                                             Officer:          Glen Conforti
                                             Direct Telephone: (07) 5449 5379
                                             Response Address: PO Box 141, Tewantin QLD 4565
                                             Email:            [email protected]
                                             Our Reference:    2008/1159
                                             Your Reference:
23 July 2008

Geoff Mitchell & Associates
PO Box 1452
NOOSAVILLE BC QLD 4566




Dear Sir

                                      Decision Notice
                                    Integrated Planning Act 1997

I refer to your application and advise that on 22 July 2008 Council decided to approve the application
in full subject to conditions.
Details of the decision are as follows:

1        APPLICATION DETAILS

    Application No:                  2008/1159
    Street address:                  16 Lorikeet Drive, Peregian Beach
    Real property description:       Lot 711 P 93127
    Planning Scheme:                 The Noosa Plan
2        DECISION DETAILS

The following type of approval has been issued:
        Preliminary Approval for Building Works - Preliminary Building Work Assessable Against the
         Planning Scheme (Alteration & Additions to Detached House)

3        RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager
conditions.

4        ASSESSMENT MANAGER CONDITIONS

1.       Development undertaken in accordance with this approval must generally comply with the
         approved plans of development. The approved plans are numbered, titled and dated:
          Plan         /     Rev.    Plan / Document Name                                          Date
          Document No.
          A0.02              A       General Project Description Drawings – Redshift               11/6/08
                                     Architecture & Art Pty Ltd
          A2.11              C       Ground Floor Plan – Redshift Architecture & Art Pty           11/6/08
                                     Ltd

                                                                                          Page 1 of 7
Full text of the other 6 pages

Page 2

                                                                                        2008/1159



      A2.12                C        Roof Plan – Redshift Architecture & Art Pty Ltd            11/6/08

      A2.21                C        Elevations – Redshift Architecture & Art Pty Ltd           11/6/08

      A2.22                C        Elevations – Redshift Architecture & Art Pty Ltd           11/6/08

      A2.31                C        Sections – Redshift Architecture & Art Pty Ltd             11/6/08

      A2.32                B        Sections – Redshift Architecture & Art Pty Ltd             11/6/08


2.    The development must be undertaken and operated in a manner that causes no detrimental
      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
      lighting nuisance or other emissions.
3.    The building height shall not exceed 8.0 metres above natural ground level.
4.    A minimum of 20% of the site shall be retained as soft landscaping.
5.    Existing trees on the site and within road reserves are to be retained, except where required to
      be removed due to building operations or the conduct of the approved use. In this regard, the
      removal of vegetation shall not extend beyond 3 metres of the building footprint of the
      Detached House.
6.    All other vegetation shall be protected from interference resulting from clearing or construction
      activities by:
      6.1.    Clearly marking vegetation to be retained with flagging tape;
      6.2.    Installing protective fencing around the drip line of the vegetation;
      6.3.    Stockpiling, storage and vehicle parking occurs in already cleared areas and does not
              cause interference with vegetation; and
      6.4.    Low impact construction techniques are used around vegetation to minimise
              interference with the vegetation.
7.    Cleared vegetation is to be suitably processed by one of the following methods and removed
      from the site:-
      7.1.    Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled
              loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a
              minimum of 10 metres between edges of heaps.
      7.2.    Disposal for firewood.
      7.3.    Disposal for landscaping purposes.
      7.4.    Transport to alternative site for breaking down materials provided that all necessary
              permits have been obtained to allow the alternate site to be used for this purpose.
      7.5.    The Applicant is advised that other methods may be considered provided full details of
              the method are submitted.
      7.6.    The applicant is advised that burning off is an unacceptable method of disposal.
8.    Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are
      not constructed under overhead electricity transmission lines, or within any easements.
9.    External colours and finishes of the building shall comprise of muted/environmental tones that
      blend with the natural environment.
10.   Gates must not be installed along the rear property boundary.


                                                                                       Page 2 of 7

Page 3

                                                                                          2008/1159



11.    Sediment and erosion control measures must be in place prior to the demolition of the house.
       If such measures are not in place or are not satisfactory, ‘on the spot’ fines may be issued.
       Such fines can be issued if sediments from the site are found to enter or have the potential to
       enter Council’s stormwater system or natural waterways.
Currency
12.    The Preliminary Approval for Building Works lapses if the work has not happened by 22 July
       2010, unless an application to extend the currency is approved by Council.

5      REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:

 Referral Trigger              Referral Status   Referral Agency        Referral Address

 Nil

6      APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
 Plan / Document No.       Rev.     Plan / Document Name                       Date
 A0.02                     A        General Project Description Drawings –     11/6/08
                                    Redshift Architecture & Art Pty Ltd
 A2.11                     C        Ground Floor Plan –            Redshift    11/6/08
                                    Architecture & Art Pty Ltd
 A2.12                     C        Roof Plan – Redshift Architecture & Art    11/6/08
                                    Pty Ltd
 A2.21                     C        Elevations – Redshift Architecture & Art   11/6/08
                                    Pty Ltd
 A2.22                     C        Elevations – Redshift Architecture & Art   11/6/08
                                    Pty Ltd
 A2.31                     C        Sections – Redshift Architecture & Art     11/6/08
                                    Pty Ltd
 A2.32                     B        Sections – Redshift Architecture & Art     11/6/08
                                    Pty Ltd

7      ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1.     The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and
       Local Law No. 12, prevents a builder or building contractor carrying out building work on a
       building site in a way that makes or causes audible noise to be made from the building work:-
       1.1.   On a Sunday or public holiday, at any time; or
       1.2.   On a Saturday or a business day, before 7.00am or after 6.30pm.
       A maximum penalty of $1,500 applies to an offence under this legislation.



                                                                                         Page 3 of 7

Page 4

                                                                                          2008/1159



2.    Prior to the commencement of the development, a plumbing assessment must be obtained
      from Noosa Council’s Plumbing Services Section in accordance with the Plumbing & Drainage
      Act 2002 (as applicable).
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can
also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.

8     PROPERTY NOTES

Not applicable
9     PRELIMINARY APPROVAL OVERRIDING SCHEME
A preliminary approval under section 3.1.6 of Integrated Planning Act 1997 has been granted and as
such the level of assessment and applicable codes for any development approval resulting from this
approval are identified in the conditions.
10    FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit required            Subject of the required Development Permit
 Development Permit for Building Works          All Building Works

11    SELF ASSESSABLE CODES

The developer must comply with the following codes for self-assessable development related to the
development approved under this Decision Notice:
Detached House Driveways Code

12    SUBMISSIONS

Not applicable
13    REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME

Not applicable

14    RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Integrated Planning Act 1997 is attached.
During the appeal period, you as the applicant may make written representations to Council about
the conditions contained within the development approval. If Council agrees or part agrees with the
representations, a “negotiated decision notice” will be issued. Only one “negotiated decision notice”
may be given. Taking this step will defer your appeal period, which will continue after Council makes
its decision. (Refer to sections 3.5.17 and 3.5.18 of the Integrated Planning Act 1997).

                                                                                         Page 4 of 7

Page 5

                                                                                   2008/1159



15     OTHER DETAILS
Should you wish to obtain more information about Council’s decision electronic copies of Council’s
decision are available on line at www.sunshinecoast.qld.gov.au, or at Council Offices.

Yours faithfully,




Daniel Smith
ASSISTANT PLANNING OFFICER




                                                                                  Page 5 of 7

Page 6

                                                                                              2008/1159



                                                 Appeal Rights
                                                INTEGRATED PLANNING ACT 1997 & 1998 REGULATION




                                                               (5) If an application is processed under section
The following is an extract from the Integrated            6.1.28(2), appeal rights for submitters for the
Planning Act (Chapter 4).                                  application are available only for the aspects of the
                                                           development that would have required public
Division 8 - Appeals to court relating to
                                                           notification under the repealed Act.
development applications
Appeals by applicants                                          (6) If an application involves assessment
4.1.27.(1) An applicant for a development                  against a concurrence agency code, appeal rights
application may appeal to the court against any of         for submitters for the application are not available
the following-                                             against the part of the approval that represents the
(a) the refusal, or the refusal in part, of a              concurrence agency’s response for the code.
    development application;                               Appeals by advice agency submitters
(b) a matter stated in a development approval,             4.1.29.(1) An advice agency may, within the limits
    including any condition applying to the                of its jurisdiction, appeal to the court about the
    development, and the identification of a code          giving of a development approval for a
                         1
    under section 3.1.6;                                   development application if-
(c) the decision to give a preliminary approval            (a) the development application involves impact
    when a development permit was applied for;                 assessment; and
(d) the length of a currency period;                       (b) the advice agency told the applicant and the
(e) a deemed refusal.                                          assessment manager to treat its response to
                                                               the application as a submission for an appeal.
    (2) An appeal under subsection (1)(a) to (d)
must be started within 20 business days (the                   (2) The appeal must be started within 20
“applicant’s appeal period”) after the day the             business days after the day the decision notice or
decision notice or negotiated decision notice is           negotiated decision notice is given to the advice
given to the applicant.                                    agency as a submitter.
    (3) An appeal under subsection (1)(e) may be           Appeals for matters arising after approval given
started at any time after the last day a decision on       (co-respondents)
the matter should have been made.                          4.1.30.(1) For a development approval given for a
Appeals by submitters                                      development application, a person to whom any of
                                                           the following notices have been given may appeal
4.1.28.(1) A submitter for a development
                                                           to the court against the decision in the notice-
application may appeal to the court about-
                                                           (a) a notice giving a decision on a request for
(a) the giving of a development approval, including
                                                               extension of the currency period for an
    any conditions (or lack of conditions) or other
                                                               approval;
    provisions of the approval; or
                                                           (b) a notice giving a decision on a request to make
(b) the length of a currency period for the approval.
                                                               a minor change to an approval.
    (2) The appeal must be started within 20
                                                               (2) The appeal must be started within 20
business days (the “submitters appeal period”)
                                                                   business days after the day the notice of the
after the day the decision notice or negotiated
                                                                   decision is given to the person.
decision notice is given to the submitter.
                                                               (3) Subsection (1)(a) does not apply if the
    (3) If a person withdraws a submission before
                                                                   approval resulted from a development
the application is decided, the person may not
                                                                   application (superseded planning scheme)
appeal the decision.
                                                                   that was assessed as if it were an
    (4) If an application involves both impact                     application under a superseded planning
assessment and code assessment, appeal rights                      scheme.
for submitters are available only for the part of the
                                                               (4) Also, a person who has made a request
application involving impact assessment.
                                                                   mentioned in subsection (1) may appeal to
                                                                   the court against a deemed refusal of the
                                                                   request.
1
     Section 3.1.6 (Preliminary approval may override
    local planning instrument)
                                                                                             Page 6 of 7

Page 7

                                                                                             2008/1159

     (5) An appeal under subsection (4) may be          For Building Works Only
         started at any time after the last day the     Rights of appeal conferred by Section 4.2.9 of the
         decision on the matter should have been        Integrated Planning Act 1997 as follows:
         made.
                                                        Division 3 – Appeals to tribunals relating to
                                                        development applications
Division 9 - Appeals to court about other
matters                                                 Appeals by applicants
Appeals for matters arising after approval given
(no co-respondents)
                                                        4.2.9(1) An applicant for a development application
4.1.31.(1) A person to whom any of the following        may appeal to the Building and Development
notices have been given may appeal to the court         Tribunal against any of the following-
against the decision in the notice-
                                                        (a) the refusal, or the refusal in part, of a
(a) a notice giving a decision on a request to              development application;
    change or cancel a condition of a development
    approval.                                           (b) a matter stated in a development approval,
                                    2                       including any condition applying to the
(b) a notice under section 6.1.44 giving a decision         development, and the identification of a code
    to change or cancel a condition of a                    under section 3.1.6;
                                                                                  3
    development approval.
                                                        (c) the decision to give a preliminary approval when a
    (2) The appeal must be started within 20                  development permit was applied for;
        business days after the day the notice of the
                                                        (d) the length of a period mentioned in section 3.5.21
        decision is given to the person.
                                                              currency period;
    (3) Also, a person who has made a request
                                                        (e) a deemed refusal.
        mentioned in subsection (1)(a) may appeal
        to the court against a deemed refusal of the       (2) An appeal under subsection (1)(a) to (d) must
        request.                                        be started within 20 business days (the “applicant’s
                                                        appeal period”) after the day the decision notice or
    (4) An appeal under subsection (3) may be           negotiated decision notice is given to the applicant.
        started at any time after the last day the
                                                            (3) An appeal under subsection (1)(e) may be
        decision on the matter should have been         started at any time after the last day a decision on the
        made.                                           matter should have been made.
Appeals against decisions to change approval            The Registrar for the Building and Development
conditions under the repealed Act                       Tribunal may be contacted at the website
4.1.33A.(1) A person who is dissatisfied with a         http://www.localgovernment.qld.gov.au/
decision made on an application to change the
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act
may appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
    (2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice
of the decision is to be given to the person.
    (3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on
the matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions
applied under a local law about the use of premises
or the erection of a building or other structure
permitted by the planning scheme may appeal to
the court against the decision or the conditions
applied.
    (2) The appeal must be started within 20
business days after the day notice of the decision
is given to the applicant.


2
     Section 6.1.44 (Conditions may be changed or
                                                        3
    cancelled by assessment manager or concurrence           Section 3.1.6 (Preliminary approval may override
    agency in certain circumstances)                        local planning instrument)
                                                                                            Page 7 of 7

Used in these records

About this file

File size
55 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2008.00001159.001 [As Published].pdf · 55 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.