2014-06-17 Infrastructure and Services Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
NOOSA COUNCIL - PROJECT DESIGN & DELIVERY 2013-2014
As at 5 June 2014 Printed: STAGE
Scope & Brief Development
Design Finalisation
Design Review
Issues Status
Construction
Procurement
Budget
Finalisation
Handover
Original balance
Design
Work Order Project Adjusted
Project Description Manager Project Actual Costs Commitments Actual Total (Adjusted Staff Allocated Staff task updates
Number Code Budget (BR1)
Budget budget -
Actual Total)
BRIDGES
Forward planning for bridge rehabilitation program Bryan OConnor CM006 100718 $10,000 $50,000 $5,045 $39,339 $44,384 $5,616 Adam Britton Level 3 inspections to Witta, Sheraton, Doonella completed. Testing requirements to be sent to specialist testing consultants.
Timber bridge inspections in progress.
Wayne Brogden Need to review inspection schedule for all bridges
Noosa Pde Munna Point bridge - Investigations and preventative works Ross Sanderson CM007 100719 $250,000 $250,000 $29,352 $31,858 $61,210 $188,790 Adam Britton Detail design and specification in progress ahead of tender preparation.
COASTAL, CANALS & WATERWAYS
David Low Way, Beach Access 49 refurbishment Ross Sanderson CM008 100720 $45,000 $55,000 $48,231 $0 $48,231 $6,769 Dallas Bickley
Work completed.
Gympie Terrace and William Street revetment wall and pathway rehabilitation Bryan OConnor CM009 100721 $50,000 $50,000 $9,121 $0 $9,121 $40,879 Dave Shing Design completed. Prescribed tidal works application to be prepared and submitted. Letter issued to Driscol re Council intention
to carry out works. Project to be constructed 14/15
Munna Point Holiday Park shoreline protection - design Bryan OConnor CM0010 100722 $50,000 $15,797 $19,530 $0 $19,530 -$3,733 Dave Shing Key stakeholder meeting for July.
Noosa Dog Beach Shoreline Erosion Management Plan Coastal Monitoring Bryan OConnor CM0011 100723 $20,000 $20,000 $3,390 $34,882 $38,272 -$18,272 Dave Shing University Sunshine Coast monitoring (ongoing). Monitoring received and currently under review with Department of
Environment and Heritage Protection
Noosa River Mouth groyne and rock wall rehabilitation Bryan OConnor CM0012 100724 $100,000 $125,000 $120,373 $0 $120,373 $4,627 Dave Shing
Work completed.
Noosa Waters revetment walls rehabilitation Ross Sanderson CM003 100725 $1,300,000 $1,300,000 $883,583 $386,983 $1,270,566 $29,434 Adam Britton Works in progress. Stage 1 works complete. Critical sections of Stage 2 in Western lake completed. Advice to residents issued.
Expected completion April 2015.
Coast guard tower rehab $0 $950 $950 -$950
COMMUNITY FACILITIES
Peregian Surf Life Saving Club Public Amenities - Planning & Design Ross Sanderson CM0013 100726 $15,000 $15,000 $202 $0 $202 $14,798 Ross Sanderson Project to remain on hold until 14/15
HOLIDAY PARKS
Noosa North Shore Beach Campground - Upgrade Septic Treatment System Allan Hazell CM0014 100756 $90,000 $49,500 $37,813 $6,154 $43,968 $5,532 Allan Hazell
(plumbing services) Work completed.
Noosa River caravan park power pole works Clint Irwin 100756 $0 $0 $4,600 $0 $4,600 -$4,600
ENVIRONMENTAL
Purchase of biodiversity land $0 $57,700 $9,887 $200 $10,087 $47,613
IT MAJOR PROJECTS
IT MAJOR PROJECTS Justin Thomas 100728 $2,300,000 $2,098,464 $142,239 $2,240,703 $59,297
PARKS & PLAYGROUNDS
Cooroy Skate Park Refurbishment Ross Sanderson CM001 100729 $34,000 $44,000 $6,222 $31,740 $37,962 $6,038 Dallas Bickley Construction start date10th June 2014
Gympie Tce Furniture Refurbishment Ross Sanderson CM0015 100730 $50,000 $50,000 $30,886 $4,516 $35,402 $14,598 Dallas Bickley Work in progress
Pomona Community House BBQ Relocation Ross Sanderson CM0016 100731 $12,000 $0 $0 $0 $0 $0 Dallas Bickley Project deleted
Noosa Heads Lions Park Wash down area Ross Sanderson CM002 100732 $30,000 $21,000 $4,990 $13,942 $18,932 $2,068 Dallas Bickley Work completed.
Peregian Beach Playground Refurbishment Ross Sanderson CM0017 100733 $30,000 $30,000 $25,166 $300 $25,466 $4,534 Dallas Bickley
Work completed.
Shade Sail Replacement Seagull Park
PATHWAYS & ENABLING FACILITIES
-$20,337 Ross Sanderson
Charles Street, Cooran pathway improvements Nigel Walker CM0018 100734 $30,000 $60,000 $61,102 $19,235 $80,337 Work completed.
$46,884 Ross Sanderson Investigations reveal low warrant for previously scoped project. TIDS funds to be redirected to higher priority projects.
Station Street, Pomona pathway improvements Nigel Walker CM0019 100735 $100,000 $50,000 $3,116 $0 $3,116
Weyba Creek Boardwalk rehabilitation stage 1 Nigel Walker CM0020 100736 $20,000 $20,000 $417 $0 $417 $19,583 Dallas Bickley Scope - timing to be advised
Gibson Road (Eumundi Noosa Rd to Thomas St) - On road cycle and pedestrian $432,871 Ross Sanderson Design completed. Documents issued to council crews for construction.
Nigel Walker CM0021 100737 $440,000 $440,000 $7,129 $0 $7,129
improvements
Sunshine Beach State School safety improvements Nigel Walker CM0022 100738 $90,000 $90,000 $3,268 $2,273 $5,541 $84,459 Ross Sanderson Design completed. Construction commenced.
$2,149 Bryan O'Connor
Edwards St Sunshine Beach Pathway Bryan OConnor $21,500 $19,351 $19,351 Work completed.
PUBLIC TRANSPORT INFRASTRUCTURE
$378 Adam Britton
Noosa Junction Mini Bus Shelter - Panels for weather protection Nigel Walker CM0023 100739 $25,000 $25,000 $24,622 $0 $24,622 Work completed.
Noosa Parade Bike lanes. / transit hub Nigel Walker CM0024 100740 $300,000 $5,000 $1,322 $3,300 $4,622 $378 Ross Sanderson Project deleted
SEALED ROAD NETWORK
Annual sealed road renewal and rehabilitation program Allan Hull CM0025 100741 $500,000 $500,000 $49,407 $424,027 $473,434 $26,566 Allan Hull Works carried out to Eenie Ck Rd (not captured in costs as yet)
Sealed road pavement surveys and investigations Bryan Oconnor CM0026 100742 $60,000 $60,000 $1,321 $21,250 $22,571 $37,430 Bryan O'Connor Network pavement investigations to be commissioned shortly.
SPORTS GROUNDS & FACILITIES
Noosa District Sports Complex (Cricket Oval) Ross Sanderson CM004 100743 $30,000 $30,000 $13,069 $20,574 $33,643 -$3,643 Dallas Bickley Construct Start Date for 6 x 9 storage shed mid June. Expect completion end June.
STORMWATER DRAINAGE
$1,061 Adam Britton Flood mitigation analysis completed. Additional less impact options under review. Grant application submitted. Concept design
Daintree Estate - Flood mitigation planning and design Ross Sanderson CM0027 100744 $50,000 $45,000 $16,439 $27,500 $43,939 prepared. Negotiations with QNPWS commenced. Targeted stakeholder consultation in progress.
Gympie Terrace pipe rehabilitation - investigation and design Ross Sanderson CM005 100745 $25,000 $25,000 $9,237 $0 $9,237 $15,763 James Bruton Additional pipe cleaning and CCTC ongoing.
Adam Britton Reviewing CCTV information to ascertain scope for next year
$7,275 Adam Britton Flood mitigation analysis completed. Grant application submitted. Concept design prepared. Progress to detailed design.
Rifle Street Pomona - Flood mitigation planning and design Ross Sanderson CM0028 100746 $50,000 $40,000 $21,450 $11,275 $32,725
Seaview Creek - open drain civil works Ross Sanderson CM0029 100747 $25,000 $53,500 $3,511 $6,196 $9,707 $43,793 Ross Sanderson Design completed. Construction prestart 6 June. Expect commence onsite 16 June 14. Met with local Bushcare group. Plants pre-
purchased.
Stormwater replacement program (non pipe work) Allan Hull CM0030 100748 $75,000 $75,000 $71,899 $0 $71,899 $3,101 Allan Hull
Work completed.
STREETSCAPE & ROAD CORRIDORS
Cooroy - Noosa Road (St Andrews Drive - Gyndier) Nigel Walker CM0031 100749 $50,000 $50,000 $3,941 $23,445 $27,386 $22,614 Dallas Traffic study completed. Engaged GHD for design.
Noosa - Eumundi Road (Eenie Ck - Walter Hay) Nigel Walker CM0031 100749 Dallas Waiting on setout quote
TRANSPORT INFRASTRUCTURE MANAGEMENT
Eenie Creek road / Langura Street Intersection safety upgrades Nigel Walker CM0032 100750 $8,000 $25,500 $2,772 $2,282 $5,054 $20,446 Dallas Engaged Callaghan & Toth Engineers. Draft design due 6 June 14.
Eenie Creek road / Walter hay Drive Intersection safety upgrades Nigel Walker CM0033 100751 $15,000 $29,500 $1,262 $2,578 $3,840 $25,660 Dallas Engaged Callaghan & Toth Engineers. Draft design due 6 June 14.
Weyba Road / Reef Street intersection improvements PIP Nigel Walker CM0034 100752 $125,000 $125,000 $3,993 $1,100 $5,093 $119,907 Scott Morgan Traffic study completed. (No linemarking changes required).
Page 57 of 86
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.