The average speed and therefore travel time does not need to be adjusted to
accommodate the electric bus technology
Disadvantages
Since Route 627 only operates every 30 minutes, a high frequency service of every 15
minutes would not operate between Tewantin and Noosa Junction even if multiple electric
buses were available for the trial
Vehicle block is linked to other routes so there will be some de-optimisation of the Sunbus
network to have a separate fleet and driver shifts designated to Route 627
3.3 Assessment of the route options for the electric bus trial
A high-level assessment of the three route options for the electric bus trial was conducted
using a Multi-Criteria Analysis (MCA) approach with the following key criteria:
Potential to maximise service coverage and patronage on the electric bus
A range of operating environments with different terrains, street types and speed limits to
test the physical capacity of the electric bus
Operational efficiency with suitable locations for recharging stations and layovers
Minimise network changes and implementation costs without community consultation
Ease of implementation for the bus operator with driver training and for the electric bus
supplier to install the recharging infrastructure
The results of the assessment are provided in Table 3. Option 3 has the most criteria scored
as Good and Option 1 is the least desirable.
Table 3 Assessment of the Routes for the Electric Bus Trial
Option 1 Network Option 2 Routes Option 3 Route
Key Criteria
Redesign 626 and 627 627 Only
Service coverage and patronage
Range of operating environments
Operational efficiency
Minimise network change
Ease of implementation
Legend
Score Description of Scoring
Good
Average
Poor or not acceptable
3.4 Recommended bus route for the electric bus
Route 627 as shown in Figure 7 is recommended for the electric bus trial because:
It is an existing route that already services the busy tourist and visitor precincts connecting
Tewantin, Noosa Heads and Noosa Junction with no requirement for the rest of the
TransLink bus network to be modified. Community consultation on the route is not
required as the existing route, bus stops and service frequencies are not affected
GHD | Feasibility Study of Electric Bus Routes in Noosa - Planning Report | 15
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.