Minor Change Report 51987 3004 01 [As Published] · 51987.3004.01
A100 1 Proposed Floor Plan, prepared by Kings Lane Architects 28.07.2022
A500 1 Construction Details, prepared by Kings Lane Architects 28.07.2022
A800 1 Fittings & Finishes, prepared by Kings Lane Architects 28.07.2022
Landscaping Works
38. The development site must be landscaped. All works must be constructed and work
procedure undertaken, in accordance with:
a. The approved plans/documents and conditions detailed in Condition 37 of this
Decision Notice.
b. All relevant Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines.
39. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
40. Landscape works must be supervised, undertaken and certified by qualified persons*.
All works must be completed in accordance with this Decision Notice.
(* Refer to Advisory Note)
41. Where damage occurs to any Council asset as a result of the development works, it
must be repaired immediately where it creates a hazard that presents risk to person or
property. Other damage must be repaired prior to completion of works.
Retention of Existing Trees and Vegetation
42. A qualified person * must be engaged for the duration of the works to:
a. Ensure works are carried out in accordance with the approved Arborist Report
b. Oversee installation of all tree protection fencing prior to commencement of any
works onsite (including any clearing).
c. Supervise tree protection within the development site and frontages, prior to,
during and following construction in accordance with AS 4970, Protection of trees
on development sites.
d. Oversee approved tree removal in proximity to retained trees.
e. Undertake a risk assessment of all trees within striking distance of the
development works and site and carry out hazard removal and amenity pruning
in accordance with AS 4373, Pruning of amenity trees.
*(Refer to Advisory Note)
Fauna Management
43. A qualified person* must be engaged to manage fauna prior and during clearing to:
a. Ensure works are carried out in accordance with the Nature Conservation Act
1992.
b. Undertake pre-clearing inspections including fauna relocation and removal or
blocking of all vacant hollows.
c. Ensure clearing works avoids nesting times of animals and birds.
d. Co-ordinate staging and sequence of clearing with fauna protection.
e. Protect and recover fauna during clearing operations (not previously removed).
Page 7 of 8
Document Set ID: 22307808
Version: 5, Version Date: 13/03/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Report 51987 3004 01 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.