EHP Permit number: SPCE05212613

 

CONDITIONS

Schedule A - General

Al In carrying out an ERA to which this approval relates, all reasonable and practicable measures must be
taken to prevent and/or to minimise the likelihood of environmental harm being caused.

A2 The registered operator of an ERA to which this approval relates must:

a) install all measures, plant and equipment necessary to ensure compliance with the conditions of this
approval; and

b) maintain such measures, plant and equipment in a proper and efficient condition; and

c) operate such measures, plant and equipment in a proper and efficient manner.

Limitations of permit

A3 Extractive activities are only permitted to be conducted generally in accordance with extraction areas
shaded grey in Attachment One. The total extent of extraction areas must not exceed 9 hectares.

Blasting

A4 No blasting is permitted under this approval.

Site Based Management Plan
AS From commencement of an ERA to which this approval relates, a site based management plan (SBMP)
must be implemented.

AG The SBMP must identify all sources of environmental harm, including but not limited to the actual and
potential release of all contaminants, the potential impact of these sources and what actions will be
taken to prevent the likelihood of environmental harm being caused.

A7 The SBMP must also provide for the review and ‘continual improvement in the overall! environmental
performance of all ERAs that are carried out.

A8 The SBMP must address the following matters:

)) Environmental commitments - a commitment by senior management to achieve specified and
relevant environmental goals.

(b) Identification of environmental issues and potential impacts.

(c) Control measures for routine operations to minimise likelihood of environmental harm.

(d) Contingency plans and emergency procedures for non-routine situations, including flood
events.

(e) Organisational structure and responsibility.

(f) Effective communication.

(g) Monitoring of contaminant releases.

(h) Conducting environmental impact assessments.

(i) Staff training and awareness of environmental issues related to the operation of the

environmentally relevant activities.
(i) Record keeping.
(k) Periodic review of environmental performance and continual improvement.

AQ The site based management plan must not be implemented or amended in a way that contravenes any
condition of this approval.
Equipment Calibration

A10 — Allinstruments, equipment and measuring devices used for measuring or monitoring in accordance with
any condition of this approval must be calibrated, and appropriately operated and maintained.

Monitoring
Ali1 A suitably qualified and competent person(s) with appropriate training must conduct and report on any

monitoring required by this approval.

Page 3 of 9 * 120607 « Version 1 Department of Environment and Heritage Protection

Sy

 

 

 
Log in to download the original file

SPCE05212613 Permit.pdf · 1.0 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.