ORDINARY MEETING MINUTES 17 JANUARY 2019
B. Advise the applicant that Council would support a change to the development approval
subject to additional conditions 5B, B1, B2 and B3 being included and condition 5C, 8
and 9 amended as follows:
5B. Prior to the Council completing the staged upgrade works to Cooroy Mountain
Road, weekly trucks shall be limited as follows:
(a) 40 water carrying trucks (namely all semi-trailers, tankers and other trucks
carrying water but excluding B-Doubles) per week;
(b) 20 ancillary trucks (namely non-articulated trucks and non-water carrying
trucks).
5C. After the Council has completed the staged upgrade works to Cooroy Mountain
Road, weekly trucks shall be limited as follows:
(a) 50 water carrying trucks (namely all semi-trailers, tankers and other trucks
carrying water but excluding B-Doubles) per week;
(b) 25 ancillary trucks (namely non-articulated trucks and non-water carrying
trucks).
Note: The road upgrade referred to is the upgrading of the remaining 2.2.
kilometres of Cooroy Mountain Road to provide two (2) 3.5 metre wide traffic lanes
with a 1.0 metre wide sealed shoulder to a total formation width of 9.0 metres.
8. The applicant must undertake improvement works to the existing site access to
Cooroy Mountain Road to the reasonable satisfaction of Council. The intersection
between Cooroy Mountain Road and the site access must be designed and
constructed to provide safe turning areas for the vehicles likely to use the access
and passing opportunities for other road users. The works must:
a. be generally in accordance with drawing number R01 - Revision C prepared
by Barlow Shelley Consulting Engineers dated 20 December 2018,
b. be designed and constructed in accordance with the most recent edition of
the Department of Main Roads Road Planning and Design Manual and The
Noosa Plan Planning Scheme Policy 5 Engineering Design Standards -
Roads, Drainage and Earthworks, and
c. the internal driveway at the access point must be widened sufficiently to
ensure that all vehicles exiting the site and travelling west can remain on the
southern side of the centreline of the improved Cooroy Mountain Road.
9. The full extent of the driveway from Cooroy Mountain Road to the loading area of
the facility must be sealed, designed and constructed in accordance with
AS/NZS2890.1-2004, AS2890.2-2002 and The Noosa Plan Planning Scheme
Policy 5 Engineering Design Standards - Roads, Drainage and Earthworks. The
driveway shall be designed and constructed to grades that prevent vehicles from
scraping and/or bottoming. Should any driveways be constructed to grades that do
not comply with ASINZS2890.1:2004 and AS2890.2-2002, Council will require that
the driveway be removed and reconstructed to levels that do comply.
B1. The road reserve opposite the site access must be landscaped. The works must
be undertaken in accordance with an Operational Works approval and the Noosa
Plan for that specific area and must include in particular:
a. An accurate account of trees removed for the works including species,
amount of visual dominance in the landscape and approximate age.
b. Replacement planting of trees removed must have a minimum pot size of
45L.
Page 4 of 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.