MCU15/0058
Noise level at a commercial place measured as the adjusted
PERIOD
maximum sound pressure level (Lamax, adj,T)
7am – 6pm Background noise level (LAbg,T) plus 10 dB(A)
6pm – 10pm Background noise level plus10 dB(A)
10pm – 7am Background noise level plus 8 dB(A)
7. When requested by Noosa Council, a Noise Impact Assessment Report (NIAR)
showing monitoring and recording of noise levels must be undertaken to
investigate any non-vexatious complaint caused by noise emissions from
operations of the facility. Such monitoring must be undertaken and completed
within a reasonable and practicable timeframe as nominated by Council and be
performed by a suitably qualified and experienced person.
8. The NIAR is to be submitted to Council detailing the results of such monitoring and
recommendations for any measures to achieve compliance with limits outlined in
Table 1 of this Decision Notice.
9. Rectification works will be required within a reasonable timeframe as set by
Council where equipment, air conditioning units, motors, electrical generators,
compressors, etc exceed the Noise Limits of Table 1.
10. Measurement of sound pressure levels (adjusted for tonality and impulse) must be
in accordance with Australian Standard AS1055.1 “Acoustics – Description and
measurement of environmental noise – General procedures”.
11. For the purpose of measuring and certifying relevant noise conditions and
reporting (eg. equipment, air conditioning units, motors, electrical generators,
compressors, etc), a suitably qualified person is either:
i. a Registered Professional Engineer of Queensland, or
ii. an environmental consultant with a minimum of 3 years current experience in
the field of acoustics.
Health and Safety
12. The development must not, at any time during the life of the development, result in
human exposure to environmental electromagnetic emissions exceeding the
current regulations, standards and/or recommendations of the Australian Radiation
Protection and Nuclear Safety Agency (ARPANSA). The carrier of the
infrastructure must provide, prior to commencement of use/transmission, written
certification to demonstrate compliance with this condition. Certification must be
based on full power transmission.
13. Warning information signs and security fencing must be provided on the site to
prevent unauthorised entry. Fencing must be camouflaged through the use of
colours, materials and screening vegetation to blend the fence into the visual
landscape.
Colours and Finishes
14. The monopole and associated panels must be finished in colours that blend in
visually into the landscape.
Cessation of Use
15. The telecommunications facility must be removed from the site upon cessation of
the use.
Page 3 of 17
Document Set ID: 20336344
Version: 8, Version Date: 09/06/2017 Print Date: 9 June 2017, 3:44 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix A Negotiated Decision Notice.pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.