Delegated Report - Code - Planning MCU22 0207

of 7

Page text shows just the words. Original shows the document exactly as it was published.

               16.    The jetty is to be used for private purposes only with no commercial operations to be
                      undertaken.
               17.    Boat repair activities are not permitted on site.
               18.    Wastewater and sullage must only be disposed of at approved pumpout facilities.
               19.    The mooring facility must not be utilised for live-aboard purposes.
               20.    Any construction and post construction activity is not to impact on the condition of the
                      waterway, and is to be conducted so as not to breach the Environmental Protection Act EPA
                      (1994) and the Environmental Protection (Water) Policy 2009.
               21.    Certification by a Registered Professional Engineer of Queensland that states that the jetty
                      is constructed in accordance with best practice methods and is structurally sound must be
                      submitted to Council. This certification must be submitted to Council within three (3) months
                      of the completion of the works. A final inspection and approval of the structure by Council’s
                      Inspector is also required. Please contact Council’s Development Assessment Branch on
                      5329 6500 to arrange the inspection.
               22.    This approval lapses where the construction of the jetty has not commenced within two (2)
                      years of the date of issue of the approval, unless application is made and approved by
                      Council for an extension.
               23.    After completion, the proposed works must be maintained in a sound state of repair in
                      accordance with the approved plans
               5.     REFERRAL AGENCIES

               The referral agencies applicable to this application are:

                Referral Status        Referral Agency and Referral Trigger                 Response
                                       Address

                    Concurrence        SARA at DILGP Via           Planning Regulation      The agency provided its
                                       MyDAS2 at                   2017 Schedule 10, Part   response on 15 March
                                       https://prod2.devasses      17 – Tidal Works or      2023 (Reference No.
                                       s. qld.gov.au/suite/ (for   Works in a Coastal       2212-32645 SRA). A
                                       assistance, contact         Management District      copy of the response is
                                       DILGP at 5352 9701 or       [Insert trigger title]   attached
                                       email:[email protected]

               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects
                      of the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.
               2.     The approval or conditions do not absolve the owner of the land from complying with all the
                      conditions of this approval and/or relevant Council By-Laws and Policies and/or relevant
                      statues and/or statutory regulations in the execution and/or performance of said works.
               3.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.


                                                                                                       Page 6 of 7

Document Set ID: 22369420
Version: 4, Version Date: 13/04/2023
Log in to download the original file

Delegated Report - Code - Planning MCU22 0207.pdf · 376 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.