Flood Study
The structures were:
Lake Entrance Boulevard Crossing 1 – 3/2100 by 1800mm RCBC (upstream IL = 0.6 mAHD,
downstream IL = 0.55 mAHD, length = 23.7m);
Lake Entrance Boulevard Crossing 2 – 4/2700 by 900mm RCBC (upstream IL = 1.19 mAHD,
downstream IL = 1.18 mAHD, length = 22.3m);
Lake Entrance Boulevard Crossing 3 – 2/750mm RCPs (upstream IL = 1.038 mAHD, downstream IL =
0.816 mAHD, length = 37.1m); and
Aspera Place Crossing – 10/1800mm RCPs (upstream IL = 2.40 mAHD, downstream IL = 2.30 mAHD,
length = 20m).
The road height levels were taken from the DTM.
The third crossing of Lake Entrance Boulevard appears to be deliberately undersized so as to divert flows
through the waterway crossing of Aspera Place, and reduce flooding of downstream areas along Lake
Entrance Boulevard.
A 450mm low flow pipe was included underneath Hollett Road. The surveyed invert level of this culvert was
6.53 mAHD.
Typical entry and exit losses of 0.5 and 1.0 respectively were assumed for the culverts, unless specified
otherwise.
No blockage of the existing culverts was assumed.
The Walter Hay Drive bridge was modelled as a 2D structure based on plans obtained from the Department
of Main Roads.
No structures were included in the 1D section of the model as the model ended upstream of Weyba Road.
The recent bridge crossing of Weyba Creek at Eenie Creek Road was not included as it was not in the Mike
11 model. The bridge crossing is not expected to have a significant impact on peak flood levels as the
bridge deck is well above peak flood levels, there is a large spacing between piers, and there are low flow
velocities in this area.
3.3 Model Calibration
th
The results of the TUFLOW model were compared to the flood event of the 24 of February 2012. SCRC
had debris levels surveyed around Lake Entrance Boulevard following this event. The rainfall was quite
spatially varied. The closest gauges at Tewantin and Upper Doonan recorded 196mm and 109mm
respectively over a 210 minute period. The rainfall applied to the WBNM sub-catchments were weighted
based on their location relative to the gauges.
The intensity frequency duration (IFD) analysis of this rainfall event at the two gauges is shown below in
Image 1.
Northbrook Corporation Pty Ltd Version 4 16 September 2013
Flood Study v4 2.doc Commercial in Confidence Page 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 13- Amended Flood Study MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 37.1 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.