Swmp
Figure 1-2: Overland Flow Paths and Flood Hazard Overlay Mapping
Lawful Point of Discharge
As outlined by the Queensland Urban Drainage Manual (4th Edition – Institute of Public Works
Engineering Australasia, Queensland Division) a test can be undertaken to determine
whether a lawful point of discharge exists:
The criteria for determining the lawful point of discharge are:
(i) Will the proposed development alter the site’s stormwater discharge characteristics in
a manner that may substantially damage a third-party property (see Section 3.6)?
If not, then no further steps are required to obtain tenure for a lawful point of
discharge (assuming any previous circumstances and changes were lawful).
It is proposed that discharge of runoff from the proposed development site will be
maintained to the property boundary within the mapped waterway.
It is considered that discharge from the site will be managed in such a manner as to not
substantially damage third party property, and as a result it is considered suitable lawful
points of discharge has been identified and achieved.
21-0166SMP01-V1 | Stormwater Management Plan | 25 Pavilion Street, Pomona |3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.