SERVICES & ORGANISATION COMMITTEE MEETING AGENDA                              8 DECEMBER 2020


Image 3: Noosaville – Eumundi-Noosa Rd Pathways




Previous Council Consideration
Nil.

Finance
The current capital delivery expenditure to 23 November 2020 is $9.8m, or 27% of the $35.2m
capital program. The delivery and completion of projects continues across the program with
ongoing recruitment of staffing resources to be finalised in the coming months to support the design
and delivery phases of the projects.
The following table and the graph shows a breakdown of expenditure as at 23 November 2020.

   Capital Works Program            Amount                                                 YTD Actual
                                                                                           Expenditure
   YTD Actual Expenditure            $9,851,670                                              27.92%

   Committed Expenditure             $3,469,333
                                                             Remaining
   Remaining Capital Expenditure    $21,961,027                Capital
                                                             Expenditure
   Full Year Budgeted Expenditure   $35,282,030                62.24%

                                                                                           Committed
                                                                                           Expenditure
                                                                                             9.83%


Risks & Opportunities
The current risk to the Capital Program is the resourcing of Design and Delivery staff. There has
been two recent resignations in this area, on top of an increased program due to the success of
recent grant announcements and COVID stimulus funding. The recruitment of replacement staff
and additional staff to cover the increased program has commenced. In further mitigating this risk,
projects have been reviewed and where necessary, projects are being re-profiled and adjusted
through the budget review process.

Consultation
External Consultation - Community & Stakeholder
Nil.


                                                                                     Page 30 of 41
Log in to download the original file

2020-12-08 Services & Organisation Committee Agenda(PDF, 2MB).pdf · 2.3 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.