O2 stormwater Report Rev Oct 2015

Attached to the e-mail MCU14/0039 - Response to Information Request.

of 38

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Table 8 - Water Quality Objectives.

                         Minimum reductions in Mean Annual Loads from unmitigated catchment

   Total Suspended Solids                Total Phosphorus                  Total Nitrogen           Gross Pollutants
             (TSS)                              (TP)                           (TN)                      > 5mm

              80%                               60%                            45%                          90%



4.4.3.       Treatment Options
MUSIC modelling has been undertaken to assess the treatment system requirements to achieve the above
water quality objectives.
4.4.3.1.     Media Filtration System
An alternative to a bioretention system is the media filtration system. Runoff is directed to a pit containing
filtration media which removes suspended solids and nutrients from the water before dispersing it into the
soil. It has been determined a media filtration system will be capable of achieving the load based reduction
targets for the site. The parameters utilised to analyse the media filtration system are presented in Table
9. A concept plan for the media filtration system, showing a typical cross section and footprint of the
system is included within Appendix C.
Table 9 – Media Filtration System Input Parameters

                                                                             Media Filtration System Parameters

Extended Detention Depth (m)                                                                0.3
                2
Filter Area (m )                                                                            400

Saturated Hydraulic Conductivity (mm/hr)                                                    100

Filter Depth (m)                                                                            0.5

NOTE: The results of the effluent disposal assessment have been utilised and an infiltration rate of
10mm/hr assumed for the modelling associated with the media filtration system.
4.4.3.2.     Swale
Runoff will be conveyed from the greenhouse roof to the media filtration system by a swale. The length of
swale varies, subject to the location of the downpipes from the roof area. As a conservative approach, a
flow length of 100mm has been assumed for runoff within the swale.
Table 10 - Swale Node Reporting Table

                                                                                   Swale Input Parameters

Length (m)                                                                                  100

Bed slope (%)                                                                               0.5


Stormwater Management Plan – Lot 1 on SP108094, 305 Lake Macdonald Drive                                          Page 12

D’VINERIPE
R003370a
Log in to download the original file

O2 stormwater Report Rev Oct 2015.pdf · 9.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.