PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 10 MARCH 2020
4 RAL19/0011 PLANNING & ENVIRONMENT COURT APPEAL NO. D7/2020 - REFUSAL
OF APPLICATION TO SUBDIVIDE 120, 126 AND 138 HAPPY JACK CREEK ROAD,
RIDGEWOOD
DOCUMENT INFORM AT ION
Author Manager Development Assessment, Kerri Coyle
Environment & Sustainable Development
Index ECM/ Application/ RAL19/0011/ Case/ Kaymond Pty Ltd
Attachments Nil
EXECUTIVE SUMMARY
Not Applicable
RECOMMENDATION
That Council note the report by the Manager Development Assessment to the Planning &
Environment Committee Meeting dated 10 March 2020 regarding Planning & Environment Court
Appeal No D7/2020 and agree to defend the appeal.
REPORT
A development application to reconfigure 3 lots into 3 lots at Happy Jack Creek Rd, Ridgewood
was refused by delegation on 6 December 2019 for the following reasons:
1. The proposal would result in an existing lot that is wholly located outside the Riparian
Buffer Area to be relocated within the buffer area, contrary to the specific and overall
outcomes of the Noosa Plan’s Biodiversity Overlay Code.
2. The proposal is contrary to the Reconfiguring a Lot Code and Natural Hazards Overlay
Code as:
2.1. Proposed lot 2 is likely to be located in an area subject to local flooding, with Happy
Jack Creek road reserve also likely to be subject to inundation during flood events;
2.2. The applicant has not demonstrated that a suitable, flood free house site area and
effluent disposal area is available for proposed lot 2; and
2.3. The applicant has not demonstrated that lot 2 has flood free access and residents of
proposed lot 2 may become isolated during flood times, potentially burdening
emergency services.
3. The proposal is contrary to the Reconfiguring a Lot Code as proposed lot 2 does not have
suitable, safe and appropriate access, as access is proposed via an existing bridge, likely
to have been privately constructed and inspection shows that the bridge is likely to require
some significant maintenance work.
4. The proposed boundary realignment will increase the amount of traffic utilising the bridge
and this will result in additional maintenance of the bridge, further burdening Council’s
resources.
Page 49 of 53
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.