RFI - Att 3 - Engineers Response Letter
ingeniir
The proposed development has a negligible increase in flows of only 2L/s in 1% AEP flows to the kerb so is
not considered capable producing a worsening of flows as there is minimal change to the existing catchment
characteristics.
If you wish to discuss this matter further, please contact Daniel Kenna.
Yours sincerely,
Daniel Kenna
Beng CPEng MIEAust RPEQ 15522 NER 3133685 EC 66121
for and on behalf of Ingeniir Pty Ltd
Ingeniir Pty Ltd | 221304-RFI-01
ABN: 99 642 485 363 | PO Box 988 Maroochydore QLD 4558 | [email protected] | 0404157187