19553 Lake Macdonald Drive Preliminary Construction Management Plan

Attached to the e-mail 19553 - 125 Lake Macdonald Drive - Response to information request - OPW20/0051 - Email 2 of 2.

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
OPW20/0051

RURAL RESIDENTIAL DEVELOPMENT AT LAKE MACDONALD DRIVE COOROY

PRELIMINARY CONSTRUCTION MANAGEMENT PLAN
This Preliminary Construction Management Plan (CMP) has been prepared to address the specific
requirements of the Lot Reconfiguration Decision Notice.

  Item                         Details
  Hours of Work                7:00am – 5:00pm
  Contact details              Principal Contractor (yet to be appointed)
  Protection of vegetation     Areas of the site have been identified as covenant areas and these will be
                               made exclusion zones during the construction phase. Some tree clearing will
                               be required to facilitate the works.
  Air Quality / control of     The areas of disturbance will be minimised as much as is practical to limit dust.
  dust                         Watering will be undertaken if necessary to control the excessive spread of
                               dust. All exposed areas will be stabilised as soon as is practical. All plant /
                               equipment used by the selected Contractor shall be serviced / maintained
                               regularly.
  Noise                        Work will only be undertaken between the hours specified above.
  Vibration                    Standard compaction equipment will be used. Vibration will be minimised as
                               far as possible, within working hours.
  Light emissions              All works shall be undertaken during daylight hours.
  Erosion & Sediment           Suitable erosion & sediment control measures will be used to ensure no
  Control /Water Quality       detrimental effect on neighbouring waterways. Refer Drawing No. 19553-
                               C1001, prepared by Tod Consulting. Temporary sediment basins will be
                               constructed in a number of locations. These basins will be flocculated and de-
                               silted as required. Water quality is to be tested, by the Contractor, prior to
                               discharge. These plans are to be considered a live document and measures
                               are to be employed, as necessary, by the Contractor as the site is worked. In
                               addition, the selected Contractor is to comply with all other statutory
                               regulations.
  Fauna                        A ‘catcher-spotter’ will be used during the tree clearing activities.
  Waste Management             Disposal of all waste will be in accordance with Local Authority requirements.
  Protection of existing       Existing infrastructure will be protected during construction, mainly in the
  infrastructure               location of the proposed road widening on Lake Macdonald Drive and the
                               extension of Wilgee Court. The selected Contractor shall clean off any debris
                               deposited on this sealed road. Dial Before You Dig enquiries will be
                               undertaken prior to all excavation works.
  Protection   of     future   All Council assets will be maintained until the end of the Maintenance period.
  Council assets
  Public Access                No public access is required to the site until completion of the works.
                               Temporary fencing will be provided around the construction site.
  Traffic     Management       To be submitted to Council for approval by the selected Contractor. All
  Plan                         temporary traffic control to be in accordance with the MUTCD.
  Parking                      There is adequate space within the site for workers to park without impacting
                               on local residents. There is an existing access on Lake Macdonald drive that
                               can be utilised.
  Communications               The appointed Contractor shall undertake a letter box drop to neighbouring
  Protocol / Complaints        properties providing contact details for the site supervisor. The site supervisor
  Procedure                    contact details shall also be provide on a sign attached to the site entry gate
  Construction Program         It is anticipated that the works will take approximately 4 months to complete


Any site specific items or variations to the above will be submitted to Council for approval. These details
will be prepared by the selected Contractor following their appointment.
Log in to download the original file

19553 Lake Macdonald Drive Preliminary Construction Management Plan.pdf · 97 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.