07/1586 - MCU - Detached House [As Published] · 132007.1586
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 20, 2 April 2007
Development within the limits ofa | 12. Does the application involve development below high water mark’® and within the limits of a port
port under the Transport Infrastructure Act 1994?
For more information refer to Guide 18. For
information about prescribed tidal work refer to
Guide 24.
you answered “YES” to Q12, the application
triggers referral to the Port Authority.
The Port Authority is a concurrence agency if the
development is -
© within 200m of a shipping channel or an entry
and exit shipping corridor for the port
© within 1000m of a swing basin, a commercial
shipping wharf, a mooring, anchorage or spoil
grounds;
© within 1000m of a planned port facility
identified in a land use plan approved under
the Transport infrastructure Act 1994.
in all other situation the Port Authority is an
advice agency.
Marinas
For more information refer to Guide 18. For
information about whether a marina is prescribed
tidal work refer to Guide 24, The local
government is the assessment manager for all
prescribed tidal work,
Ifyou answered “YES” to Q13, the application
triggers referral to Queensland Fire and Rescue
Service as an advice agency. .
13.
NO
YES - complete Part M of Form 1, or Part P of Form 1 if the work is prescribed tidal work
Does the application involve operational work that is tidal work for a marina’? with more than 6
vessel berths?
INO
(11 YES - complete Part M of Form 1, or Part P of Form 1 if the tidal work is prescribed tidal work
Tidal works in strategic port land tidal
areas 7 /
For more information refer to Guide 18,
Uniess you answered “NO" to Q14, the relevant
Port Authority is the assessment manager for the|
application and the Environmental Protection .
Agency (EPA) and Queensland Transport (QT)
are concurrence agencies for the’ sopkcatnn.
Heritage
For further Information veer to ute 19,
if you answered “YES” to Q15, the application
triggers referral to the Queensland Heritage -
Council as concurrence agency for the
application.
Unless you answered “none of the abave” to
Q15(b), the application involves referral to the.
Environmental Protection Agency as an advice
=
15.
4,
Does the application involve tidal works within a strategic port land tidal area?
JNO
(CI YES - complete Part M of Form 1
Does the application involve development in a heritage registered place as defined under the
Queensland Heritage Act 1992?
INO
(C1 YES - complete Part C of Form 4
415(b)The application involves: (tick applicable boxes)
a material change of use assessable against the planning scheme and the lot shares a
common boundary with a protected area or registered place under the Queensland
(i)
agency for the application Heritage Act 1992;
(ii) reconfiguring a lot if the lot shares a common boundary with a protected area or
tegistered place under the Queensland Heritage Act 1992;
&] (iii) none of the above.
Declared catchment areas. 16. The application is in an area declared to be a catchment area under the Water Act 2000 and
For more information, including a list of the
declared catchment areas within Queensland,
refer to Guide $3,
Unless you answered “none of the above” to
Q16, the application requires assessment by the
Department of Natural Resources and Water
(NRW).
If an agency other than NRW is the assessment
manager for the application, NRWis a -
concurrence agency for the application in
relation to this matter.
involves: (tick the applicable box/es)
(C1) reconfiguring a lot if any lot resuiting from the reconfiguration is less than 16 hectares;
{1 (i) development assessable against the planning scheme involving the establishment or
expansion of a waste water disposal system, other than a disposal system for carrying
out an environmentally relevant activity under the Environmental Protection Act 1994;
EX] (iii) none of the above
18 High water mark is defined in the Coastal Protection and Management Act 1995 and means the ordinary high water mark at spring tide.
19 Marina is defined in the Transport Operations (Maritime Pollution) Regutation 1995.
20 Strategic port land tidal areas are the areas generally 50 metres seaward of high water mark adjacent to strategic port land.
_ Pages -
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
07/1586 - MCU - Detached House [As Published]Related documentApplication case desk ↗
About this file
- File size
- 1.9 MB (small file)
- File type
No other editions are linked here.