Delegated Report - Code - Planning OPW21 0187

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Author	Development Engineer, Laurie Schreck
Development Assessment

APPLICATION DETAILS
Application No.	OPW21/0187
Applicant	Callaghan & Toth Consulting Engineers
Proposal	Operational Works - Drainage Works, Stormwater, Vehicle Crossover
Properly Made Date	24 June 2021
Information Request Date	15 July 2021
Information Response Date	16 July 2021
Decision Due Date	27 August 2021
Report Completed Date	19 July 2021
Report Reviewed By	Mark Lewis

PROPERTY DETAILS
Property Address	19 Key Ct Noosa Heads Qld 4567
RP Description	Lot 174 RP 884826
Land Area	1268.0000 m²
Existing Use of Land	Residential (Lot 1) and Vacant (Lot 2)

STATUTORY DETAILS
SEQRP Designation	Urban Footprint
Zone	Low Density Residential
Precinct	Not Applicable
Local Plan Area	Not Applicable
Overlays	Land Subject to Acid Sulfate Soils – 5m AHD or Below Flood Hazard – Flooding and Inundation Extent
Assessment Type	Code
PROPOSAL
The application seeks approval for an Operational Works - Drainage Works, Stormwater, and Vehicle Crossover.
The locality and proposal plan are included below.
Figure 1 – Locality

Figure 2 – Site Plan

site details
Background
This Operational Works application has been submitted as part of the requirements set in the conditions of the higher order approval RAL20/0025.
Site Description
The subject site has been subdivided into two lots. Lot 1 to the west which has the existing dwelling still remaining, requires the construction of a concrete driveway and vehicle crossover to the dwelling. The higher order Reconfigure of Lot approval requires the crossover to be installed without disturbance to the existing street trees. Consequently the crossover meanders to avoid the street trees and line up with the dwelling garage. Verge grades are relatively flat so a compliant crossover can be achieved.
Lot 2 to the east has had the dwelling removed and is currently vacant. There is an existing underground stormwater line running along the eastern boundary. The higher order RAL approval requires the construction of a drainage swale along the eastern boundary to allow for overland flow.
Surrounding Land Uses

assessment
Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following statutory planning instruments to the extent they are relevant to the development:
State Planning Policy;
South East Queensland Regional Plan;
Planning Regulation 2017; and
Noosa Plan 2020.
Noosa Plan 2020
The following codes from the Noosa Plan 2020 are applicable to this development:
Driveways and Parking Code; and
Water Quality and Drainage Code.
cONSULTATION
Referral Agencies
Not applicable.
Internal Council Referrals
Not applicable.
conclusion & reasons for decision
The proposed development generally complies with the requirements of the planning scheme and does not raise any significant issues that cannot be addressed by reasonable and relevant conditions. The application is therefore recommended for approval.
The report is provided in accordance with Section 63(5) of the Planning Act 2016.
RECOMMENDATION
With regard to Application No OPW21/0187 for an Operational Works - Drainage Works, Stormwater and Vehicle Crossover situated at 19 Key Ct Noosa Heads Qld 4567 and described as Lot 174 RP 884826, it is recommended the application be approved in accordance with the following details for the Decision Notice:
application details
Application No:	OPW21/0187
Street address:	19 Key Ct Noosa Heads Qld 4567
Real property description:	Lot 174 RP 884826
Planning Scheme:	Noosa Plan 2020 (25 September 2020)
Decision details
Council decided to issue the following type of approval:
Development Permit for approval for Operational Works - Drainage Works, Stormwater and Vehicle Crossover
CURRENCY PERIOD of approval
The currency period for this development approval is stated in the conditions below.
assessment manager conditions
APPROVED PLANS
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
2103-01	C	Proposed Lot Configuration Key Court, Noosa Heads – Site Plan & Drawing Index as prepared by Callaghan and Toth	June 2021
2103-03	C	Proposed Lot Configuration Key Court, Noosa Heads – Easement Overland Flow Path Detail as prepared by Callaghan and Toth	June 2021
2103-04	C	Proposed Lot Configuration Key Court, Noosa Heads – Swale Longitudinal Section as prepared by Callaghan and Toth	June 2021
2103-05	C	Proposed Lot Configuration Key Court, Noosa Heads – Easement Cross Sections as prepared by Callaghan and Toth	June 2021
N/A	N/A	Arboricultural Report and Tree Protection Methodology/Plan as prepared by Australian Tree Contractors & Arboricultural Consultants Pty Ltd	22 June 2021
CURRENCY PERIOD
The Currency Period for this development approval lapses if the development has not substantially started by 27 July 2023, unless an application to extend the currency period is approved by Council.
SITE SPECIFIC CONDITIONS
Any disturbance to the verge area during the works must be reinstated to match the existing verge treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be maintained by the developer until established.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
Tree protection fencing must be installed under the supervision of the Project Arborist in accordance with the approved Arboricultural Report.
Copies of the approved plans, duly signed by the consultant Registered Professional Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer at the “pre start” meeting.
A condition report of the drainage system must be completed for agreement at the prestart meeting. The condition report is to include a CCTV inspection of the existing pipe and must include at least the section of RCBC between the pit on Key Court and the outlet.
A condition report consisting of photographs of the frontage of the site and the property boundary adjacent the proposed drainage swale must be completed and submitted to Council at the prestart meeting / prior to any works commencing.
Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting.
Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The pre-start meeting must include the relevant parties or their proxy for the following aspects of the works:
Civil engineering works;
Erosion and sediment control works;
Other relevant parties
A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following:
Traffic Management during all aspects of the construct phase including:
A Traffic Management Control Plan in accordance with Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction;
Maintenance of safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased;
Proposed fencing to the works during the construction phase of the development;
No queuing of trucks is permitted on residential streets, especially prior to 7.00am. Further parked trucks must have engines turned off.
Maintenance and protection of water quality and existing drainage lines through the construction site through the implementation of appropriate erosion and sediment control measures; and
Include a post out to the local residents and businesses advising of the proposed works, the expected time frames and the site contact details.
Bonds
A site control and/or compliance bond of $5000 is to be submitted to Council prior to the pre-start meeting. The pre-start meeting will only be held once Council's Construction Engineering Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with these conditions or any additional inspections incurred for substandard work or work undertaken not in accordance with this permit.
Bonds must:
Meet the requirements of Council’s relevant Planning Scheme Policy for performance and uncompleted works;
Be calculated using a schedule of works and relevant bond equation;
Include GST;
Have approval of the bond calculations and amount from Council prior to lodgement;
Be lodged with Council and accompanied by the Bond Administration Fee/s; and
Be requested for release by writing to Council, when relevant approval requirements have been met.
Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to Council in writing within five business days of the change occurring.
Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development.
The works associated with the overland flow path must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers.
All works must be constructed and work procedure undertaken in accordance with:
The approved plans/documents and conditions detailed in this Decision Notice;
The relevant conditions of the higher order Reconfiguration of Lot approval RAL20/0025 to which this approval relates;
All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines; and
The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site.
Works within Road Reserve/Reinstatement
Safe pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with.
All frontage works must match neatly with existing road and verge/footpath features. Additional works beyond the frontage may be required to provide an acceptable transition to existing road and verge/footpath profiles.
Electrical conduits or other services proposed to be installed within existing and proposed road reserves under existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is not permitted, unless specifically approved by Council.
Site Access and Driveways
Driveway crossovers must be constructed in accordance with Council’s Standard Drawings RS-049 and RS-050.
The following must be complied with during the construction of the required crossover/driveway:
The driveway surfacing must consist of either an approved hot mixed asphaltic concrete or patterned/plain concrete;
The driveway must be constructed so as not to concentrate stormwater runoff onto neighbouring properties;
Underground service conduits for water supply, electricity and any other services must be provided as part of the access driveway; and
The property access must be located a minimum of 1m clear of existing power poles, streetlights or other signage. The developer is responsible for any necessary relocation of existing services to provide this clearance and must contact the relevant service authorities and comply with their requirements in relation to these works.
Earthworks
Slope and batters are a maximum grade of:
1 in 6 where in proximity to waterbodies;
1 in 4 for grassed areas;
1 in 3 for planted areas; and
1 in 2 for combined structural engineering and planting solutions.
With the exception of the swale batters which must be constructed generally in accordance with the approved plans.
Stormwater Drainage
Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets.
Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (e.g. by blocking or interfering with natural overland flows).
Construction of all internal stormwater drainage works must comply with the relevant section/s of Australian Standard AS/NZS 3500.3.
Prior to the completion of the development, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium- to long-term (refer to E&SC Advisory Notes). For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination.
Erosion and Sediment Control
Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection Regulation 2019) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination.
Sediment and erosion control measures must be in place prior to works commencing. If such measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such fines can be issued if sediments from the site are found to enter or have the potential to enter Council’s stormwater system, natural waterways, any downstream stormwater filtration system or adversely impacting on other properties.  The sediment and erosion control design and measures have NOT been approved, it is the site's Supervising Engineer who is responsible for ensuring that the sediment and erosion control measures have:
Been duly designed and revised by a suitably qualified person and constructed in accordance with "best practise" methods;
Been revised to address predicted rainfall events, and
Achieve the desired environmental outcomes.
Council may request further controls to be installed should the implemented measures be found inefficient.
The erosion and sediment control measures must be designed, installed and maintained in accordance with the Supervising Engineers instructions and the current best practice standards * (Refer to Advisory Note).
The developer must ensure non-essential exposure of soil is prevented by restricting the extent of disturbance and minimising the duration of soil exposure to adverse weather conditions and effectively turf, cover or stabilise any disturbed area without delay and prior to rainfall occurring.
The developer must ensure sediment does not leave the site or enter onto adjoining properties or Council’s drainage system or natural waterways due to surface runoff or on tyres of vehicles and/or machinery. It is essential to implement appropriate approved erosion and sediment control measures throughout the site during all phases of construction including vehicle shakedown pad/grid (or similar) at the access to the construction site. Where sediments or other contaminants are deposited on a road, they must be removed so as not to enter Council’s drainage system or waterways.
Prior to the completion of the development and commencement of use, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term. For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination.
FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
Certification
Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit.
Upon completion of the works and prior to the sealing of survey, a final condition report of the underground drainage system must be provided to Council. The report must include CCTV footage of at least the section of RCBC between the pit on Key Court and the outlet.
As Constructed Plans and ADAC XML Files (Council)
Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory “As-Constructed” records must be submitted to Council. The bundle of “As Constructed” information shall include:
As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed) prepared in accordance with industry standards and recorded in “MGA - UTM56 / GDA94” projection.
Please Note: Further information and advice relating to the as-constructed drawing presentation, as-constructed survey capture and associated guidelines for preparation of a compliant ADAC XML digital file are available on the webpage titled “As-Constructed Guidelines” and accessible at the Noosa Council Website: Planning & Development / Development Tools & Guidelines / As-Constructed Guidelines.
The “As-Constructed” drawings will require certification by a:
Qualified experienced Civil Engineer (RPEQ) confirming design intent and conformance with applicable standards and specifications, along with the relevant descriptions of assets, services and structures and;
Licensed Surveyor in regard to the cadastral and locational information, levels and applicable survey datum.
The data must be in accordance with Council’s “Planning Scheme Policy 6 – Engineering Design Standards”, and fully detail the levels for all engineering works including but not limited to the drainage network and structures, finished ground and pavement surface levels.
A final inspection and approval of the new driveway and completed reinstatement works by Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the inspection.
referral agencies
Not applicable.
Advisory notes
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
General Advisory Notes
As this driveway is a private structure, the owner bears full responsibly for the standard of its construction, maintenance and any liabilities associated with its construction. It is recommended that professional advice be sought for the construction of the driveway to ensure that the driveway is constructed in accordance with standard drawings RS-049, RS-050 and RS-056 (a copy is attached).
Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works.  A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design.  Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent.
Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time.
Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees.
Prestart, On and Off Maintenance Inspections Request
Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5 business days’ notice of preferred inspection time.
If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time.
A minimum maintenance period of 12 months will apply to all municipal works and thereafter until such time as the works are performing in accordance with the approved design unless noted otherwise
Environmental Advisory Notes
The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
Accepted best practice standards include International Erosion Control Association Australasia Best Practice Erosion and Sediment Control
Qualified Person, for the purpose of erosion and sediment control is a Certified Professional in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional Engineer of Queensland (RPEQ).
As a general rule, a site is determined to have achieved effective short-term stabilisation if at the time of the plan sealing inspection:
Methods of stabilisation are:
Appropriate for slopes and slope lengths; and
Are consistent with best practice environmental management practices such as in the Manual for Erosion and Sediment Control or the IECA Manual; and
Stormwater runoff from the site is not currently, and is not likely to result in visible evidence of sedimentation or erosion, or lead to water contamination.
If at the time of request for plan sealing, the method of short-term stabilisation has not achieved a level of stability that Council's Officers believe will have a high probability of achieving long term stability (i.e. until house construction has occurred on all lots), Council Officers may take the following matters into consideration in determining whether the site is capable of achieving medium to long-term stability:
Evidence that the site has been effectively stabilised in the short term;
Evidence that soil has been adequately ameliorated;
Evidence that seed of annual and perennial grass species has been applied at an adequate rate; and
That grass seed has germinated at a density that is likely to achieve an effective grass cover.
For example, while hydromulch can provide an immediate and effective stabilising cover to soils, the protective cover can be relatively short-lived if vegetation fails to establish before the thin layer of mulch decomposes. So if hydromulch is selected as the method of temporary short term stabilisation, Council Officers will seek to confirm that perennial as well as annual grasses are well established at the time of plan sealing to reduce the risk of instability of the site in the medium to long term. As a general rule, hydromulch will only be accepted as a “patch” fix and should comprise no more than 20% of the exposed site area due to the high risk of failure. Due to the requirement to progressively stabilise exposed areas, it is not envisioned that this will present any difficulties for an appropriately managed and compliant site
property notes
Not applicable.
VARIATION approval details
Not applicable.
further development permits required
Not applicable.
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

[word/footer1.xml]
Page 4 of 12

[word/header1.xml]
3

[word/header2.xml]
DEVELOPMENT ASSESSMENT DELEGATED REPORT

[Attachment: image1.png (image text)]
Australig

Ieee
fafienle. 4 Noosa Weed ekecscomnestaurant & Bar
‘ nag ersaelin

SRE oc:

essen

ia, Noosaklead
rai

 


[Attachment: image2.png (image text)]
  
      
 
 
 
 
  
 
  
 
  
 
 

LoT 283
RP881375 ence as per perat on | NO. 17
LoT 172

RP214930

=7=

 

 

72 am TO Be REMOVED.
FROM FLOOD PLAN T0 FOR
OVERLAND FLOW PATH

 

 

 

 

 

 

on
ET MEW CROSSOVER TONE STO]
(WG 9005 To avo Taee ROOTS |
DRIVEWAY TOBE CONSTRUCTED
UNDER SUPERVISION OF ARBORIST
5 PER ARBORST REPORT »

 

 

LoT 175
\ N21858

ow


[Attachment: image3.png (image text)]
Zones
Low Density Residential
Medium Density Residential
High Density Residential
Tourist Accommodation
MI Major Centre
MM Districe Centre
lM Local Centre
Neighbourhood Censre
Low Impact Industry
Medium Impact Industry
Recreation and Open Space
IB Environmental Management and Conservation
Community Facilities
IM Innovation
Rural
I Rural Residential
Community Facilities Label Legend

erlay Maps

   

   
   

Q 2
toendrees —70N2058

 

1
somiziesr

    
    
 
  
 

 
 

sper e744
1s
soonP20e7e4 a
ia . ‘aon 880
“0
sesnzv080
seantese
2
9 eon i089
t 3 sauizi090
Log in to download the original file

Delegated Report - Code - Planning OPW21 0187.docx · 2.3 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.