    ATTACHMENT 1 – REFERRAL AGENCY (ADVICE) RESPONSE
    Powerlink Queensland supports this application subject to the inclusion of the following conditions in the
    Assessment Manager’s Decision Notice.

   No.       Condition                                                               Timing                          Reason
   1         The development must be carried out                                     At all times.                   To ensure that the
             generally in accordance with the reviewed                                                               development is carried out
             plans detailed in Table 1.                                                                              generally in accordance with
                                                                                                                     the plans of development
                                                                                                                     submitted with the application.
   2         The statutory clearances set out in the                                 At all times.                   To ensure that the purpose of
             Electrical Safety Regulation 2013 must be                                                               the Electrical Safety Act 2002
             maintained during construction and                                                                      is achieved, and electrical
             operation. No encroachment within the                                                                   safety requirements are met.
             statutory clearances is permitted.
   3         Compliance with the terms and conditions of                             At all times.                   To ensure that the existing
             the easement dealing no. shown in the                                                                   rights contained in the
             heading of this letter.                                                                                 registered easement dealings
                                                                                                                     are maintained.
   4         Compliance with the generic requirements in                             At all times.                   To ensure that the purpose of
             respect to proposed works in the vicinity of                                                            the Electrical Safety Act 2002
             Powerlink Queensland infrastructure as                                                                  is achieved, and electrical
             detailed in the enclosed Annexure "A".                                                                  safety requirements are met.
                                                                                                                     To ensure the integrity of the
                                                                                                                     easement is maintained.

    Advice to Council and the Applicant
1. Powerlink have assessed the awning/shelter structure and determined that it is not permitted in its current
   location on the easement. Consequently, it has been excluded from our referral response. Powerlink's
   preference is to remove or relocate the structure to the side of the easement at such time as the vacant easement
   is required for future transmission purposes.

    Unfortunately, Powerlink have been unable to reach a feasible arrangement with the applicant that will uphold the
    relocation or removal of the structure should ownership change prior to the removal being requested by
    Powerlink. Until such time as a resolution can be reached, the structure will be recorded as an unapproved co-
    use development of the transmission easement.

2. Should any doubt exist in maintaining the prescribed clearance to electrical infrastructure the applicant is obliged
   under the Electrical Safety Act 2002 to seek advice from Powerlink.
3. In order for Powerlink to maintain and operate a safe and reliable supply of electricity, we require unrestricted 24-
   hour access to our corridors and infrastructure.

    We will require practical access (typically by 4WD vehicle – but to standard no less than existing) to the Powerlink
    structures.

    If it is envisaged that there will be any interference or alteration to our current access arrangements prior, during
    or after the completion of your works, we require that the applicant contacts our Works Control Manager
    Easements (Mr Ehren Wittmer – ph 0418 233 916) to formalise unrestricted 24-hour access arrangements.




  33 Harold Street Virginia QLD 4014 Australia | PO Box 1193 Virginia QLD 4014 Australia
  07 3898 4090 | | [email protected] | powerlink.com.au

  Powerlink Queensland is the registered business name of the Queensland Electricity Transmission Corporation Limited. ABN 82 078 849 233

Used in these records

About this file

File size
5.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Referral Agency Response for DA6226.pdf · 5.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.