Table 14-42 — All Demolition, removal or relocation
Including amendments to 3 July 2017
column 1 column 2
The Noosa Plan
Specific Outcomes Acceptable solutions (if accepted
development subject to requirements)
Probable solutions (if code assessment)
14.85 Re-use of buildings or materials
O1 Opportunities for re-use of buildings are S1.1 Buildings are relocated to another site and
maximised. adapted to meet the needs of users.
OR
S1.2 At least 10% of building materials are
reused or recycled (measured in cubic metres).
O2 The development ensures waste during S2.1 For assessable development a Waste
any construction and demolition works is Management Plan prepared in accordance with
minimised and construction and demolition Schedule 8 Demolition & Construction Waste
materials are reused and recycled where Management specifies—
possible. a) estimated volumes of waste to be
generated;
b) estimated volumes of recyclables;
c) initiatives to minimise waste by waste
reduction, reuse or recycling;
d) plans showing the location and details of
the waste storage areas; and
e) a description of the type of containers
proposed to store the waste.
14.86 Safety and protection of infrastructure
O3 Demolition, removal, relocation or S3.1 Infrastructure including, reticulated water,
associated works does not result in— sewerage, stormwater, and electricity are
a) ‘live’ or ‘active’ infrastructure that may protected from damage and made safe to the
present a risk to people using the site or standard required by the regulatory authority;
surrounding areas; or AND
b) damage to infrastructure or other works. S3.2 Infrastructure is disconnected, capped or
sealed including--
Editor’s note: a) electricity meters are removed and
An approval will be required from Council’s electrical wires disconnected; and
Building and Plumbing Services for b) telephone lines are disconnected; and
decommissioning plumbing apparatus c) high speed data cables and television
including– provider boxes are disconnected and
-sanitary drains or reticulated water supply; removed;
and AND
-septic tanks, holding tanks or on-site S3.3 A temporary crossing is provided to
treatment systems. protect road reserve infrastructure including
kerb and channel;
AND
S3.4 Any damage to footpaths, street
plantings, natural vegetation/trees kerb and
channel, bridges or roadways at the removal
site, the new site or between the sites is
repaired or reinstated to at least pre-existing
conditions.
14.87 Amenity and environmental protection
O4 Waste materials are removed from the site S4.1 Waste, building materials, footings and
to avoid causing unhealthy conditions stumps are removed from the site.
including--
a) potential fire hazard; S4.2 The site is turfed if not built on within 3
b) ponding of water; and months of demolition or removal of a building.
14-97
Building Removal and Demolition Code
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.