Brisbane Office
Project No: 1-23262-A
Ref: 1-23262-A LR 1.1
Author: Jim Dixon/gb
11 August 2023
Connor O’Meara Solicitors
Email: [email protected]
ATTENTION: ALASTAIR STORIE
RE: CONSTRUCTION METHODOLOGY PLAN
DAVID WILLIAM NEATE V NOOSA SHIRE COUNCIL & ORS PLANNING AND
ENVIRONMENT COURT APPEAL NO. 1219 OF 2020
1.0 INTRODUCTION
I refer to the Mediation Agreement of 20 July, 2023 (copy attached).
The following recommendations are presented to address the issues related ensuring the
stability of the site within and below the Construction Footprint including:-
a) The construction methodology
b) The weight and footprint pressure of the equipment to be used
c) The sequence of construction with respect to all earthworks and structures
Comments and recommendations made should be read in conjunction with the following
reports:-
• Golder Associates Report, dated November, 2003
• Core Consultants Report, dated July, 2021
• Geotechnical JER 1, dated 23 May, 2022
• Geotechnical SJER, dated 13 April, 2023
• Soil Surveys Engineering letter, dated 3 July, 2023
2.0 CONSTRUCTION METHODOLOGY
The construction methodology and sequencing will be governed by the final detailed design
of the structures taking into account the varying site levels and floor levels and considering
foundation and stability requirements.
69
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Sealed Judgement Neate 1219 of 2020.pdfRelated documentApplication case desk ↗
About this file
- File size
- 94.9 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.