Court Judgement 01032021 Cases - Appeal 20-034 · 132010.105.01
instrument made by a local government that is a planning scheme, a temporary local
planning instrument or a planning scheme policy.
78. A “planning instrument” is also defined in section 8 of the PA to be an instrument that sets
out policies for planning or development assessment.
79. Section 30 of the BA also refers to a resolution of the relevant local government.
Development approvals can be granted by resolution of a local government or by
delegated authority to an officer of the local government. While no evidence was
presented to the Tribunal with respect to whether the Change Approval was given by the
Respondent by delegated authority or at a local government meeting, the Tribunal has
considered the Respondent’s meeting agendas for 202012 and notes that no meeting was
held on 26 October 2020, being the date the Respondent granted the Change Approval.13
On this basis, conditions 23 and 24 of the Change Approval were not imposed pursuant
to a resolution of the Respondent.
80. Conditions 23 and 24 of the Change Approval are clearly not a “local planning instrument”,
nor do they fall within any of the other laws or documents that are defined to be building
assessment provisions in section 30 of the BA.
81. Accordingly, the Tribunal finds that conditions 23 and 24 of the Change Approval are not
building assessment provisions as defined by section 30 of the BA.
82. Section 31(3) of the BA, relevantly provides that the effect of a building assessment
provision mentioned in section 30(a) to (d), (f) or (g) can not be changed under a local
law, local planning instrument or local government resolution.
83. Section 31(4) of the BA, relevantly provides that a local law, local planning instrument or
local government resolution must not include provisions about building work, to the extent
a building assessment provision mentioned in subsection (3) applies to the building work.
84. Section 31(5) of the BA, relevantly provides that to the extent a local law, local planning
instrument or local government resolution does not comply with subsection (4), the local
law, local planning instrument or local government resolution is of no effect.
85. Given that conditions 23 and 24 of the Change Approval are not a local law, local planning
instrument or a local government resolution, nor are they building assessment provisions,
the Tribunal is satisfied that section 31 of the BA does not apply to negate the effect of
the conditions.
86. Finally, at the hearing, Mr Murphy, on behalf of the Respondent, made oral submissions
that conditions 23 and 24 of the Change Approval met the conditions test in section 65 of
the PA.
87. In the absence of evidence presented by the Appellant to the contrary, the Tribunal
accepts Mr Murphy’s evidence and is satisfied that conditions 23 and 24 of the Change
Approval are lawfully imposed pursuant to the PA.
The structures within the FPZ
88. While the Appellant’s grounds of appeal and the Appellant’s Final Submissions turn on a
legal interpretation of sections 30 and 31 of the BA, at the hearing of the appeal, the
parties also considered at length, the location of the shed and the proposed new patio
roof within the FPZ.
12
Pursuant to section 249 of the PA, the Tribunal has broad powers to inform itself in the way it considers appropriate when
conducting a tribunal proceeding.
13
See page 1 of the Decision Notice issued by the Respondent and dated 29 October 2020.
- 10 -
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Court Judgement 01032021 Cases - Appeal 20-034.pdfRelated documentApplication case desk ↗
About this file
- File size
- 562 KB (small file)
- File type
No other editions are linked here.