Table 14-42 — All Demolition, removal or relocation




                                                                                                                      Including amendments to 3 July 2017
                  column 1                                              column 2




                                                                                                          The Noosa Plan
              Specific Outcomes                             Acceptable solutions (if accepted
                                                          development subject to requirements)
                                                         Probable solutions (if code assessment)
14.85    Re-use of buildings or materials
O1 Opportunities for re-use of buildings are          S1.1 Buildings are relocated to another site and
maximised.                                            adapted to meet the needs of users.
                                                      OR
                                                      S1.2 At least 10% of building materials are
                                                      reused or recycled (measured in cubic metres).
O2      The development ensures waste during          S2.1 For assessable development a Waste
any construction and demolition works is              Management Plan prepared in accordance with
minimised and construction and demolition             Schedule 8 Demolition & Construction Waste
materials are reused and recycled where               Management specifies—
possible.                                             a)   estimated volumes of waste to be
                                                           generated;
                                                      b)   estimated volumes of recyclables;
                                                      c)   initiatives to minimise waste by waste
                                                           reduction, reuse or recycling;
                                                      d)   plans showing the location and details of
                                                           the waste storage areas; and
                                                      e)   a description of the type of containers
                                                           proposed to store the waste.

14.86    Safety and protection of infrastructure
O3 Demolition, removal, relocation or                 S3.1 Infrastructure including, reticulated water,
associated works does not result in—                  sewerage, stormwater, and electricity are
a)   ‘live’ or ‘active’ infrastructure that may       protected from damage and made safe to the
     present a risk to people using the site or       standard required by the regulatory authority;
     surrounding areas; or                            AND
b)   damage to infrastructure or other works.         S3.2 Infrastructure is disconnected, capped or
                                                      sealed including--
   Editor’s note:                                     a)     electricity meters are removed and
   An approval will be required from Council’s               electrical wires disconnected; and
   Building and Plumbing Services for                 b)     telephone lines are disconnected; and
   decommissioning plumbing apparatus                 c)     high speed data cables and television
   including–                                                provider boxes are disconnected and
   -sanitary drains or reticulated water supply;             removed;
   and                                                AND
   -septic tanks, holding tanks or on-site            S3.3 A temporary crossing is provided to
   treatment systems.                                 protect road reserve infrastructure including
                                                      kerb and channel;
                                                      AND
                                                      S3.4 Any damage to footpaths, street
                                                      plantings, natural vegetation/trees kerb and
                                                      channel, bridges or roadways at the removal
                                                      site, the new site or between the sites is
                                                      repaired or reinstated to at least pre-existing
                                                      conditions.
14.87    Amenity and environmental protection
O4 Waste materials are removed from the site          S4.1 Waste, building materials, footings and
to avoid causing unhealthy conditions                 stumps are removed from the site.
including--
a)    potential fire hazard;                          S4.2 The site is turfed if not built on within 3
b)    ponding of water; and                           months of demolition or removal of a building.


                                                  14-97
                                   Building Removal and Demolition Code
Log in to download the original file

2017-11-07 P&E Committee - Attachment 1 to Item 1 - Amendments for Multiple Housing Type 2 Duplex & Minor Corrections(PDF, 9MB).pdf · 9.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.