Haynes Consulting Engineers Pty Ltd
ABN No. 53613630078
P.O Box 549 Noosa Heads 4567

Ph: 0432 784 150




        2nd March 2018                                                             File No:   1707


        Noosa Shire Council
        (by email)

        Attention:      Patrick Murphy

        Dear Sir,

                      RAL17/0511 – Information Request Response for Subdivision,
                                       11 Church Street, Pomona

        In response to the information request dated 8-12-17 we enclose the latest information
        requested in italics, with numbered responses in bold text.

        Flooding

        Information Required

            1. Provide suitable flood modeling for the southern gully.

            1. We enclose BSM report Flood Levels and Impacts report (Final) dated 21-2-
               2018.

            2. Provide amended plans that are based on the flood modeling for the site as a whole
               (northern and southern gullies) and include:

                     a. Bearings and distances for the 1%AEP flood line with any areas below the
                        flood line included in a “drainage easement”.
                     b. The area available within the lots above the 1% AEP floodline.

            2. Please refer to plan 1707-02B.
                  a. A bearing and distance plan for entire flood line with so many changes
                     in direction would be very complex and difficult to read, however the
                     northern boundary of lots 2 and 3 is along flood line and shows
                     distances. To comply with the request in a simpler form we have shown
                     the 1% AEP flood line and drainage easement on plan 1702-02B, the
                     surveyor will formalize an accurate drainage easement based on 1%
                     AEP flood line at time of plan seal based on current BSM flood study.
                  b. The area available within lots above 1% AEP floodline is shown on plan
                     1707-02B.




        J:\HCE files 19-12-17\APROJECTS\1707 MJ 4 lots Pomona\CORROUT\RAL 17 0511.docx
Log in to download the original file

RAL 17 0511 RFI.pdf · 189 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.