OPW16/0104 - Decision Notice

of 1

Text shows just the words. Original shows the document exactly as it was published.

Officer:	:Mark Lewis
Direct Telephone:	 07 53296290
Our Reference:	:OPW16/0104
Your Reference:	:B15-001

27 May 2016

KS Monahan
C/- Westera Partners Pty Ltd
PO Box 2016
FORTITUDE VALLEY  QLD  4006

Dear Sir/Madam

Decision Notice
Sustainable Planning Act 2009
I refer to your application and advise that on 27 May 2016, Council decided to approve the application in full subject to conditions.
Details of the decision are as follows:
1.	APPLICATION DETAILS

Application No:	OPW16/0104
Street Address:	36 Lorikeet Dr PEREGIAN BEACH  QLD  4573
Real Property Description:	Lot 639 P 93128
Planning Scheme:	The Noosa Plan (16 September 2013)

2.	DECISION DETAILS

The following type of approval has been issued:

Development Permit for Operational Work Engineering Works - Sewer Infrastructure

3.	RELEVANT PERIOD OF APPROVAL

The relevant period for this development approval is 2 years starting the day that this development approval takes effect.

4.	ASSESSMENT MANAGER CONDITIONS

APPROVED PLANS
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
B15/001 S	C	Sewer Works Plan & Long Section prepared by Westera Partners as annotated by Council	7 August 2015
123834	00	Traffic Guidance Scheme prepared by Evolution Traffic Control	13 April 2016
SITE SPECIFIC CONDITIONS
Where the works in the road reserve affect private assets written authority from the asset owners (property owners Nos 38-42 Lorikeet Drive) must be provided to Council. The authority must be provided to Council at the prestart meeting and describe the agreed works and any reinstatement works.
A site control and/or compliance bond of $5000 is to be submitted to Council prior to the pre-start meeting. The pre-start meeting will only be held once Council's Construction Engineering Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with these conditions or any additional inspections incurred for substandard work or work undertaken not in accordance with this permit.

PRIOR TO COMMENCEMENT OF WORKS
Engineering
Tree protection fencing must be installed under the supervision of the Project Arborist.
All necessary approvals from external service providers (eg Unitywater, Telstra etc) and external parties on which the development works are proposed have been obtained and a copy supplied to Council.
A condition report including photographs of the relevant section of Lorikeet Drive must be completed and submitted to Council at the prestart meeting and prior to any works commencing.
Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council at the prestart meeting.
Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6244. The pre-start meeting must include the relevant parties for the following aspects of the works:
Civil engineering works;
Erosion and sediment control works;
Other relevant parties
A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following:
Management during all aspects of the construct phase including:
Maintenance of safe pedestrian access across the extent of the works both during daily construction and after daily construction has ceased
Adequate parking arrangements for construction workers
No queuing of trucks is permitted on residential streets, especially prior to 7.00am. Further parked trucks must have engines turned off
Maintenance and protection of water quality and existing drainage lines through the construction area through the implementation of appropriate erosion and sediment control measures
Works programme identifying key components of the works and their respective durations
Establishment of a communication protocol with the general public, adjoining owners, emergency services and local businesses to advise of agreed construction times, impacts on traffic and services and other relevant issues
identification of complaint management procedures including:
contact details for the on-site manager
dispute resolution procedures
Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development.
All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers.
All works must be constructed and work procedure undertaken in accordance with:
The approved plans/documents and conditions detailed in this Decision Notice
The relevant conditions of the associate Unitywater approval Connection Application No. 2015003316 to which this approval relates
All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines
The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site
Works within Road Reserve/Reinstatement
Safe pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with.
All works must match neatly with existing road and verge/footpath features. Additional works may be required to provide an acceptable transition to existing road and verge/footpath profiles.
Where existing concrete pathways/driveways need to be modified or cut, full width panels of pathways/driveways between existing joints are to be removed. No pathways/driveways are to be cut longitudinally in half in part thereof. Reinstatement is to comply with the applicable Standard Drawings for pathways and driveways (RS-049, RS-050 and RS-065).
All service infrastructure proposed to be installed within existing and proposed road reserves under existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is not permitted, unless specifically approved by Council.
Service location paint markings on hard surfaces (footpaths, driveways, roads etc) must be non-permanent and must be removed after work is complete.
Infrastructure markers for underground installations are to be provided at all kerb crossings, footpaths and driveways.
Redundant pits and conduits are to be removed and the area reinstated.
All areas that are disturbed by the operations are to be restored to the original conditions which will include, but not be limited to, levelling, compaction to prevent future sinking, top soiling and turf.
Stormwater Drainage
Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets.
Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (eg by blocking or interfering with natural overland flows).
Environment
Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must not be released from the works or to waters within the areae, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination.
Erosion and sediment control measures must be installed and maintained to minimise erosion on the site and to minimise the export of sediment and associated pollutants from the site. The erosion and sediment control measures must be designed, installed and maintained in accordance with current best practice standards (refer to advisory notes).
Prior to the final inspection all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term (refer to advisory notes). For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination.
Damage to Services and Assets
Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times:
where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or
where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval.
FOLLOWING CONSTRUCTION
Certification
Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit.
As Constructed Information
Copies of the necessary Unitywater “As Constructed” information must be supplied to Council for records purposes.
Bonds
Bonds must:
meet the requirements of council’s relevant Planning Scheme Policy for performance and uncompleted works.
be calculated using a schedule of works and relevant bond equation
include GST
have approval of the bond calculations and amount from Council prior to lodgement
be lodged with Council and accompanied by the Bond Administration Fee/s.
be requested for release by writing to Council, when relevant approval requirements have been met.
A final inspection and approval of the new works and completed reinstatement works by Council’s Inspector is required. Please contact Council on 5329 6244 to arrange for the inspection.

5.	REFERRAL AGENCIES

Not Applicable.

6.	REFERENCED DOCUMENTS

The following documents are referenced in the assessment manager conditions:

Referenced Documents
Document No.	Rev.	Document Name	Date
Connection Application No:2015003316		Decision Notice , Connection Application No:2015003316 by Unitywater	6/8/2015

7.	ADVISORY NOTES

The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:

General Advisory Notes
Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works.  A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ.  The RPEQ bears full responsibility for all aspects of the engineering design.  Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent.
Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time.
Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Sustainable Planning Act 2009 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees.

Prestart, On and Off Maintenance Inspections Request
Contact Council on 5329 6244 to arrange a prestart or an inspection giving a minimum of 5 business days notice of preferred inspection time.
If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time.
A minimum maintenance period of 12 months will apply to all municipal works and thereafter until such time as the works are performing in accordance with the approved design unless noted otherwise

Environmental Advisory Notes
The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm.

Erosion and Sediment Control
Accepted best practice standards include:
the Sunshine Coast Regional Council Manual for Erosion and Sediment Control V1.2 or other superseding document subsequently adopted by Council;
Best Practice Erosion and Sediment Control, International Erosion Control Association (2008)
As a general rule, a site is determined to have achieved effective short-term stabilisation if at the time of the plan sealing inspection:
Methods of stabilisation are:
appropriate for slopes and slope lengths; and
are consistent with best practice environmental management practices such as in the Manual for Erosion and Sediment Control or the IECA Manual; and
Stormwater runoff from the site is not currently, and is not likely to result in visible evidence of sedimentation or erosion, or lead to water contamination.

Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that:  “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage.”   It is an offence to fail to comply with the duty of care.  Substantial monetary penalties may apply to individuals or corporations breaching this duty of care.  Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit on 07 3247 6212 to discuss any obligations under the ACH Act.

8.	PROPERTY NOTES

Not Applicable.

9.	PRELIMINARY APPROVAL OVERRIDING PLANNING SCHEME

Not Applicable.

10.	FURTHER DEVELOPMENT PERMITS REQUIRED

Not Applicable

11.	SELF ASSESSABLE CODES

Not Applicable.

12.	SUBMISSIONS

Not Applicable.

13.	REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME

Not Applicable.

14.	RIGHTS OF APPEAL

You are entitled to appeal against this decision.  A copy of the relevant appeal provisions from the Sustainable Planning Act 2009 is attached.

During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval.  If Council agrees or agrees in part with the representations, a “negotiated decision notice” will be issued.  Only one “negotiated decision notice” may be given.  Taking this step will defer your appeal period, which will commence again from the start the day after you receive a “negotiated decision notice”.

15.	OTHER DETAILS

If you wish to obtain more information about Council’s decision, electronic copies are available on line at www.noosa.qld.gov.au, or at Council Offices.

Yours faithfully

Mark Lewis
Coordinator-Engineering

Enc:	Approved Plans/Documents
Appeal Rights

cc	Unitywater

	Appeal Rights SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING REGULATION 2009

The following is an extract from the Sustainable Planning Act 2009  (Chapter 7).
MATERIAL CHANGE OF USE, RECONFIGURING A LOT & OPERATIONAL WORKS

Division 8 	Appeals to court relating to development applications and approvals

461 	Appeals by applicants
(1) 	An applicant for a development application may appeal to the court against any of the following—
(a) 	the refusal, or the refusal in part, of the development application;
(b) 	any condition of a development approval, another matter stated in a development approval and the identification or inclusion of a code under section 242;
(c) 	the decision to give a preliminary approval when a development permit was applied for;
(d) 	the length of a period mentioned in section 341;
(e) 	a deemed refusal of the development application.
(2) 	An appeal under subsection (1)(a), (b), (c) or (d) must be started within 20 business days (the applicant’s appeal period) after—
(a) 	if a decision notice or negotiated decision notice is given—the day the decision notice or negotiated decision notice is given to the applicant; or
(b) 	otherwise—the day a decision notice was required to be given to the applicant.
(3) 	An appeal under subsection (1)(e) may be started at any time after the last day a decision on the matter should have been made.

462 	Appeals by submitters—general
(1) 	A submitter for a development application may appeal to the court only against—
(a) 	the part of the approval relating to the assessment manager’s decision about any part of the application requiring impact assessment under section 314; or
(b) 	the part of the approval relating to the assessment manager’s decision under section 327.
(2) 	To the extent an appeal may be made under subsection (1), the appeal may be against 1 or more of the following—
(a) 	the giving of a development approval;
(b) 	any provision of the approval including—
(i) 	a condition of, or lack of condition for, the approval; or
(ii) 	the length of a period mentioned in section 341 for the approval.
(3) 	However, a submitter may not appeal if the submitter—
(a) 	withdraws the submission before the application is decided; or
(b) 	has given the assessment manager a notice under section 339(1)(b)(ii).
(4) 	The appeal must be started within 20 business days (the submitter’s appeal period) after the decision notice or negotiated decision notice is given to the submitter.

463 	Additional and extended appeal rights for submitters for particular development applications
(1) 	This section applies to a development application to which chapter 9, part 7 applies.
(2) 	A submitter of a properly made submission for the application may appeal to the court about a referral agency’s response made by a prescribed concurrence agency for the application.
(3) 	However, the submitter may only appeal against a referral agency’s response to the extent it relates to—
(a) 	if the prescribed concurrence agency is the chief executive (environment)—development for an aquacultural ERA; or
(b) 	if the prescribed concurrence agency is the chief executive (fisheries)—development that is—
(i) 	a material change of use of premises for aquaculture; or
(ii) 	operational work that is the removal, damage or destruction of a marine plant.
(4) 	Despite section 462(1), the submitter may appeal against the following matters for the application even if the matters relate to code assessment—
(a) 	a decision about a matter mentioned in section 462(2) if it is a decision of the chief executive (fisheries);
(b) 	a referral agency’s response mentioned in subsection (2).

464 	Appeals by advice agency submitters
(1) 	Subsection (2) applies if an advice agency, in its response for an application, told the assessment manager to treat the response as a properly made submission.
(2) 	The advice agency may, within the limits of its jurisdiction, appeal to the court about—
(a) 	any part of the approval relating to the assessment manager’s decision about any part of the application requiring impact assessment under section 314; or
(b) 	any part of the approval relating to the assessment manager’s decision under section 327.
(3) 	The appeal must be started within 20 business days after the day the decision notice or negotiated decision notice is given to the advice agency as a submitter.
(4) 	However, if the advice agency has given the assessment manager a notice under section 339(1)(b)(ii), the advice agency may not appeal the decision.

465 	Appeals about decisions relating to extensions for approvals
(1) 	For a development approval given for a development application, a person to whom a notice is given under section 389, other than a notice for a decision under section 386(2), may appeal to the court against the decision in the notice.
(2) 	The appeal must be started within 20 business days after the day the notice of the decision is given to the person.
(3) 	Also, a person who has made a request under section 383 may appeal to the court against a deemed refusal of the request.
(4)	An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made.

466 	Appeals about decisions relating to permissible changes
(1) 	For a development approval given for a development application, the following persons may appeal to the court against a decision on a request to make a permissible change to the approval—
(a) 	if the responsible entity for making the change is the assessment manager for the application—
(i) 	the person who made the request; or
(ii) 	an entity that gave a notice under section 373 or a pre-request response notice about the request;
(b) 	if the responsible entity for making the change is a concurrence agency for the application—the person who made the request.
(2) 	The appeal must be started within 20 business days after the day the person is given notice of the decision on the request under section 376.
(3) 	Also, a person who has made a request under section 369 may appeal to the court against a deemed refusal of the request.
(4)	An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made.

467 	Appeals about changing or cancelling conditions imposed by assessment manager or concurrence agency
(1) 	A person to whom a notice under section 378(9)(b) giving a decision to change or cancel a condition of a development approval has been given may appeal to the court against the decision in the notice.
(2) 	The appeal must be started within 20 business days after the day the notice of the decision is given to the person.

[word/footer1.xml]
Page 3 of 10

[word/footer2.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 10

[word/header1.xml]
OPW16/0104

[Attachment: image4.png (image text)]
 
 
 

 
 
 

a
mm

  

NOOSA
COUNCIL

Used in these records

About this file

File size
105 KB (small file)
File type
DOCX

No other editions are linked here.

Original file

Log in to download the original file

OPW16_0104 - Decision Notice.docx · 105 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.