Information Request Response_OPW24-0142 17092025

of 8

Page text shows just the words. Original shows the document exactly as it was published.

   17 September 2025

   Our Reference: 676
   Council File Reference: OWP24/0142

   Noosa Shire Council
   BY EMAIL TRANSMISSION
   [email protected]

   Attention: Engineering Officer – Diogo Carrico

   Dear Diogo,

   RE:        RESPONSE TO INFORMATION REQUEST
              Development Application for Operational Works (Drainage Works, Earthworks,
              Landscaping, Roadworks Stormwater) on land at Lakelands Resorts 396 and 2/396 Lake
              Cooroibah Road, Cooroibah, QLD, 4565 (legally described as Lot 1 GTP1928 and Lot 2
              GTP1926)

   I refer to Council’s Information Request dated 23 October 2024 issued in respect of the above
   application. Each of Council’s request items have been set out and responded to below. The following
   supporting information is enclosed with this response.

         Attachment 1          Overall Site Plan
         Attachment 2          Proposed Bin Enclosure
         Attachment 3          Road Section Details

   Body Corporate

   Item 1 – The subject application relates to a lot (Lot 2 GTP1926) which is under a body corporate with
   Lot 1 GTP (owned by another party) and Lot 0 GTP (common property). The subject application seeks
   approval for works both in Lot 2 and Lot 0. Body corporate consent to the proposed works has not
   been submitted.

   Provide Body Corporate’s written approval for the works proposed in the subject application.

   Response –In accordance with section 51(2) of the Planning Act 2016, development applications must
   be accompanied by the written consent of the owner of the premises to the application, to the extent
   (nb. emphasis added by bold underline) –

         (a) The application is not the owner; and
         (b) The application is for –



                                                                                                            P: 07 5452 5207
                                                                                                   E: [email protected]
                                                                           Level 1, 9 First Avenue, Maroochydore Qld 4558
                                                                                         PO Box 1043 Maroochydore Q 4558
Page 1 of 8                                                                             innovativeplanningsolutions.com.au
Log in to download the original file

Information Request Response_OPW24-0142 17092025.pdf · 1.2 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 7 pages

Page 2

               (i) A material change of use of premises or reconfiguring a lot; or

   This application seeks approval for operational works only, and therefore written consent is not
   required to be provided.

   Staging and Carparking

   Item 2 - The proposed staging is not in accordance with the higher order approval ref - 51987.2966.05.
   As a result:
   (i) the carparking is not located adjacent to the relevant stage,
   (ii) the carparking is not located in close proximity to the reception/managers
   (iii) residence,
   (iv) the carparking for stages 1 and 2 are located closer to the adjoining residences
   (v) on Lot 1 GTP1928 and Lot 12 on RP209011 (No 400)
   (vi) the proposed carparking areas require a longer access driveway to be
   (vii) constructed in the first stage, and
   (viii) the communal structures (BBQ pavilion, pool and play area) are not located in
   (ix) any specific stage

   Provide amended plans that are consistent with the higher order approval or provide justification
   for the proposed staging layout and the associated issues.

   Response – the most recent decision notice for the higher order material change of use approval
   (Council Ref. 51987.2966.05) provides (inter alia) that development is to be undertaken in accordance
   with building plans that are generally in accordance with the requirements of the approval (Conditions
   1 and 2 of 51987.2966.05 refer). It is acknowledged that the approved Overall Site Plan (Plan No.
   DD01 Rev L) denotes the manner in which approved works are anticipated as being staged – with
   works proposed to occur over three stages (refer Figure 1 below).

   It is still intended that the development will be delivered over three primary stages (with Stage 1
   involving a minor sub staging arrangement). Figure 2 below provides the adjustments that are
   proposed by the amended Overall Site Plan (also included at Attachment 1), which are arguably
   generally in accordance with the approved Overall Site Plan. For complete transparency, the
   following description is provided for the proposed staging:

    Stage        Current approved Overall Site Plan          Proposed New Staging
                                                             (per Attachment 1)
    Stage 1(A) •     Caretakers dwelling and associated •        Caretakers dwelling and associated
                     shed out-building (already completed        shed out-building (already completed
                     under separate Building Approval            under separate Building Approval
                     (BA).                                       (BA).




                                                                                                            P: 07 5452 5207
                                                                                                   E: [email protected]
                                                                           Level 1, 9 First Avenue, Maroochydore Qld 4558
                                                                                         PO Box 1043 Maroochydore Q 4558
Page 2 of 8                                                                             innovativeplanningsolutions.com.au

Page 3

    Stage        Current approved Overall Site Plan          Proposed New Staging
                                                             (per Attachment 1)
                 •   6 x Glamping Tents (2 of which are      • 2 x Glamping Tents (already
                     already completed under separate            completed under separate Building
                     Building Approval (BA).                     Approval (BA).
                 •   Stormwater drainage for 6 x Glamping    • Stormwater drainage first 2 x
                     tents in accordance with the MCU            Glamping tents in accordance with
                     approved Stormwater Management              the MCU approved Stormwater
                     Report.                                     Management Report.
                 •   Landscaping for Stage 1.                • Landscaping around the Stormwater
                 •   Driveway Crossover into the property        Soakage Pit and screening between
                     in accordance with Council Standard         the Tents and the Caretakers
                     Drawing IPWEA RS – 056 and 3.0m             Dwelling.
                     wide access driveway up to Carpark A.   • Prepare & mark (including signage)
                 •   New Carpark A (i.e. 8 spaces).              temporary access driveway from
                                                                 existing driveway access to the 2 x
                                                                 Glamping Tents including a 6m x 3m
                                                                 car park for each tent.
    Stage 1(B)                                               •   4 x Glamping Tents (making up a Total
                                                                 of 6 for Stage 1)
                                                             •   New Driveway Crossover into the
                                                                 property in accordance with Council
                                                                 Standard Drawing IPWEA RS – 056
                                                             •   New 3.0m wide access driveway up to
                                                                 the carparking for Stage 1.
                                                             •   New carparking for 6 x Glamping tents
                                                                 including 2 x visitor spaces and 1
                                                                 disabled car park, a total of 6 + 1 +1 +
                                                                 1 x disabled reserve = 9 spaces.
                                                             •   Landscaping for Stage 1.
                                                             •   Construction of Recreation/Camp
                                                                 Kitchen area and ablution block.
    Stage 2      •   6 x Glamping Tents.                     •   Construction of 6 x Glamping Tents.
                 •   Recreation/Camp Kitchen area and        •   Construction of swimming pool area
                     ablution block.                             including required fencing and
                 •   Swimming pool area including                landscaping.
                     required fencing and landscaping.       •   Extra carparking for 6 more Glamping
                 •   Carpark B (i.e. 7 spaces) and               tents.
                     associated extension to driveway.       •   Landscaping for Stage 2.
                 •   Landscaping for Stage 2.
    Stage 3      •   Final 6 x Glamping Tents                •   Final 6 x Glamping Tents



                                                                                                            P: 07 5452 5207
                                                                                                   E: [email protected]
                                                                           Level 1, 9 First Avenue, Maroochydore Qld 4558
                                                                                         PO Box 1043 Maroochydore Q 4558
Page 3 of 8                                                                             innovativeplanningsolutions.com.au

Page 4

    Stage     Current approved Overall Site Plan    Proposed New Staging
                                                    (per Attachment 1)
              •   Carpark C (i.e. 7 spaces) and • Carparking for 6 more Glamping
                  associated extension to driveway.     tents.
              •   Landscaping for Stage 3.          • Landscaping for Stage 3.
                                                    • Seal access driveway & driveway
                                                        crossover from Cooroibah Rd (done as
                                                        maintenance activity against existing
                                                        approval)
                                                    • Undertake Maintenance to put a 2
                                                        coat "Chip n Tar seal" (moisture proof
                                                        & wear seal) to driveway.




                    Figure 1: Staging per Development Approval 21987.2966.05




                                                                                                     P: 07 5452 5207
                                                                                            E: [email protected]
                                                                    Level 1, 9 First Avenue, Maroochydore Qld 4558
                                                                                  PO Box 1043 Maroochydore Q 4558
Page 4 of 8                                                                      innovativeplanningsolutions.com.au

Page 5

                                Figure 2: Proposed Minor adjustments to Staging

   Importantly, the overall intent and sequence of delivery remains consistent with the higher order
   approval, with the following key observations provided:

       •      Driveway and Access: It continued to be intended that the main driveway will be constructed
              in accordance with required civil engineering specifications and staged to suite project
              delivery. This ensures compliance with Council’s requirements for safe and orderly access to
              each stage of the proposed development;
       •      Carparking: appropriate allocation of sealed carparking will be provided for each stage, with
              clear allocation for client, visitor and accessible (PWD) spaces. The total parking provisions
              with the proposed amended staging matches the scale of development at each stage;
       •      Bushfire Setbacks: it continued to be intended that a 10m bushfire risk setback (hatched) will
              be provided in accordance with Council’s bushfire management requirements;
       •      Stormwater and Wastewater: Vegetated swales, water storage to each tent, and staged
              upgrades to the EP20 wastewater treatment plant are included, demonstrating compliance
              with water quality and environmental protection standards;
       •      Tourist Villas/Glamping Tents: The number, location, and maximum size of tourist villas
              remains the same, with no intensification beyond what was approved;
       •      Ancillary Facilities: Manager’s residence, pool, BBQ pavilion, bin enclosure, and internal
              pathways continued to be intended and staged appropriately




                                                                                                               P: 07 5452 5207
                                                                                                      E: [email protected]
                                                                              Level 1, 9 First Avenue, Maroochydore Qld 4558
                                                                                            PO Box 1043 Maroochydore Q 4558
Page 5 of 8                                                                                innovativeplanningsolutions.com.au

Page 6

       •      Title Boundaries and Land Use: there is no encroachment of unauthorised works across stage
              boundaries with plan clearly showing the boundaries of Lots 1 (common land), Lot 1 (no
              works) and Lot 2 (subject site).

   In light of the above, we submit that the sequence and scope of works in the amended Overall Site
   Plan remain true to the approved Overall Site Plan, with only minor refinements that do not alter the
   overall intent or intensity. There is also no increase in the number of glamping sites or intensity of
   use and all critical elements (i.e. access, parking, bushfire management, stormwater and wastewater
   management) are appropriately addressed and staged to ensure compliance at each phase.

   Driveway

   Item 3 – The proposed driveway works are not in accordance with the higher order approval ref -
   51987.2966.05:
   (i) Condition 11 of the higher order approval requires that access to the carparking is provided with
        a sealed pavement, and
   (ii) the approved plan DD01 Revision L includes a notation “main driveway to civil engineer’s spec. to
        be staged to suit project staging”.

   The submitted documentation does not propose to undertake any upgrading works for the access
   driveway.

   Provide amended plans that demonstrate compliance with the higher order approval.

   Response – in relation to the driveway, the applicant advises as follows:

       •      Existing Approved Driveway Crossover and Access Driveway: Ongoing Maintenance of
              existing approved driveway crossover and access driveway will continue to occur and be
              driven by increased usage. These activities already have Council approval to construct and use
              (which came with the obligation to undertake maintenance activities as required).

       •      Temporary Car Parking for the 2 x Glamping Tents Constructed as part of Stage 1 (a): while
              the proposed design for access to the 2 x Glamping tents is informal, it aligns with the rural
              nature of the development, and incorporates the following features:

               (i)    Carpark Dimensions: The carpark locations for each cabin is shown on the amended
                      Overall Site Plan included at Attachment 1 with minimum "informal" car parking
                      dimensions of 6m x 6m, plus turning tapers as per IPWEAQ RS-056. These proposed
                      dimensions exceed the parking provisions in AS2890.1, maintaining the informal rural
                      nature of the proposed cabin development.
               (ii)   Driveway Sections: The minimum driveway width of 3 meters is shown on the
                      amended Overall Site Plan included at Attachment 1. Standard cross sections and
                      table drains with pipe crossing details for rural driveways are covered in IPWEAQ RS-


                                                                                                               P: 07 5452 5207
                                                                                                      E: [email protected]
                                                                              Level 1, 9 First Avenue, Maroochydore Qld 4558
                                                                                            PO Box 1043 Maroochydore Q 4558
Page 6 of 8                                                                                innovativeplanningsolutions.com.au

Page 7

                      056. This is an industry standard drawing for rural driveway sections and pipe
                      crossings (refer also Attachment 3). The minor driveway to cabins does not intercept
                      major gully lines or large catchment.
              (iii)   Each tent will be provided with a marked 6m x 3m parking bay which exceeds the min
                      requirements of AS2890.1. A temporary access driveway (a min 3 m wide) will also be
                      marked with star pickets from the existing access driveway up to the marked parking
                      areas for each tent

   Item 4 and Item 5 – No detail has been provided to demonstrate how the proposed development will
   address conditions 10, 14 and 15 of the higher order approval ref - 51987.2966.05:

   Provide comment on any agreement to provide electricity throughout the site

   Provide comment on how conditions 14 & 15 will be addressed. Indicate on the plans any necessary
   waste collection and storage areas.

   Response – the subject site is already connected to electricity in accordance with the requirement s
   of Condition 10 of the higher order material change of Use approval. No further detail is therefore
   required to be provided in relation to this matter.

   In relation to conditions 14 and 15 of the higher order material change of use approval, refer to the
   amended Overall Site Plan included at Attachment 1 which identifies the provision of a bin enclosure
   located immediately to the east of the driveway and setback at least 2m from the boundary of Lake
   Cooroibah Road. This is generally consistent with the location as shown on the approved Overall Site
   Plan. Details of specifications for the proposed bin enclosure are as shown at Attachment 2.

   Bonds and Contributions

   Item 6 – The higher order conditions 6 and 17 make reference to the timing for the payment of bonds
   and contributions. It is noted that a number of buildings either exist or are under construction on the
   subject site (Lot 2).

   Provide advice on how the applicant intends to address Conditions 6 and 17 of the higher order
   approval.

   Response – in relation to the contributions required by Condition 6 of the higher order material
   change of use approval, the applicant advises that it is intended that a staged payment will be provided
   in accordance with the staging articulated by the amended Overall Site Plan included at Attachment
   1. Invoices from Council to this effect are anticipated as being provided.

   In relation to the bond referenced by Condition 17 of the higher order material change of use approval,
   the requirement for this provision appears to have now passed, given previous building approvals



                                                                                                              P: 07 5452 5207
                                                                                                     E: [email protected]
                                                                             Level 1, 9 First Avenue, Maroochydore Qld 4558
                                                                                           PO Box 1043 Maroochydore Q 4558
Page 7 of 8                                                                               innovativeplanningsolutions.com.au

Page 8

   issued over the site. Notwithstanding, the applicant is prepared to (if still required by Council) make
   immediate lodgement of this bond following successful completion of this application.

   This response is considered to constitute a full response to Council’s Information Request and we
   therefore request that Council proceed with its assessment of the application. We would also
   welcome the opportunity to meet and discuss the application material with Council, and can avail
   ourselves at a suitable time to Council assessment officers.

   Should you have any further queries or wish to discuss anything further, please do not hesitate to
   contact our office on 07 5452 5207.

   Yours sincerely




   James Brownsworth
   DIRECTOR
   INNOVATIVE PLANNING SOLUTIONS




                                                                                                             P: 07 5452 5207
                                                                                                    E: [email protected]
                                                                            Level 1, 9 First Avenue, Maroochydore Qld 4558
                                                                                          PO Box 1043 Maroochydore Q 4558
Page 8 of 8                                                                              innovativeplanningsolutions.com.au

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗