Gympie Terrace Noosaville Pty Ltd



existing and potential acidity at this site would be classified as VH (very high) treatment in accordance with
Queensland Soil Management Guidelines V4.0 - Table 4.2 (i.e. between 5 and 25 tonnes of aglime).
The SPP14 guidelines require that for Category VH treatment, a stand-alone ASS Management Plan
(ASSMP) must be provided. Recommendations on strategies to be included in the ASSMP are as follows:

      Excavated soil must be managed by neutralisation of existing and potential acidity. Good quality
       agricultural lime should be thoroughly mixed with the spoil. Any lime treatment should be carried out in
       accordance with Queensland Acid Sulfate Soil Technical Manual, Soil Management Guidelines (Ver.
       4.0. 2014).

      Treatment should be carried out on prepared pads. The earthworks strategy should be formulated to
       provide an appropriately sized pad to enable practical spreading, mixing and drying, so that adequate
       time is available to complete the treatment and verification before placing the next layer of soil. Should
       an area not be available for a treatment pad due to space restrictions treatment could be carried out
       in-situ.

      Stormwater should be diverted away from treatment/fill areas.

      Verification sampling and analysis is to be carried out on the treated soil to confirm that appropriate
       amounts of the neutralising agent have been incorporated into the soil.

      Groundwater quality should be monitored through new groundwater monitoring wells located across
       the site.

      Management of groundwater seepage and rainfall collected in excavations and other works areas on
       site, including treatment recommendations, must be incorporated into the ASSMP.
During construction, it is recommended that all waters collected from groundwater or surface water inflow, be
retained, monitored and if needed, treated to comply with the appropriate discharge criteria prior to discharge
offsite.

8.0      LIMITATIONS
Should you require any further information please contact the undersigned. We draw your attention to the
document, Limitations, which is included in Appendix D.




J000799-002-R-Rev0                                                                                    Page 10

Used in these records

About this file

File size
10.7 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Geotech Report Reference Document OPW19-0239.pdf · 10.7 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.