Delegated Report - Code - Planning MCU25 0057, OPW25 0078 & RAL25 0010 (As Published) · MCU25/0057

of 25

Text shows just the words. Original shows the document exactly as it was published.

                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods,
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods,
                      c.      Been revised to address predicted rainfall events, and
                      d.      Achieve the desired environmental outcomes.
               34.    Council may request further controls to be installed should the implemented measures be
                      found inefficient.
               35.    The erosion and sediment control measures must be designed, installed and maintained in
                      accordance with the supervising engineer instructions and the current best practice
                      standards * (Refer to Advisory Note).
               36.    The developer must ensure non-essential exposure of soil is prevented by restricting the
                      extent of disturbance and minimising the duration of soil exposure to adverse weather
                      conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
                      to rainfall occurring.
               37.    The developer must ensure sediment does not leave the site or enter onto adjoining
                      properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
                      machinery. It is essential to implement appropriate approved erosion and sediment control
                      measures throughout the site during all phases of construction including vehicle shakedown
                      pad/grid (or similar) at the access to the construction site. Where sediments or other
                      contaminants are deposited on a road, they must be removed so as not to enter Council’s
                      drainage system or waterways.
               38.    Prior to the completion of the development and commencement of use, all site surfaces must
                      be effectively stabilised using methods which have achieved effective short-term stabilisation
                      and which will continue to achieve effective stabilisation in the medium to long-term. For the
                      purpose of this condition, an effectively stabilised surface is defined as one that does not, or
                      is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
                      lead to sedimentation, or lead to water contamination.
                      Vegetation Clearing
               39.    Removal of trees and vegetation must be undertaken by a qualified person* and must
                      include:
                      a.      No damage to vegetation for retention.
                      b.      Legal disposal of all removed vegetation and debris.

                      Fauna Management
               40.    Prior to felling or pruning, all trees are to be checked for wildlife (i.e. koalas, possums, birds
                      etc.) If wildlife is present, the tree vegetation must not be felled or pruned until the wildlife
                      has left vegetation or has been relocated by a qualified fauna spotter catcher.
                      *(Refer to Advisory Note)
                      Landscape Works
               41.    Landscape works must be supervised, undertaken and certified by qualified persons*. All
                      works must be completed in accordance with this Decision Notice.
                      *(Refer to Advisory Note)
               42.    Where damage occurs to any Council asset as a result of the development works, it must be
                      repaired immediately where it creates a hazard that presents risk to person or property. Other
                      damage must be repaired prior to completion of works.



                                                                                                        Page 20 of 25

Document Set ID: 24104255
Version: 15, Version Date: 15/10/2025

Used in these records

About this file

File size
3.6 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning MCU25 0057, OPW25 0078 & RAL25 0010 (As Published).pdf · 3.6 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.