Performance Outcomes Acceptable Outcomes Response
Filling and excavation for Filling and excavation for The development involves
operational works do not directly, operational works is designed excavation works to facilitate the
indirectly or cumulatively cause and constructed to ensure basement level. The
adverse impacts external to the overland flow and/or flooding is development be designed via a
development site by: not worsened, impeded, or condition to ensure that the
otherwise diverted to adversely construction of the basement will
a) causing ponding of water
affect other properties or not result in overland and/or
on the site or nearby land;
downstream environments. flooding is worsened or diverted
b) increasing flooding, which to other properties.
adversely affects the
safety or use of any land
upstream or downstream;
or
c) adversely affecting the
flow of water in any
overland flow path.
Medium Density Residential Zone Code 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.