18. A final inspection and approval of the structure by Council’s Inspector is also required prior to
the return of any bond monies held by Council. Please contact Council’s Operational Works
Assessment Section to arrange the inspection.
19. The jetty shall be licensed with the Council upon completion of the structural work and shall be
licensed annually thereafter.
20. The Development Permit for Operational Works lapses if the works have not been completed
by 2 June 2011, unless an application to extend the relevant period is approved by Council.
5 REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Referral Trigger Referral Status Referral Agency Referral Address
Operational work in a Concurrence Queensland Regional Harbour Master
canal that is Prescribed Transport (Maritime Mac Arthur Ave East
Tidal Work Safety Queensland) PINKENBA QLD 4008
A copy of any referral agency conditions is attached.
6 APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
Plan / Document No. Rev. Plan / Document Name Date
477-01 A Site Layout – AAA Design & 7 May 2009
Development Pty Ltd
477-02 Pontoon Details – AAA Design & 3 February 2009
Development Pty Ltd
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a Change to an Existing Approval Application under the Integrated
Planning Act must be made. Amended plans clearly indicating the changes must be lodged
with this application along with the appropriate fees.
2. The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and
Local Law No. 12, prevents a builder or building contractor carrying out building work on a
building site in a way that makes or causes audible noise to be made from the building work:-
2.1. On a Sunday or public holiday, at any time; or
2.2. On a Saturday or a business day, before 7.00am or after 6.30pm.
A maximum penalty of $1,500 applies to an offence under this legislation.
Page 3 of 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Letter - Change to an Existing Approval [As Published]Related documentApplication case desk ↗
About this file
- File size
- 166 KB (small file)
- File type
No other editions are linked here.