24-7-19 Attachment F Rev Stormwater Mgmt Plan

of 34

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (22.6 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
18 July 2019



                                            Existing Discharge                         Proposed Discharge
         ARI Year
                                            From Site (m3/sec)                          From Site (m3/sec)

             2                                       0.196                                   0.192

             5                                       0.271                                   0.249

            10                                       0.310                                   0.306

            20                                       0.359                                   0.355

            50                                       0.390                                   0.369

           100                                       0.435                                   0.413

                                      Table 1 – Existing and Developed Peak Flows

5.3.3 Stormwater Quality Management Strategy

In order to satisfy the requirements of the State Planning Policy July 2017 for the adequate
treatment of stormwater runoff, natural treatment solutions have been provided to remove
hydrocarbons, suspended solids and nutrients prior to being discharged from site.

5.3.3.1 Potential Pollutants Generated
The pollutants that could be potentially generated as a result of the development use are as
follows:

          Litter
          Sediment
          Nutrients (Nitrogen and Phosphorous)
          Hydrocarbons (oils and grease)
          Surfactants
          Pathogens/Faecal Coliforms (bacteria and viruses)

The MUSIC computer modelling program developed by the Co-operative Research Centre for
Catchment Hydrology was used to predict the performance of the proposed stormwater treatment
train.

At this stage the pollutants modelled in MUSIC are Total Suspended Solids (TSS), Total
Phosphorous (TP) and Total Nitrogen (TN).

5.3.3.2 Rainfall
The rainfall data used in the model was based on the Bureau of Meteorology data from rainfall
station 40059 Cooroy Composite. The model was run for a 10-year period from 1 January 1973 to
31 December 1983. The modelling time step was 6 minutes.




5.3.3.3 Rainfall Runoff Properties


Excellence with Economy in Engineering                                                                       10
l:\7000-7999\7700-7799\7700\reports\18-07-19 stormwater management plan_issue d.docx
Log in to download the original file

24-7-19 Attachment F Rev Stormwater Mgmt Plan.pdf · 22.6 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.