               Assessment
               Noosa Council engaged ‘BMT Commercial Australia - consulting coastal engineers’ to peer review
               the Applicant’s coastal erosion assessments. These included a Royal Haskoning DHV [RHDHV]
               report dated 18 June 2024 and an updated report by Moffatt and Nichol dated 22 January 2025.
               Areas of dispute between the consultants related to the relevant storm tide level applicable to the
               site and the impact this would have on the extent / width of any erosion prone encroachment.
               Ultimately both consultants agreed that an erosion prone area of 85 metres measured from the
               seaward toe of the frontal dune (2.3 metres AHD) was applicable, based on a storm tide level of
               1.79 metres AHD. A storm tide level of 1.79 metres AHD is approximately a 1 in 300-year ARI
               event.
               The Moffat and Nichol (2025) assessment has included a reassessment of the EPA, applying the
               requested storm tide level of 1.79m AHD. I confirm that we have reviewed the information provided
               and accept the recalculated EPA width of 85m.
               Source: BMT Commercial Australia, 29.01.2025
               An 85-metre erosion prone area encroaches into the eastern portion of the site by approximately
               11 metres. This degree of encroachment involves approximately 5 metres of the proposed eastern
               building.




               Further discussion with BMT Commercial Australia about whether the building footprint should be
               moved out of the erosion area concluded that a condition could be applied to ensure that any
               building footings within the erosion area was to ensure free movement of sediments through natural
               processes.
               The condition provided by BMT Commercial Australia for Council is included within the decision.


               4.     CONSULTATION
               4.1. Referral Agencies
               Not Applicable
               4.2. Internal Council Referrals
               The application was forwarded to the following internal Council officers for review and/or comment:
               •    Senior Development Engineer, Development Assessment
                    - The most significant concerns with the site were the potential for coastal erosion. It is
                       understood that this issue has been addressed separately by the planning officer.

                                                                                                   Page 21 of 33

Document Set ID: 23561450
Version: 5, Version Date: 10/04/2025

Used in these records

About this file

File size
12.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning MCU24 0094 [As Published].pdf · 12.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.