Chief Executive under
Section 760 of the SPA (Statutory Guideline 06/09), as follows:
"Although it will depend on the individual circumstances of the development, the following list
identifies changes that may result in a substantially different development and would,
therefore, not be a minor change or permissible change under the SPA. This list is intended as
a guide to assist assessment managers and applicants to determine whether a change will
result in a substantially different development and is not intended to be exhaustive.”
2
Page 3
An assessment of the proposed changes against the criteria in the Guideline is included in the table
below.
Guideline Criteria Response
Involves a new use with different or additional The proposed changes do not alter the uses
impacts. approved, being Retail Business (Type 5 Vehicle
Uses (Service Station) and Type 2 Shop & Salon
(Shop)) and Entertainment & Business (Type 1
Food & Beverages (Food Outlet)). No new uses
are introduced and the changes do not involve
any different or additional impacts which were not
addressed by the applicant and Council through
the assessment process for the original
application.
Results in the application applying to a new The proposed changes do not involve the
parcel of land. addition of any new land to the development
application.
Dramatically changes the built form in terms of The built form, scale, bulk and appearance is
scale, bulk and appearance. maintained. The proposed change relates to an
administrative error to the conditions. The
change involves deleting inconsistent conditions
regarding to stormwater quality.
Changes the ability of the proposal to operate as The proposed change does not alter the ability for
intended. For example, reducing the size of a the proposal to operate as a service station and
retail complex may reduce the capacity of the food outlets. The proposed change relates to an
complex to service the intended catchment. administrative error to the conditions. The
change involves deleting inconsistent conditions
regarding to stormwater quality.
Removes a component that is integral to the The proposed changes do not result in a removal
operation of the development. of any component of the development. The
proposed change relates to an administrative
error to the conditions. The change involves
deleting inconsistent conditions regarding to
stormwater quality.
Significantly impacts on traffic flow and the The changes do not impact the traffic flow and
transport network, such as increasing traffic to transport network.
3
Page 4
the site.
Introduces new impacts or increases the severity The changes are not considered to increase the
of known impacts. severity of any impacts created by the
development as originally approved. Specifically,
the changes will not have an adverse effect on
stormwater management.
Removes an incentive or offset component that The development as originally approved did not
would have balanced a negative impact of the include any incentive or offset component.
development.
Impacts on infrastructure provision, location or The proposal does not increase built form or
demand. scale of the development. The changes do not
impact on infrastructure provision, location or
demand.
The proposed change relates to an administrative
error to the conditions. The change involves
deleting inconsistent conditions regarding to
stormwater quality.
(b) If the application for the approval were remade including the change—
(i) Require referral to additional concurrence agencies; or
(ii) For an approval for assessable development that previously did not require impact
assessment—require impact assessment; or
Response:
The development originally did not required referral to the State Assessment and Referral Agency
(SARA). The changes to the conditions will not result in triggers requiring referral of the development
to SARA.
The original development application triggered Impact Assessment for the development.
(c) For an approval for assessable development that previously required impact assessment—
be likely, in the responsible entity’s opinion, to cause a person to make a properly made
submission objecting to the proposed change, if the circumstances allowed; or
Response:
The original application required Impact Assessment. The alteration to the conditions regarding
stormwater quality is unlikely to cause a person to make a properly made submission objecting to the
4
Page 5
proposed change. We also note that no properly made submissions were received about the original
development application.
(d) Cause development to which the approval relates to include any prohibited development.
Response:
The proposal does not include any prohibited development.
(2) For deciding whether a change is a permissible change under subsection (1)(b) or (d), the
planning instruments or law in force at the time the request for the change was made apply.
Response:
No new planning instruments/laws applicable to the site or approved development have come into
effect since the original approval was granted on 12 January 2017 pursuant to Noosa Plan 2006.
It is requested that the approval package is amended. We request that conditions 26 and 27 be
deleted. We note that there are no amendments to the approved plans.
Suggested amendments are outlined as follows, with deletions in blue and struck out and additions in
blue and underlined.
Assessment Manager Conditions
26. A stormwater quality treatment system must be provided for the development to achieve
pollutant reduction targets of 90% reduction in gross pollutants, 80% reduction in Total
Suspended Solids, 60% reduction in Total Phosphorous and 45% reduction in Total Nitrogen.
27. The Operational Works application must be supported by a MUSIC model that includes
water quality treatment nodes endorsed by Stormwater Australia or their delegate to meet the
Stormwater Quality Improvement Devices Evaluation Protocol. Evidence of the endorsement of
the product must be provided with the Application for Operational Works.
5
Page 6
Given the proposed change relates to an administrative error which resulted in conditions that were
inconsistent with the approved plans and which could have been rectified in the development
application process, we respectfully request that the application fee be waived.
In summary, we consider that the above assessment demonstrates that the proposed changes can be
considered a Permissible Change to the approval under SPA. The changes do not result in a
substantially different development, do not significantly alter the external built form, do not result in
external extensions to the building, and do not increase potential adverse impacts from the
development.
We trust the supplied documentation is sufficient in order for Council to undertake an assessment of
this request. If you have any questions, please do not hesitate to contact Penny Milton or the
undersigned on (07) 3007 3800.
Yours sincerely,
Cameron Stanley
Director
6
Used in these records
3. Final-Letter-170418-BA4090-Permissible Change.pdfRelated documentApplication case desk ↗
3. Final-Letter-170418-BA4090-Permissible Change.pdfRelated documentApplication case desk ↗
About this file
- File size
- 402 KB (small file)
- File type
No other editions are linked here.