         Settlers Cove Wetlands - Stage 1
         ESTIMATE OF PROBABLE COSTS
         DATE: 13-08-2008
         ISSUE: Draft - for internal comment only
                                                                                                                                                                                                TOTAL
Item     Description                                                                                                               Unit          Rate                           Qty              Amount
1.00     PRELIMINARIES
1.01     Site establishment (traffic management, secure storage, EMP activites)                                                     ea           $      12,000.00                 1              $                     12,000.00
1.02     Install & maintain sediment fencing                                                                                        m            $            9.00              250              $                      2,250.00
1.03     Grub vegetation, remove marked trees                                                                                      m2            $            4.00             7000              $                     28,000.00
                                                                                                                                                        SUBTOTAL                                 $                     42,250.00
2.00     DIVERT INFLOWS
2.01     Block culverts, build temporary dam, create collection sumps                                                               hr           $          35.00                80              $                      2,800.00
2.02     Pumps & hoses (hire, running - 4 months)                                                                                   ea           $      75,000.00                 2              $                   150,000.00
                                                                                                                                                        SUBTOTAL                                 $                   152,800.00
3.00     PILES & RETAINING WALLS
3.01     Prepare heavy equipment access (mats, earthworks)                                                                          ea           $      15,000.00                 1              $                     15,000.00
3.02     Receive piles & wall panels (float, crane hire)                                                                            ea           $       7,500.00                 1              $                      7,500.00
3.03     Drive & trim piles, install wall panels                                                                                    m            $       1,500.00               125              $                   187,500.00
3.04     Finish off around stormwater piping                                                                                        hr           $          50.00                40              $                      2,000.00
3.05     Remove & store heavy equipment access                                                                                      ea           $       5,000.00                 1              $                      5,000.00
                                                                                                                                                        SUBTOTAL                                 $                   217,000.00
4.00     LAND SHAPING
4.01     Remove spoil                                                                                                              m3            $          69.00               245              $                     16,905.00
4.02     Receive & place clean fill                                                                                                m3            $          78.00              4485              $                   349,830.00
4.03     Profile as per plan                                                                                                       m2            $            3.00             7000              $                     21,000.00
                                                                                                                                                        SUBTOTAL                                 $                   387,735.00
5.00     INLET STRUCTURE
2.01     Form in place                                                                                                              ea           $      14,500.00                 1              $                     14,500.00
2.02     Backfill & profile                                                                                                         ea           $       1,000.00                 1              $                      1,000.00
                                                                                                                                                        SUBTOTAL                                 $                     15,500.00
6.00     PATHWAY & FENCING
6.01     Demolish existing pathway                                                                                                 m2            $         108.00               250              $                     27,000.00
6.02     Receive & place clean fill                                                                                                m3            $          78.00               350              $                     27,300.00
6.03     Form & pour new pathway                                                                                                   m2            $         110.00               250              $                     27,500.00
6.04     Receive & install new fencing                                                                                              m            $          56.00                80              $                      4,480.00
                                                                                                                                                        SUBTOTAL                                 $                     86,280.00
7.00     WEIR                                                                                                                                                                                    $                             -
7.01     Receive riser fabricated components                                                                                        ea           $       2,000.00                 1              $                      2,000.00
7.02     Excavate trench, position riser, form grounding block, fill trench, fit riser components                                   ea           $       8,000.00                 1              $                      8,000.00
7.03     Form spillway                                                                                                              ea           $      15,000.00                 1              $                     15,000.00
7.04     Profile weir as per plan                                                                                                  m2            $            3.00              120              $                        360.00
7.05     Receive & install geotech lining (Bentofix)                                                                               m2            $          80.00                60              $                      4,800.00
7.06     Receive & place riprap cover                                                                                              m3            $          96.00                30              $                      2,880.00
                                                                                                                                                        SUBTOTAL                                 $                     33,040.00


         TOTAL                                                                                                                                                                                   $                   934,605.00

         20% Contingency                                                                                                                                                                         $                   1,121,526.00


8.00     EXCLUSIONS
8.01     Dewatering & soil treatment                                                                                                ea                PC item
8.02     Landscaping & macrophyte zone plantings                                                                                    ea                PC item
8.03     Site restoration                                                                                                           ea                PC item
                                                                                                                                                               SUBTOTAL
         DISCLAIMERS FOR COST ESTIMATES
       1 The information set out in the above table was prepared for the sole purposes of Cape Bouvard Developments (“Client”) for the purpose of providing general information about the cost of landscape goods and
         services to be provided by third parties and which are contemplated in the attached plan(s) (“Purpose”). The information is strictly limited to the Purpose and does not apply directly or indirectly and will not be used
         for any other application, purpose, use or matter. The information is presented without the assumption of a duty of care to any other person (other than the Client) (“Third Party”) and may not be relied on by Third
         Party.
       2 Natural Solutions has compiled the information in the above table from varying tenders received by it from third parties for the provision of landscape goods and services over the past 6 months. The information is
         not intended to be an exact estimate of costs of the landscape works or specifically refer to the goods and services required by the Client. The information is provided by third parties and Natural Solutions does not
         provide an opinion nor make any representation or warranty as to the accuracy, suitability or reasonableness of any of the prices or information contained in the above table.
       3 The information in the above table is intended to provide an initial and general estimate of costs only. Due to the number of variables involved in construction and structural works, the information should only be
         used as a general guide to costs. Prior to proceeding with any work the Client should obtain an exact estimate of costs from a licensed Quantity Surveyor.
       4 Natural Solutions will not be liable (in negligence or otherwise) for any direct or indirect loss, damage, liability or claim arising out of or incidental to the Client or a Third Party using or relying on information
         contained in the above table without obtaining a further estimate from a Quantity Surveyor, nor in any case where Natural Solutions has used or relied on information provided to it by the Client or a Third Party
         where the information is incorrect, incomplete, inaccurate, out-of-date or unreasonable.




  Natural Solutions Environmental Consultants Pty Ltd                                                          4                                                                                                    4/09/2008

Used in these records

About this file

File size
89 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Original Application Part 7 - Cost Estimate [As Published].pdf · 89 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.