6. Geotechnical Recommendations
General recommendations to help maintain the stability of the site are given in the document Some
Guidelines for Hillside Construction, which is attached.
6.1 Development Limitations
It is anticipated earthworks may include cuts for the basement level of up to about 7 m deep with only
minor filling expected to be required up to about 1 m in height to form finished surface levels. Should
proposed cuts/fills exceed this quantity, Tectonic must assess the impacts on slope stability before
construction.
6.2 Earthworks
6.2.1 Site Preparation and Trafficability
Following removal of the existing buildings and associated construction elements (e.g. footings, services,
etc.), any tree stumps and large roots should be ‘grubbed out’. Any organic rich topsoil and uncontrolled
fill should then be stripped and set aside. Based on site observations and boreholes, topsoil (where
present) stripping depths should generally range between 0.1 m and 0.2 m BGL, with uncontrolled fill
encountered to depths of between 0.4 m to 0.6 m BGL. It is noted that deeper pockets of topsoil or
uncontrolled fill may exist and deeper, localised grubbing out of tree roots may be required.
Rubbish was noted during soil testing by ASI at a depth of 0.7 m BGL. Three boreholes (designated BH2,
BH2A and BH2B) were drilled by Tectonic in this area to delineate the extent of this rubbish, however, no
deleterious material was encountered at those locations. It would be prudent to allow to investigate this
area further by excavation of test pits prior to construction commencing to assess if rubbish is present
and to what extent.
Topsoil materials must not be used in structural fill; however, may be placed across landscaping areas.
Unsuitable natural material such as any saturated, loose or soft materials encountered should also be
removed during subgrade preparation for bulk earthworks.
It should be noted that compaction of such relatively ‘clean’ sands as structural fill requires the addition
of substantial volumes of water (‘flooding’) combined with the use of vibratory compaction equipment
(typically a vibrating plate). Care must be taken with the use of vibratory equipment (e.g. compactors or
sheet piling) to ensure that there are no adverse impacts on surrounding structures. The impacts from
ground vibration must be closely monitored and managed during construction. It would be prudent to
conduct a dilapidation survey of neighbouring structures prior to commencement of construction.
The exposed natural subgrade following excavations will likely be in a loose condition and must be
compacted by several passes of a vibrating plate or minimum 4 tonne vibrating smooth drum roller, in
conjunction with surface application of ample water, to achieve the required compaction.
Due to the potential for poor trafficability during placement of a minimum 150 mm thick granular
working platform may be required on soil subgrades along haul roads and across laydown areas.
Specific platform design would be required prior to mobilisation and trafficking of any heavy mobile
plant on the site (e.g. cranes, concrete pumps or piling rigs).
Proposed Unit Development
30 September 2024 | 24265-001-Rev0 11
Document Set ID: 23376055
Version: 1, Version Date: 28/11/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.