Original source · versioned page text
G - Infrastructure Services Report (13.09.19)
Original PDF page 12, section 1. The text section number identifies this passage in the reader.
Infrastructure Services Report
Noosa Marketplace Development, 2 - 20 Hofmann Dr, Noosaville
4.4 Electricity Supply
Energex is the responsible authority for the provision of electricity supply facilities for the development. A
network of high voltage cables traverse along Hofmann Drive, which will be sufficient in providing power supply
to the development.
Transformers, high voltage cables and kiosk substations will be required to be extended across the site to
provide trunk electricity supply for the development.
Figure 4-4 Power assets (Energex asset plans)
13 September 2019 Cardno 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.