6 Martin St Peregian - DA - REV E- 04.05.23

of 18

Page text shows just the words. Original shows the document exactly as it was published.

Very large file (10.4 MB): the original may take a few minutes to open or download. The page text below is quick to read.

                                                                     N      USE FIGURED DIMENSIONS. DO NOT SCALE
                                                                            FROM THE DRAWINGS. CONFIRM ALL
                                                                            DIMENSIONS ON SITE PRIOR TO
                                                                            CONSTRUCTION OR FABRICATION. IT REMAINS
                                                                            THE CONTRACTORS RESPONSIBILITY TO
                                                                            ENSURE COMPLIANCE WITH ALL RELEVANT
                                                                            CODES AND REGULATIONS IS MAINTAINED AT
                                                                            ALL TIMES.



                                                                            DATE              ISSUE / AMENDMENT
                                                                            4/05/2023 2:51:07 PM


                                                                             09.11.2021             A    DD ISSUE
                                                                             20.01.2022             B DA ISSUE
                                                                             06.09.2022             C DA REV
                                                                         WALL LEGEND
                                                                             13.02.2023             D    DA REV
                                                                             04.05.2023             E    DA ISSUE E
                                                                                                   New Stud Wall (as dimensioned)
                                                                                                   Internal - 10mm Plasterboard - Paint Finish
                                                                                                   External - FC Sheet as noted on elevations
                                                                                                   Insulation to external walls to NCC requirements

                                                                                                   Existing Wall - Retained
                                                                                                   Varying construction types


                                                                                                   Existing Wall / Column - Demolished
                                                                                                   Varying construction types




                                                      UP




                                                           UP




                                                                UP



                                                                            DCM BUILDING DESIGN
                                                                            MOB: 0422 722 719 OR 0412 277 163
                                                                            EMAIL: info@dcmbuilding design.com.au
                                                                            QBCC: 1286569 & 1302906

                                                                            PROJECT

                                                                            UNIT 2 / 6 MARTIN STREET

                                                                            PEREGIAN BEACH, QLD


                                                                            CLIENT


                                                                            TITLE
                                                                            UNITS 1 & 2 EXISTING + DEMOLITION
                                                                            + PROPOSED - GROUND FLOOR

                                                                            DATE
                                                                                                   04.05.2023
                                                                            SCALE
                                                                                                   As indicated
                                                                            DRAWN                                      CHECKED
                                                                                                   SA                                  DC
                                                                            PROJ No
                                                                                                   21-068
                                                                            DRAWING No                                     ISSUE
1   EXISTING + DEMOLITION + PROPOSED GROUND FLOOR
    SCALE   1 : 100          0   1   2   3   4   5m
                                                                                           DD-09                                        E
Log in to download the original file

6 Martin St Peregian - DA - REV E- 04.05.23.pdf · 10.4 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.