Minor Change Existing Approval MCU21/0156.03 [As Published]

of 16

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                             Officer:            Georgina Schramm
                                                             Direct Telephone:   07 53296569
                                                             Our Reference:      MCU21/0156.03
                                                             Your Reference:     240368

               25 February 2025


               AI McRaye
               C/- EarthCert Building Consultancy Pty Ltd
               PO Box 432
               POMONA QLD 4568
               [email protected]



               Dear Sir/Madam,
                                             Decision Notice – Minor Change
                                                         Planning Act 2016

               I refer to your application received on 12 November 2024, requesting a minor change to an existing
               development approval. Council decided your requested changes.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              MCU21/0156.03

                   Street address:              Malolo Noosa 13/89 Eumundi Noosa Rd Noosaville Qld 4566

                   Real property description:   Lot 13 SP 333814 & SP 333814

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               The following type of approval was issued on 1 June 2022
               •       Development Permit for Material Change of Use of Premises - (22 x Multiple Dwelling
                       units)
               In relation to the request to make a minor change to the existing approval, Council on 25 February
               2025, decided to approve the requested changes. The changes are detailed below.
               A.      Approve the change.
               B.      Amend condition 2.
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.




               ABN 97.969.214.121                                                                     PO Box 141
               noosa.qld.gov.au                                                                Tewantin QLD 4565
               [email protected]                                                                07 5329 6500
                                                                                                         Page 1 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
v6 NOOSA
@®& Council

Officer: Georgina Schramm
Direct Telephone: 07 53296569

Our Reference: MCU21/0156.03
Your Reference: 240368

25 February 2025

Al McRaye

C/- EarthCert Building Consultancy Pty Ltd
PO Box 432

POMONA QLD 4568

[email protected]

Dear Sir/Madam,

Decision Notice — Minor Change
Planning Act 2016

| refer to your application received on 12 November 2024, requesting a minor change to an existing
development approval. Council decided your requested changes.

Details of the decision are as follows:

1. APPLICATION DETAILS

Application No: MCU21/0156.03

Street address: Malolo Noosa 13/89 Eumundi Noosa Rd Noosaville Qld 4566
Real property description: Lot 13 SP 333814 & SP 333814

Planning Scheme: Noosa Plan 2020 (25 September 2020)

2. DECISION DETAILS
The following type of approval was issued on 1 June 2022

e Development Permit for Material Change of Use of Premises - (22 x Multiple Dwelling
units)

In relation to the request to make a minor change to the existing approval, Council on 25 February
2025, decided to approve the requested changes. The changes are detailed below.

A. — Approve the change.
B. Amend condition 2.
3. CURRENCY PERIOD OF APPROVAL

The currency period for this development approval is stated in the conditions below.

 

ABN 97.969.214.121 PO Box 141

noosa.qld.gov.au Tewantin QLD 4565

[email protected] 07 5329 6500
Page 1 of 16

Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025
Full text of the other 15 pages

Page 2

               4.     ASSESSMENT MANAGER CONDITIONS

               PLANNING
                      When Conditions must be Complied With
               1.     Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
                      the use commencing, and then compliance maintained at all times while the use continues.
                      Approved Plans
               2.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                         Plan No.          Rev.    Plan/Document Name                                 Date

                         DA.5              F       Site Plan, prepared by Black Wood Architecture 7/03/2022
                                                   & design

                         DA.6              H       Ground Floor Site Plan, prepared by Black Wood 13/05/2022
                                                   Architecture & design

                         DA.7              F       Level One Site Plan, prepared by Black Wood 7/03/2022
                                                   Architecture & design

                         DA.8              F       Site Elevations, prepared by Black Wood 7/03/2022
                                                   Architecture & design

                         DA.9              F       Site Elevations, prepared by Black Wood 7/03/2022
                                                   Architecture & design

                         DA.10             F       Site Elevations, prepared by Black Wood 7/03/2022
                                                   Architecture & design

                         DA.11             F       Site Section, prepared       by   Black    Wood 7/03/2022
                                                   Architecture & design

                         DA.12             F       Ground Floor Plan: TH01-TH04, prepared by 7/03/2022
                                                   Black Wood Architecture & design

                         DA.13             F       Level One Floor Plan: TH01-TH04, prepared by 7/03/2022
                                                   Black Wood Architecture & design

                         DA.14             F       TH01-TH04 Elevations, prepared by Black 7/03/2022
                                                   Wood Architecture & design

                         DA.15             F       TH01-TH04 Elevations, prepared by Black 7/03/2022
                                                   Wood Architecture & design

                         DA.16             F       TH01-TH04 Sections, prepared by Black Wood 7/03/2022
                                                   Architecture & design

                         DA.17             H       Ground Floor Plan: TH05-TH08, prepared by 13/05/2022
                                                   Black Wood Architecture & design

                         DA.18             F       Level One Floor Plan: TH05-TH08, prepared by 7/03/2022
                                                   Black Wood Architecture & design




                                                                                                      Page 2 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
4. ASSESSMENT MANAGER CONDITIONS

PLANNING

When Conditions must be Complied With

1. Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
the use commencing, and then compliance maintained at all times while the use continues.

Approved Plans

2. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.

Plan No.

DA.5

DA.6

DA.7

DA.8

DA.9

DA.10

DA.11

DA.12

DA.13

DA.14

DA.15

DA.16

DA.17

DA.18

Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025

Rev.

F

Plan/Document Name

Site Plan, prepared by Black Wood Architecture
& design

Ground Floor Site Plan, prepared by Black Wood
Architecture & design

Level One Site Plan, prepared by Black Wood
Architecture & design

Site Elevations, prepared by Black Wood
Architecture & design

Site Elevations, prepared by Black Wood
Architecture & design

Site Elevations, prepared by Black Wood
Architecture & design

Site Section, prepared by Black Wood
Architecture & design

Ground Floor Plan: THO1-TH04, prepared by
Black Wood Architecture & design

Level One Floor Plan: THO1-TH04, prepared by
Black Wood Architecture & design

THO1-THO4 Elevations, prepared by Black
Wood Architecture & design

THO1-THO4 Elevations, prepared by Black
Wood Architecture & design

THO1-TH04 Sections, prepared by Black Wood
Architecture & design

Ground Floor Plan: THO5-THO8, prepared by
Black Wood Architecture & design

Level One Floor Plan: THO5-TH08, prepared by
Black Wood Architecture & design

Date

7103/2022

13/05/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

13/05/2022

7103/2022

Page 2 of 16

Page 3

                         DA.19         F   TH05-TH08 Elevations, prepared by Black 7/03/2022
                                           Wood Architecture & design

                         DA.20         F   TH05-TH08 Elevations, prepared by Black 7/03/2022
                                           Wood Architecture & design

                         DA.21         F   TH05-TH08 Sections, prepared by Black Wood 7/03/2022
                                           Architecture & design

                         DA.22         F   Ground Floor Plan: TH09-TH12, prepared by 7/03/2022
                                           Black Wood Architecture & design

                         DA.23         F   Level One Floor Plan: TH09-TH012 prepared by 7/03/2022
                                           Black Wood Architecture & design

                         DA.24         F   TH09-TH12 Elevations, prepared by Black 7/03/2022
                                           Wood Architecture & design

                         DA.25         F   TH09-TH12 Elevations, prepared by Black 7/03/2022
                                           Wood Architecture & design

                         DA.26         F   TH09-TH12 Sections, prepared by Black Wood 7/03/2022
                                           Architecture & design

                         DA.27         F   Ground Floor Plan: TH13-TH16, prepared by 7/03/2022
                                           Black Wood Architecture & design

                         DA.28         F   Level One Floor Plan: TH13-TH16, prepared by 7/03/2022
                                           Black Wood Architecture & design

                         DA.29         F   TH13-TH16 Elevations, prepared by Black 7/03/2022
                                           Wood Architecture & design

                         DA.30         F   TH13-TH16 Elevations, prepared by Black 7/03/2022
                                           Wood Architecture & design

                         DA.31         F   TH13-TH16 Sections, prepared by Black Wood 7/03/2022
                                           Architecture & design

                         DA.32         F   Ground Floor Plan: TH17-TH18 + APT19- 7/03/2022
                                           APT22, prepared by Black Wood Architecture &
                                           design

                         DA.33         F   Level One Floor Plan: TH17-TH18 + APT19- 7/03/2022
                                           APT22, prepared by Black Wood Architecture &
                                           design

                         DA.34         F   TH17-TH18 + APT 19-22 Elevations, prepared 7/03/2022
                                           by Black Wood Architecture & design

                         DA.35         F   TH17-TH18 + APT 19-22 Elevations, prepared 7/03/2022
                                           by Black Wood Architecture & design

                         DA.36         F   TH17-TH18 + APT 19-22 Sections, prepared by 7/03/2022
                                           Black Wood Architecture & design




                                                                                       Page 3 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
DA.19

DA.20

DA.21

DA.22

DA.23

DA.24

DA.25

DA.26

DA.27

DA.28

DA.29

DA.30

DA.31

DA.32

DA.33

DA.34

DA.35

DA.36

Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025

THO5-THO8 Elevations, prepared by Black
Wood Architecture & design

THO5-THO8 Elevations, prepared by Black
Wood Architecture & design

THO5-THO8 Sections, prepared by Black Wood
Architecture & design

Ground Floor Plan: THO9-TH12, prepared by
Black Wood Architecture & design

Level One Floor Plan: THO9-TH012 prepared by
Black Wood Architecture & design

THO9-TH12 Elevations, prepared by Black
Wood Architecture & design

THO9-TH12 Elevations, prepared by Black
Wood Architecture & design

THO9-TH12 Sections, prepared by Black Wood
Architecture & design

Ground Floor Plan: TH13-TH16, prepared by
Black Wood Architecture & design

Level One Floor Plan: TH13-TH16, prepared by
Black Wood Architecture & design

TH13-TH16 Elevations, prepared by Black
Wood Architecture & design

TH13-TH16 Elevations, prepared by Black
Wood Architecture & design

TH13-TH16 Sections, prepared by Black Wood
Architecture & design

Ground Floor Plan: TH17-TH18 + APT19-
APT22, prepared by Black Wood Architecture &
design

Level One Floor Plan: TH17-TH18 + APT19-
APT22, prepared by Black Wood Architecture &
design

TH17-TH18 + APT 19-22 Elevations, prepared
by Black Wood Architecture & design

TH17-TH18 + APT 19-22 Elevations, prepared
by Black Wood Architecture & design

TH17-TH18 + APT 19-22 Sections, prepared by
Black Wood Architecture & design

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

Page 3 of 16

Page 4

                         DA.37         F   Type A Floor Plan, prepared by Black Wood 7/03/2022
                                           Architecture & design

                         DA.38         F   Type A1 Floor Plan, prepared by Black Wood 7/03/2022
                                           Architecture & design

                         DA.39         F   Type B Floor Plan, prepared by Black Wood 7/03/2022
                                           Architecture & design

                         DA.40         F   Type C Floor Plan, prepared by Black Wood 7/03/2022
                                           Architecture & design

                         DA.41         F   Type D Floor Plan, prepared by Black Wood 7/03/2022
                                           Architecture & design

                         DA.42         F   Type E Floor Plan, prepared by Black Wood 7/03/2022
                                           Architecture & design

                         DA.43         F   Type F Floor Plan, prepared by Black Wood 7/03/2022
                                           Architecture & design

                         DA.44         F   External Materials & Finishes prepared by Black 7/03/2022
                                           Wood Architecture & design

                         DA.46         G   Landscape Area, prepared by Black Wood 30/03/2022
                                           Architecture & design

                         DA.48         F   Perspective 1, prepared     by   Black   Wood 7/03/2022
                                           Architecture & design

                         DA.49         G   Perspective 2, prepared     by   Black   Wood 13/05/2022
                                           Architecture & design

                         DA.51         G   Perspective 4, prepared     by   Black   Wood 13/05/2022
                                           Architecture & design

                         DA.52         G   Perspective 5, prepared     by   Black   Wood 13/05/2022
                                           Architecture & design

                         DA.53         G   Perspective 6, prepared     by   Black   Wood 13/05/2022
                                           Architecture & design

                         DA.54         G   Perspective 7, prepared     by   Black   Wood 13/05/2022
                                           Architecture & design

                         DA.55         G   Perspective 8, prepared     by   Black   Wood 13/05/2022
                                           Architecture & design

                         DA.58         A   AO9 Accessibility Compliance, prepared by 7/03/2022
                                           Black Wood Architecture & design

                         DA.59         A   Type B1 Floor Plan, prepared by Black Wood 7/03/2022
                                           Architecture & design

                         BA0.09        -   West Fence Plan, prepared by Black Wood 29/06/2022
                                           Architecture & design



                                                                                          Page 4 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
DA.37

DA.38

DA.39

DA.40

DA.41

DA.42

DA.43

DA.44

DA.46

DA.48

DA.49

DA.51

DA.52

DA.53

DA.54

DA.55

DA.58

DA.59

BAO.09

Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025

Type A Floor Plan, prepared by Black Wood
Architecture & design

Type A1 Floor Plan, prepared by Black Wood
Architecture & design

Type B Floor Plan, prepared by Black Wood
Architecture & design

Type C Floor Plan, prepared by Black Wood
Architecture & design

Type D Floor Plan, prepared by Black Wood
Architecture & design

Type E Floor Plan, prepared by Black Wood
Architecture & design

Type F Floor Plan, prepared by Black Wood
Architecture & design

External Materials & Finishes prepared by Black
Wood Architecture & design

Landscape Area, prepared by Black Wood
Architecture & design

Perspective 1, prepared by Black Wood
Architecture & design

Perspective 2, prepared by Black Wood
Architecture & design

Perspective 4, prepared by Black Wood
Architecture & design

Perspective 5, prepared by Black Wood
Architecture & design

Perspective 6, prepared by Black Wood
Architecture & design

Perspective 7, prepared by Black Wood
Architecture & design

Perspective 8, prepared by Black Wood
Architecture & design

AO9 Accessibility Compliance, prepared by
Black Wood Architecture & design

Type B1 Floor Plan, prepared by Black Wood
Architecture & design

West Fence Plan, prepared by Black Wood
Architecture & design

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

7103/2022

30/03/2022

7103/2022

13/05/2022

13/05/2022

13/05/2022

13/05/2022

13/05/2022

13/05/2022

7103/2022

7103/2022

29/06/2022

Page 4 of 16

Page 5

                         MCU21/0156.03 – Outdoor Covered Area for Unit 13

                         A103               -      Proposed Site Plan, prepared by Collins Building 16.01.2025
                                                   Designs

                         A202               -      Proposed Ground Plan, prepared by Collins 16.01.2025
                                                   Building Designs

                         A301               -      North & East Elevations, prepared by Collins 16.01.2025
                                                   Building Designs

                         A401               -      Building Cross Section S1, prepared by Collins 16.01.2025
                                                   Building Designs

                      Nature and Extent of Approved Use
               3.     Eighteen (18) small dwellings and 4 x other dwellings are approved.
                      Currency Period
               4.     This development approval lapses if the use has not happened by 4 April 2028, unless an
                      application to extend the currency period is approved by Council.
                      Built Form and Development Appearance
               5.     The maximum height of the development must not exceed 8 metres above the natural and
                      finished ground levels.
               6.     Certification must be submitted to Council from a Licensed Surveyor which certifies that the
                      buildings do not exceed the maximum height requirement of this Decision Notice.
               7.     Deleted
               8.     All air conditioning units or other mechanical equipment must be fully enclosed or screened
                      such that they are not visible from the street frontages nor adjoining properties.
               9.     All deck and balcony areas above ground floor must not be enclosed by permanent fixtures
                      such as shutters, louvres, glass panelling or the like, except where required to satisfy any
                      privacy condition of this Decision Notice.
               10.    The refuse area must be of muted environmental tones to reduce the visual impact of the
                      infrastructure in the streetscape and suitably screened by landscaping where viewed from
                      the street.
               11.    The development must use muted environmental colour tones that blend with the natural
                      environment.
                      Performance Bond
               12.    Security in the form of a cash bond or trading bank guarantee to the sum of $30,000 must
                      be submitted to Council, to secure performance of all conditions of this approval, prior to pre-
                      start meeting. The cash bond or trading bank guarantee will be returned on performance of
                      the conditions of approval less any costs incurred by Council in respect of enforcing
                      performance of this permit. Council reserves the right to call upon the bond or guaranteed
                      sum to effect compliance with conditions.
                      Protection of Privacy
               13.    A maximum of 0.6m of fill is permitted within 1m of the boundary where adjoining a residential
                      use.
               14.    Screening devices for the upper decks of TH4, TH5 & TH8 must be provided as indicated on
                      the approved plans and where necessary to meet privacy conditions of this Decision Notice.
               15.    To ensure privacy is protected between adjoining properties to the north and east,
                      townhouses (TH) 1-8 must:


                                                                                                       Page 5 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
10.

11.

12.

13.

14.

15.

MCU21/0156.03 — Outdoor Covered Area for Unit 13

A103 - Proposed Site Plan, prepared by Collins Building | 16.01.2025
Designs
A202 - Proposed Ground Plan, prepared by Collins | 16.01.2025

Building Designs

A301 - North & East Elevations, prepared by Collins | 16.01.2025
Building Designs

A401 - Building Cross Section S1, prepared by Collins | 16.01.2025
Building Designs
Nature and Extent of Approved Use
Eighteen (18) small dwellings and 4 x other dwellings are approved.
Currency Period

This development approval lapses if the use has not happened by 4 April 2028, unless an
application to extend the currency period is approved by Council.

Built Form and Development Appearance

The maximum height of the development must not exceed 8 metres above the natural and
finished ground levels.

Certification must be submitted to Council from a Licensed Surveyor which certifies that the
buildings do not exceed the maximum height requirement of this Decision Notice.

Deleted

All air conditioning units or other mechanical equipment must be fully enclosed or screened
such that they are not visible from the street frontages nor adjoining properties.

All deck and balcony areas above ground floor must not be enclosed by permanent fixtures
such as shutters, louvres, glass panelling or the like, except where required to satisfy any
privacy condition of this Decision Notice.

The refuse area must be of muted environmental tones to reduce the visual impact of the
infrastructure in the streetscape and suitably screened by landscaping where viewed from
the street.

The development must use muted environmental colour tones that blend with the natural
environment.

Performance Bond

Security in the form of a cash bond or trading bank guarantee to the sum of $30,000 must
be submitted to Council, to secure performance of all conditions of this approval, prior to pre-
start meeting. The cash bond or trading bank guarantee will be returned on performance of
the conditions of approval less any costs incurred by Council in respect of enforcing
performance of this permit. Council reserves the right to call upon the bond or guaranteed
sum to effect compliance with conditions.

Protection of Privacy

A maximum of 0.6m of fill is permitted within 1m of the boundary where adjoining a residential
use.

Screening devices for the upper decks of TH4, TH5 & TH8 must be provided as indicated on
the approved plans and where necessary to meet privacy conditions of this Decision Notice.

To ensure privacy is protected between adjoining properties to the north and east,
townhouses (TH) 1-8 must:

Page 5 of 16

Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025

Page 6

                      a.      provide screening devices to upper level balconies; and/or
                      b.      have a minimum window sill height or 1.7 metres above floor level; and/or
                      c.      be fitted with translucent glazing; and/or
                      d.      be fitted with fixed external screens..
                      Street Identification
               16.    The street address of the development must be clearly visible and discernible from the
                      primary frontage of the site by the provision of a street number and, where appropriate, the
                      building name.
                      Fencing and Walls
               17.    The maximum height any fences adjoining a residential use must not exceed 2.0m above
                      the natural ground level at any point. If additional height is required to satisfy the acoustic
                      condition of this notice, this should be in accordance with an Operational Works approval.
               18.    Street fencing must be provided generally as shown on the approved plans.
               19.    The area of land between the fence and the front property boundary must be densely
                      landscaped to screen any fencing from the street. A mix of understorey and taller species
                      must be included.
               20.    A privacy fence must be constructed to the full length of the northern, southern and eastern
                      boundaries.
               21.    The fence along the boundary adjoining Lot 99 SP106085 and Lot 100 SP106085 (adjoining
                      visitor car spaces) must be constructed to prevent nuisance from car head lights and be
                      acoustically constructed to limit the transfer of noise. Written certification must be provided
                      to Council confirming the acoustic treatments have been incorporated.
                      Clothes Drying Areas
               22.    Each dwelling unit must be provided with access to an outdoor clothes line which is screened
                      from public view.
                      Community Management Statement
               23.    Any proposed Community Management Statement required for the development pursuant to
                      the Body Corporate and Community Management Act 1997 must be submitted to Council for
                      endorsement at the same time as submission of the Building Format Plan (or similar) to
                      Council for compliance assessment.
               24.    All clauses and by-laws of the proposed Community Management Statement must accord
                      with the requirements of this Decision Notice and, in particular, must include the following
                      additional clauses:
                      a.      The site includes a stormwater management and water quality treatment system.
                      b.      The stormwater management and water quality treatment system must be maintained
                              in accordance with the Water by Design (2009) Maintaining Vegetated Stormwater
                              Assets (Version 1).
                      c.      The full cost of maintaining the system in accordance with the Water by Design (2009)
                              Maintaining Vegetated Stormwater Assets (Version 1) must be included in the
                              proposed levies for each dwelling owner/body corporate.
                      Land Amalgamation
               25.    All properties subject to the development must be amalgamated into a single lot prior to
                      endorsement of the first survey plan (plan seal) for the development and evidence of such
                      amalgamation must be submitted to Council.




                                                                                                       Page 6 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
16.

17.

18.
19.

20.

21.

22.

23.

24.

25.

provide screening devices to upper level balconies; and/or
have a minimum window sill height or 1.7 metres above floor level; and/or

be fitted with translucent glazing; and/or

aoe

be fitted with fixed external screens..
Street Identification

The street address of the development must be clearly visible and discernible from the
primary frontage of the site by the provision of a street number and, where appropriate, the
building name.

Fencing and Walls

The maximum height any fences adjoining a residential use must not exceed 2.0m above
the natural ground level at any point. If additional height is required to satisfy the acoustic
condition of this notice, this should be in accordance with an Operational Works approval.

Street fencing must be provided generally as shown on the approved plans.

The area of land between the fence and the front property boundary must be densely
landscaped to screen any fencing from the street. A mix of understorey and taller species
must be included.

A privacy fence must be constructed to the full length of the northern, southern and eastern
boundaries.

The fence along the boundary adjoining Lot 99 SP106085 and Lot 100 SP106085 (adjoining
visitor car spaces) must be constructed to prevent nuisance from car head lights and be
acoustically constructed to limit the transfer of noise. Written certification must be provided
to Council confirming the acoustic treatments have been incorporated.

Clothes Drying Areas

Each dwelling unit must be provided with access to an outdoor clothes line which is screened
from public view.

Community Management Statement

Any proposed Community Management Statement required for the development pursuant to
the Body Corporate and Community Management Act 1997 must be submitted to Council for
endorsement at the same time as submission of the Building Format Plan (or similar) to
Council for compliance assessment.

All clauses and by-laws of the proposed Community Management Statement must accord
with the requirements of this Decision Notice and, in particular, must include the following
additional clauses:

a. The site includes a stormwater management and water quality treatment system.

b. | The stormwater management and water quality treatment system must be maintained
in accordance with the Water by Design (2009) Maintaining Vegetated Stormwater
Assets (Version 1).

Cc. The full cost of maintaining the system in accordance with the Water by Design (2009)
Maintaining Vegetated Stormwater Assets (Version 1) must be included in the
proposed levies for each dwelling owner/body corporate.

Land Amalgamation

All properties subject to the development must be amalgamated into a single lot prior to
endorsement of the first survey plan (plan seal) for the development and evidence of such
amalgamation must be submitted to Council.

Page 6 of 16

Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025

Page 7

                      Noise
               26.    Written certification is required from a suitably qualified person confirming that sound
                      pressure levels from all mechanical plant and equipment comply with the following:
                      a.      Air-conditioning and Refrigeration
                                  i.   7am to 10pm: Maximum level allowable = background + 5dB(A)
                                 ii.   10pm to 7am: Maximum level allowable = background + 3dB(A)
                      b.      Pumps
                                  i.   7am to 7pm: Maximum level allowable = background + 5dB(A)
                                 ii.   7pm to 10pm: Maximum level allowable = background + 3dB(A)
                                iii.   10pm to 7am: No audible noise.
               27.    The certification must be submitted to Council, which certifies that operational noise from any
                      fixed plant and equipment complies and with the requirements of this Decision Notice.
                      Waste Storage
               28.    The developer must provide waste storage and disposal facilities in accordance with
                      Planning Scheme Policy 9, Waste Management, including an external imperviously paved
                      area correctly sized for all refuse and recycling containers and suitably screened from public
                      places and neighbouring properties. A bin wash area is required with a cold-water tap, hose
                      and drain outlet connected to sewer, via a bucket trap. The drain outlet must be designed to
                      prevent storm water entry to the sewerage system.
               29.    Refuse containers must be provided in accordance with the requirements of the
                      Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
                      Regulation 2000, for the storage and collection of refuse.
               ENGINEERING
                      External Works
               30.    Eumundi Noosa Road must be upgraded at the frontage of the development site. The works
                      must be undertaken in accordance with an Operational Works approval and must include in
                      particular:
                      a.      Extending the raised concrete central median so it extends 6m past the southern side
                              of the proposed crossover and making any necessary adjustments to surrounding line
                              marking at the frontage of the site to accommodate this median extension; and
                      b.      Removal of the existing property access crossovers to 89, 91 and 93 Eumundi Noosa
                              Road and reinstatement of the kerb and channel.
                      This condition is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
                      infrastructure.
               31.    Pedestrian and bicycle facilities must be provided for the development. The works must be
                      undertaken in accordance with an Operational Works approval and must include in particular:
                      a.      Construction of a 2.0m wide concrete footpath and verge area to match the balance of
                              the site frontage, including the provision of topsoil and turf where the existing verge is
                              grassed generally in accordance with plan number 31131-C6.1 as prepared by SCG
                              Consulting Engineers.
                      This condition is imposed pursuant to s128 of the Planning Act 2016 being necessary trunk
                      infrastructure identified by Council’s LGIP to service the development.
                      Site Access and Driveways
               32.    A sealed access driveway must be provided from Eumundi Noosa Road to all parking and
                      manoeuvring areas of the development. The works must be undertaken in accordance with
                      an Operational Works approval and must include in particular:



                                                                                                         Page 7 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
Noise

26. Written certification is required from a suitably qualified person confirming that sound
pressure levels from all mechanical plant and equipment comply with the following:

a. _ Air-conditioning and Refrigeration

i. 7am to 10pm: Maximum level allowable = background + 5dB(A)
ii. 10pm to 7am: Maximum level allowable = background + 3dB(A)

b. Pumps

i. 7am to 7pm: Maximum level allowable = background + 5dB(A)
ii. 7pm to 10pm: Maximum level allowable = background + 3dB(A)
iii. | 10pm to 7am: No audible noise.

27. Thecertification must be submitted to Council, which certifies that operational noise from any
fixed plant and equipment complies and with the requirements of this Decision Notice.

Waste Storage

28. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy 9, Waste Management, including an external imperviously paved
area correctly sized for all refuse and recycling containers and suitably screened from public
places and neighbouring properties. A bin wash area is required with a cold-water tap, hose
and drain outlet connected to sewer, via a bucket trap. The drain outlet must be designed to
prevent storm water entry to the sewerage system.

29. Refuse containers must be provided in accordance with the requirements of the
Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
Regulation 2000, for the storage and collection of refuse.

ENGINEERING
External Works

30. Eumundi Noosa Road must be upgraded at the frontage of the development site. The works
must be undertaken in accordance with an Operational Works approval and must include in
particular:

a. Extending the raised concrete central median so it extends 6m past the southern side
of the proposed crossover and making any necessary adjustments to surrounding line
marking at the frontage of the site to accommodate this median extension; and

b. Removal of the existing property access crossovers to 89, 91 and 93 Eumundi Noosa
Road and reinstatement of the kerb and channel.

This condition is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.

31. Pedestrian and bicycle facilities must be provided for the development. The works must be
undertaken in accordance with an Operational Works approval and must include in particular:

a. Construction of a 2.0m wide concrete footpath and verge area to match the balance of
the site frontage, including the provision of topsoil and turf where the existing verge is
grassed generally in accordance with plan number 31131-C6.1 as prepared by SCG
Consulting Engineers.

This condition is imposed pursuant to s128 of the Planning Act 2016 being necessary trunk
infrastructure identified by Council’s LGIP to service the development.

Site Access and Driveways

32. A sealed access driveway must be provided from Eumundi Noosa Road to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance with
an Operational Works approval and must include in particular:

Page 7 of 16
Document Set ID: 23576112

Version: 3, Version Date: 25/02/2025

Page 8

                      a.      A driveway crossover generally in accordance with plan numbers 31131-C6.1 & 31131-
                              C6.2 as prepared by SCG Consulting Engineers and Councils Standard Drawing RS-
                              051.
                      Car Parking
               33.    A minimum of 34 car parking spaces must be provided and marked on the site. The works
                      must be undertaken in accordance with an Operational Works approval and must include in
                      particular:
                      a.      A minimum of 34 covered parking spaces within the total;
                      b.      A minimum of 8 visitor parking spaces within the total, which are clearly marked for that
                              purpose and accessible at all times for visitor use;
                      c.      1 disabled parking space/s within the total; and
                      d.      Dimensions, crossfalls and gradients must be in accordance with Australian Standard
                              AS2890: Parking Facilities.
               34.    Suitable ingress and egress to visitor car spaces must be demonstrated with any Operational
                      Works application. If this cannot be achieved, amended plans relating to this approval must
                      be submitted.
                      Stormwater Drainage
               35.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken in accordance with an Operational Works approval
                      and the Queensland Urban Drainage Manual and be generally in accordance with SCG’s
                      Stormwater Management Plan, ref. 31131 (SWMP), Rev B, dated 02/03/2022 and plan
                      numbers 31131-SW1.1 Rev B, 31131-SW1.2 and 31131-SW1.5 as prepared by SCG
                      Consulting Engineers.
                      Services
               36.    Underground reticulated electricity and telecommunication services must be provided to
                      each unit in accordance with an approval for Operational Works and the standards and
                      requirements of the relevant service provider.
               37.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               38.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater) which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.
                      Easements
               39.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               40.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               41.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.




                                                                                                         Page 8 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
33.

34.

35.

36.

37.

38.

39.

40.

41.

a. | Adriveway crossover generally in accordance with plan numbers 31131-C6.1 & 31131-
C6.2 as prepared by SCG Consulting Engineers and Councils Standard Drawing RS-
051.

Car Parking

A minimum of 34 car parking spaces must be provided and marked on the site. The works
must be undertaken in accordance with an Operational Works approval and must include in
particular:

a. | Aminimum of 34 covered parking spaces within the total;

b. | Aminimum of 8 visitor parking spaces within the total, which are clearly marked for that
purpose and accessible at all times for visitor use;

1 disabled parking space/s within the total; and

Dimensions, crossfalls and gradients must be in accordance with Australian Standard
AS2890: Parking Facilities.

Suitable ingress and egress to visitor car spaces must be demonstrated with any Operational
Works application. If this cannot be achieved, amended plans relating to this approval must
be submitted.

Stormwater Drainage

The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with an Operational Works approval
and the Queensland Urban Drainage Manual and be generally in accordance with SCG’s
Stormwater Management Plan, ref. 31131 (SWMP), Rev B, dated 02/03/2022 and plan
numbers 31131-SW1.1 Rev B, 31131-SW1.2 and 31131-SW1.5 as prepared by SCG
Consulting Engineers.

Services

Underground reticulated electricity and telecommunication services must be provided to
each unit in accordance with an approval for Operational Works and the standards and
requirements of the relevant service provider.

Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.

Certification must be submitted to Council from all relevant service providers (Energex, NBN
and Unitywater) which certifies that the development has met the requirements of this
Decision Notice and all applicable legislation at the time of construction.

Easements

Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.

All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.

All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.

Page 8 of 16

Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025

Page 9

                      Earthworks and Retaining Walls
               42.    All fill, associated batters and retaining structures, both above and below ground must be
                      contained entirely within the subject site unless written permission from the respective
                      landowner(s) is provided to Council. All earthworks must be undertaken in accordance with
                      an Operational Works approval and be generally in accordance with plan numbers 31131-
                      C3.1 – “Bulk Earthworks”, and 31131-C3.2 – “Earthworks Sections”, prepared by SCG
                      Consulting Engineers.
               43.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Damage to Services and Assets
               44.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
                      Landscaping Works
               45.    The development site must be landscaped in accordance with Planning Scheme Policy PSP2
                      – Landscaping and cover at least 35% of the site. The works must be undertaken in
                      accordance with an Operational Works approval and the Noosa Plan for that specific area
                      and must include in particular:
                      a.      the works shown on the Approved Plans;
                      b.      provide a planting and plant schedule including species and pot size;
                      c.      a minimum 0.5 metre wide densely landscaped strip between the fence and the front
                              property boundary on Eumundi Noosa Road frontage of the subject site, in accordance
                              with the Plan BA0.09 – West Fence Plan, exclusive of the access driveway, generally
                              uncompromised by infrastructure items;
                      d.      a minimum 1 metre wide densely landscaped strip planted at a maximum of 1.5m
                              centres behind the Eumundi Noosa Road frontage fence;
                      e.      minimum 1 metre wide garden to the full length of both side boundaries and rear
                              boundary. The gardens must include screening trees planted at a maximum of 1.5m
                              centres and have a 200mm pot size. The trees must have a mature height of at least
                              6m;
                      f.      landscaping required at front entry area;
                      g.      suitable screening trees planted at a minimum 6m height and maximum 1.5m centres
                              around the edge of the bioretention in particular along the rear and side boundaries;
                      h.      Provision of 1 street tree within the road reserve for every 8m of road frontage (location
                              considering sightlines);
                      i.      1 x 45 litre feature shade tree in each garden.
               46.    Bioretention area: The area provided is suitable for screening plantings of trees (eg.
                      melaleuca quinquinervia). Provide 45L trees at maximum 3m spacings within this area
                      outside of the filter media area to visually screen the development from adjacent properties.




                                                                                                         Page 9 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
Earthworks and Retaining Walls

42. All fill, associated batters and retaining structures, both above and below ground must be
contained entirely within the subject site unless written permission from the respective
landowner(s) is provided to Council. All earthworks must be undertaken in accordance with
an Operational Works approval and be generally in accordance with plan numbers 31131-
C3.1 — “Bulk Earthworks”, and 31131-C3.2 — “Earthworks Sections”, prepared by SCG
Consulting Engineers.

43.  Allretaining walls must be designed and constructed in accordance with the planning scheme
and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
safety fence.

Damage to Services and Assets

44. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:

a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or

b. — where otherwise, upon completion of the works associated with the development.

Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.

Landscaping Works

45. The development site must be landscaped in accordance with Planning Scheme Policy PSP2
— Landscaping and cover at least 35% of the site. The works must be undertaken in
accordance with an Operational Works approval and the Noosa Plan for that specific area
and must include in particular:

a. the works shown on the Approved Plans;
b. provide a planting and plant schedule including species and pot size;

Cc. a minimum 0.5 metre wide densely landscaped strip between the fence and the front
property boundary on Eumundi Noosa Road frontage of the subject site, in accordance
with the Plan BAO.09 — West Fence Plan, exclusive of the access driveway, generally
uncompromised by infrastructure items;

d. a minimum 1 metre wide densely landscaped strip planted at a maximum of 1.5m
centres behind the Eumundi Noosa Road frontage fence;

e. minimum 1 metre wide garden to the full length of both side boundaries and rear
boundary. The gardens must include screening trees planted at a maximum of 1.5m
centres and have a 200mm pot size. The trees must have a mature height of at least
6m;

f. landscaping required at front entry area;

g. suitable screening trees planted at a minimum 6m height and maximum 1.5m centres
around the edge of the bioretention in particular along the rear and side boundaries;

h. Provision of 1 street tree within the road reserve for every 8m of road frontage (location
considering sightlines);

i. 1 x 45 litre feature shade tree in each garden.

46. Bioretention area: The area provided is suitable for screening plantings of trees (eg.
melaleuca quinquinervia). Provide 45L trees at maximum 3m spacings within this area
outside of the filter media area to visually screen the development from adjacent properties.

Page 9 of 16
Document Set ID: 23576112

Version: 3, Version Date: 25/02/2025

Page 10

               47.    All landscape works must be established and maintained in accordance with the approved
                      design for the life of the development, and in a manner that ensures healthy, sustained and
                      vigorous plant growth. All plant material must be allowed to grow to full form and be
                      refurbished when its life expectancy is reached.
               48.    All landscape works must be maintained generally in accordance with the approved design
                      for the life of the development.
                      Stormwater Drainage
               49.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken in accordance with an Operational Works approval
                      and the Queensland Urban Drainage Manual, and must include in particular:
                      a.      the works described in Site Based Stormwater Management Plan (prepared by SCG
                              Consulting Engineers, dated 02/03/2022);
                      b.      the use of gravity stormwater drainage and not surcharge pits;
                      c.      Design of the internal roadway drainage to ensure all floor level including garages
                              (particularly on the downslope side of the internal roadway) are not inundated in the
                              1%AEP climate change event at Year 2100;
                      d.      Design of the internal drainage system to ensure all flows in the 1%AEP climate change
                              event at Year 2100 reach the detention basin;
                      e.      Updated analysis for the portion of the site discharging to Eumundi-Noosa Rd either
                              demonstrating that the roadway flow criteria of QUDM (Section 7.4) are still achieved
                              in the road for the 1%AEP event despite the increase in discharge from the site, or
                              provision of detention for this part of the site such that non-worsening discharge to the
                              road is achieved.
                      Stormwater
               50.    In conjunction with the application for Operational Works approval, provide CCTV survey of
                      the downstream stormwater network and demonstrate that the system has the capacity
                      assumed in the Stormwater Management Plan (prepared by SCG Consulting Engineers,
                      dated 02/03/2022). Maintenance and rectification of the system is to be undertaken if
                      required to restore system capacity, prior to commencement of works within the development
                      site.
                      Stormwater Quality Management
               51.    A stormwater quality treatment system must be provided for the development. The works
                      must be undertaken in accordance with an Operational Works approval and the latest version
                      of the Water Sensitive Urban Design Technical Design Guidelines for South East
                      Queensland, and must include in particular:
                      a.      stormwater quality treatment devices of a size and location generally in accordance
                              with those shown in Site Based Stormwater Management Plan (prepared by SCG
                              Consulting Engineers, dated 02/03/2022)
                      b.      bioretention devices which:
                               i.      are modified to include a maintenance access ramp from the internal roadway to
                                       the floor of the basin with minimum width of 2.5m;
                              ii.      are designed generally in accordance with the Bioretention Technical Design
                                       Guidelines (Water by Design, 2014)
                             iii.      are designed generally in accordance with IPWEA Standard Drawing No. DS-
                                       073, DS-075, DS-076, and DS-078
                             iv.       are provided with a free-draining outlet from the sub-soil drainage system
                      c.      Rainwater storage and reuse consistent with the Site Based Stormwater Management
                              Plan (prepared by SCG Consulting Engineers, dated 02/03/2022)


                                                                                                         Page 10 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
47. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.

48. All landscape works must be maintained generally in accordance with the approved design
for the life of the development.

Stormwater Drainage

49. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with an Operational Works approval
and the Queensland Urban Drainage Manual, and must include in particular:

a. the works described in Site Based Stormwater Management Plan (prepared by SCG
Consulting Engineers, dated 02/03/2022);

b. the use of gravity stormwater drainage and not surcharge pits;

Cc. Design of the internal roadway drainage to ensure all floor level including garages
(particularly on the downslope side of the internal roadway) are not inundated in the
1%AEP climate change event at Year 2100;

d. Design of the internal drainage system to ensure all flows in the 1%AEP climate change
event at Year 2100 reach the detention basin;

e. Updated analysis for the portion of the site discharging to Eumundi-Noosa Rd either
demonstrating that the roadway flow criteria of QUDM (Section 7.4) are still achieved
in the road for the 1%AEP event despite the increase in discharge from the site, or
provision of detention for this part of the site such that non-worsening discharge to the
road is achieved.

Stormwater

50. In conjunction with the application for Operational Works approval, provide CCTV survey of
the downstream stormwater network and demonstrate that the system has the capacity
assumed in the Stormwater Management Plan (prepared by SCG Consulting Engineers,
dated 02/03/2022). Maintenance and rectification of the system is to be undertaken if
required to restore system capacity, prior to commencement of works within the development
site.

Stormwater Quality Management

51. A stormwater quality treatment system must be provided for the development. The works
must be undertaken in accordance with an Operational Works approval and the latest version
of the Water Sensitive Urban Design Technical Design Guidelines for South East
Queensland, and must include in particular:

a. stormwater quality treatment devices of a size and location generally in accordance
with those shown in Site Based Stormwater Management Plan (prepared by SCG
Consulting Engineers, dated 02/03/2022)

b. bioretention devices which:

i. are modified to include a maintenance access ramp from the internal roadway to
the floor of the basin with minimum width of 2.5m;

ii. are designed generally in accordance with the Bioretention Technical Design
Guidelines (Water by Design, 2014)

iii. are designed generally in accordance with IPWEA Standard Drawing No. DS-
073, DS-075, DS-076, and DS-078

iv. are provided with a free-draining outlet from the sub-soil drainage system

Cc. Rainwater storage and reuse consistent with the Site Based Stormwater Management
Plan (prepared by SCG Consulting Engineers, dated 02/03/2022)

Page 10 of 16
Document Set ID: 23576112

Version: 3, Version Date: 25/02/2025

Page 11

               52.    Permanent educational signage must be erected to educate the public about the function of
                      the bioretention device(s).
               53.    All stormwater quality treatment devices must be maintained in accordance with the Water
                      by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1). Records of all
                      maintenance activities undertaken must be kept and made available to Council upon request
               54.    Any proposed Community Management Statement required for the development must
                      include Water by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1) and
                      must include the full cost of maintaining the system in accordance with Water by Design
                      (2009) Maintaining Vegetated Stormwater Assets (Version 1). The cost of maintaining the
                      system must be included in the proposed levies for each unit owner.
                      Erosion and Sediment Control
               55.    In conjunction with the application for Operational Works approval, provide an erosion and
                      sediment control plan, prepared in accordance with Best Practice Erosion and Sediment
                      Control (IECA, 2008) and which achieves the construction phase stormwater design
                      objectives of the State Planning Policy 2017. In addition, the ESCP is to demonstrate how
                      the downstream residential properties will be protected from increases in peak flows and
                      contaminated (with sediment) site runoff through all stages of construction.
               DEMOLITION
                      Performance Bond
               56.    Security in the form of a cash bond or trading bank guarantee to the sum of $5,000 must be
                      submitted to Council prior to the issue of a Development Permit for Building Works for
                      demolition, to secure the demolition conditions of this approval. The cash bond or trading
                      bank guarantee will be returned on performance of the demolition conditions of this approval
                      less any costs incurred by Council in respect of enforcing performance of these demolition
                      conditions. Council reserves the right to call upon the bond or guaranteed sum to effect
                      compliance with conditions.
                      Works
               57.    Demolition must be undertaken in a manner that causes no detrimental effect upon the
                      amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
                      hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
                      in accordance with the nuisance provisions of the Environmental Protection Act 1994.
                      Waste management
               58.    A Waste Management Plan (demolition) must be submitted in accordance with Planning
                      Scheme Policy PSP10 - Waste Management and approved by Council’s Waste Coordinator
                      prior to issue of a development permit for Building Works for demolition, removal or
                      relocation.
                      The purpose of the Waste Management Plan is to facilitate the segregation of waste for the
                      effective reuse and recycling of such materials. Segregated wastes attract significantly
                      reduced disposal fees at the landfill with some items free. Higher gate fees are charged for
                      mixed waste.
                      Waste storage areas must provide for adequate separation of all reusable, recyclable and
                      waste materials. These must be located so that they are convenient and safe to use.
                      The Plan must contain the following information:
                      a.      The areas for the storage and separation of waste shown on a site plan;
                      b.      A waste management table as indicated below is to be completed showing how waste
                              material is to be segregated - recycled – reused or disposed; and
                      c.      Table – Waste Management Table




                                                                                                     Page 11 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
52.

53.

54.

55.

Permanent educational signage must be erected to educate the public about the function of
the bioretention device(s).

All stormwater quality treatment devices must be maintained in accordance with the Water
by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1). Records of all
maintenance activities undertaken must be kept and made available to Council upon request

Any proposed Community Management Statement required for the development must
include Water by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1) and
must include the full cost of maintaining the system in accordance with Water by Design
(2009) Maintaining Vegetated Stormwater Assets (Version 1). The cost of maintaining the
system must be included in the proposed levies for each unit owner.

Erosion and Sediment Control

In conjunction with the application for Operational Works approval, provide an erosion and
sediment control plan, prepared in accordance with Best Practice Erosion and Sediment
Control (IECA, 2008) and which achieves the construction phase stormwater design
objectives of the State Planning Policy 2017. In addition, the ESCP is to demonstrate how
the downstream residential properties will be protected from increases in peak flows and
contaminated (with sediment) site runoff through all stages of construction.

DEMOLITION

56.

57.

58.

Performance Bond

Security in the form of a cash bond or trading bank guarantee to the sum of $5,000 must be
submitted to Council prior to the issue of a Development Permit for Building Works for
demolition, to secure the demolition conditions of this approval. The cash bond or trading
bank guarantee will be returned on performance of the demolition conditions of this approval
less any costs incurred by Council in respect of enforcing performance of these demolition
conditions. Council reserves the right to call upon the bond or guaranteed sum to effect
compliance with conditions.

Works

Demolition must be undertaken in a manner that causes no detrimental effect upon the
amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
in accordance with the nuisance provisions of the Environmental Protection Act 1994.

Waste management

A Waste Management Plan (demolition) must be submitted in accordance with Planning
Scheme Policy PSP10 - Waste Management and approved by Council’s Waste Coordinator
prior to issue of a development permit for Building Works for demolition, removal or
relocation.

The purpose of the Waste Management Plan is to facilitate the segregation of waste for the
effective reuse and recycling of such materials. Segregated wastes attract significantly
reduced disposal fees at the landfill with some items free. Higher gate fees are charged for
mixed waste.

Waste storage areas must provide for adequate separation of all reusable, recyclable and
waste materials. These must be located so that they are convenient and safe to use.

The Plan must contain the following information:
a. | The areas for the storage and separation of waste shown on a site plan;

b. | Awaste management table as indicated below is to be completed showing how waste
material is to be segregated - recycled — reused or disposed; and

Cc. Table — Waste Management Table

Page 11 of 16

Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025

Page 12

                          MATERIALS ON-SITE                                   DESTINATION
                                                                  Re-use and Recycling                    Disposal
                          Expected waste    Estimated  On-site                 Off-site               *specify contractor
                          materials         volume(m³) *specify     proposed   *specify contractor    and landfill site or
                                                         re-use or on-site     and recycling outlet   other disposal site
                                                         recycling methods
                          Excavation
                          material
                          Green waste
                          Bricks
                          Concrete
                          Timber-please
                          specify
                          Plasterboard
                          Metals - please
                          specify
                          Asbestos
                          Other - please
                          specify
                      Note * If a demolition contractor is undertaking works, then the Waste Management table is
                      to be completed by the demolition contractor.
                      Damage to infrastructure
               59.    Any damage to footpaths, street plantings, natural vegetation/trees kerb and channel,
                      bridges or roadways must be repaired or reinstated to at least pre-existing conditions.
                      Vacant site
               60.    The site must be left clean and tidy free from debris such as concrete, wire, rubble, brick/s
                      and the like. If the site remains vacant for more than 30 days the lot/s must be turfed or
                      landscaped in accordance with Planning Scheme Policy PSP 2 – Landscaping and to the
                      satisfaction of Council so as to not cause nuisance to the surrounding area.
               61.    All waste materials must be removed from site.
                      Litter, erosion and sediment control
               62.    Litter, erosion and sediment control measures must be installed and maintained until soils
                      are stabilised by turf, vegetation or sealed.
                      Note: it is an offence under the Environmental Protection Act 1994 to deposit or potentially
                      allow litter, waste, soil, or other contaminants to enter a waterway or storm water drainage
                      system (e.g. roadside gutter).
                      Asbestos
               63.    Removal of building materials containing asbestos must be undertaken by a licensed
                      asbestos removalist.
               64.    Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
                      requires a licensed asbestos removalist to give notice to Workplace Health and Safety
                      Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
                      commences. Notification must be made using Form 65: Notification of licensed asbestos
                      removal work, demolition work or emergency demolition.
               65.    All building materials containing asbestos products are wrapped and disposed of in
                      accordance with the Public Health Regulation 2006 and the Environmental Protection
                      Regulation 2008.
                      Note: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
                      businesses that transport asbestos waste, and landfills that accept this waste.




                                                                                                       Page 12 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
59.

60.

61.

62.

63.

64.

65.

 

MATERIALS ON-SITE DESTINATION

 

 

Re-use and Recycling Disposal
Expected waste | Estimated On-site Off-site *specify contractor
materials volume(m?) *specify proposed | “specify contractor | and landfill site or

re-use or on-site | and recycling outlet | other disposal site
recycling methods

 

Excavation
material

 

Green waste

 

Bricks

 

Concrete

 

Timber-please
specify

 

Plasterboard

 

Metals - please
specify

 

Asbestos

 

Other - please
specify

 

 

 

 

 

 

 

Note * If a demolition contractor is undertaking works, then the Waste Management table is
to be completed by the demolition contractor.

Damage to infrastructure

Any damage to footpaths, street plantings, natural vegetation/trees kerb and channel,
bridges or roadways must be repaired or reinstated to at least pre-existing conditions.

Vacant site

The site must be left clean and tidy free from debris such as concrete, wire, rubble, brick/s
and the like. If the site remains vacant for more than 30 days the lot/s must be turfed or
landscaped in accordance with Planning Scheme Policy PSP 2 — Landscaping and to the
satisfaction of Council so as to not cause nuisance to the surrounding area.

All waste materials must be removed from site.
Litter, erosion and sediment control

Litter, erosion and sediment control measures must be installed and maintained until soils
are stabilised by turf, vegetation or sealed.

Note: it is an offence under the Environmental Protection Act 1994 to deposit or potentially
allow litter, waste, soil, or other contaminants to enter a waterway or storm water drainage
system (e.g. roadside gutter).

Asbestos

Removal of building materials containing asbestos must be undertaken by a licensed
asbestos removalist.

Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
requires a licensed asbestos removalist to give notice to Workplace Health and Safety
Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
commences. Notification must be made using Form 65: Notification of licensed asbestos
removal work, demolition work or emergency demolition.

All building materials containing asbestos products are wrapped and disposed of in
accordance with the Public Health Regulation 2006 and the Environmental Protection
Regulation 2008.

Note: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
businesses that transport asbestos waste, and landfills that accept this waste.

Page 12 of 16

Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025

Page 13

               66.    All building materials containing asbestos, including asbestos cement sheeting or roofing and
                      lagging are removed from the building prior to demolition/relocation.
                      Plumbing and Drainage
               67.    It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
                      demolition of a building, the existing sanitary drain upstream from the connection point for a
                      service provider’s sewerage system must be sealed water tight. This work is deemed as
                      notifiable Work and must be carried out by a suitably licenced plumber who must submit an
                      As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
                      Construction Commission) within 10 days of completing the work.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      Building and Construction Industry (Portable Long Service Leave) Levy
               1.     The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid.
                      Co-ordination of Operational Works Assessment
               2.     Additional application fees apply to Operational Work applications where the different
                      aspects of the works are lodged separately. Significant savings in application fees will result
                      if all works are lodged in a single application.
                      Preparation of a Preliminary Construction Management Plan
               3.     A preliminary Construction Management Plan must be submitted with the Operational Works
                      application and must address the following:
                      a.      Appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD);
                      b.      Provision for safe pedestrian access across the frontage of the site both during daily
                              construction and after daily construction has ceased; and
                      c.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site, through the implementation of appropriate erosion and sediment
                              control measures.
                      Infrastructure Charges
               4.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
                      Aboriginal Cultural Heritage Act 2003
               5.     There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
                      approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
                      The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
                      carries out an activity must take all reasonable and practicable measures to ensure the
                      activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
                      duty of care. Substantial monetary penalties may apply to individuals or corporations
                      breaching this duty of care. Injunctions may also be issued by the Land and Resources
                      Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity


                                                                                                       Page 13 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
66. All building materials containing asbestos, including asbestos cement sheeting or roofing and
lagging are removed from the building prior to demolition/relocation.

Plumbing and Drainage

67. It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019 that at
demolition of a building, the existing sanitary drain upstream from the connection point for a
service provider's sewerage system must be sealed water tight. This work is deemed as
notifiable Work and must be carried out by a suitably licenced plumber who must submit an
As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
Construction Commission) within 10 days of completing the work.

5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES

The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:

Building and Construction Industry (Portable Long Service Leave) Levy

1. | The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.

Co-ordination of Operational Works Assessment

2. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees will result
if all works are lodged in a single application.

Preparation of a Preliminary Construction Management Plan

3. Apreliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:

a. Appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD);

b. Provision for safe pedestrian access across the frontage of the site both during daily
construction and after daily construction has ceased; and

Cc. Maintenance and protection of water quality and existing drainage lines through the
construction site, through the implementation of appropriate erosion and sediment
control measures.

Infrastructure Charges

4. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qid.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges

Aboriginal Cultural Heritage Act 2003

5. | There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).

 

 

The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
carries out an activity must take all reasonable and practicable measures to ensure the
activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
duty of care. Substantial monetary penalties may apply to individuals or corporations
breaching this duty of care. Injunctions may also be issued by the Land and Resources
Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity

Page 13 of 16
Document Set ID: 23576112

Version: 3, Version Date: 25/02/2025

Page 14

                      that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
                      of Aboriginal cultural heritage.
                      You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
                      Equitable Access and Facilities
               6.     The plans for the proposed building work have NOT been assessed for compliance with the
                      requirements of the National Construction Code - Building Code of Australia (Volume 1) as
                      they relate to people with disabilities. Your attention is also directed to the fact that in addition
                      to the requirements of the National Construction Code as they relate to people with
                      disabilities, one or more of the following may impact on the proposed building work:
                      a.      the Disability Discrimination Act 1992 (Commonwealth);
                      b.      the Anti-Discrimination Act 1991 (Queensland); and
                      c.      the Disability (Access to Premises – Buildings) Standards.
                      Development Compliance Inspection
               7.     Prior to the commencement of the use, please contact Council's Development Assessment
                      Branch to arrange a Development Compliance Inspection.
                      Resubmission of Amended Plans Required
               8.     The conditions of this Decision Notice require resubmission of plans to Council with
                      amendments. Please address the amended plan/s to Council’s Development Assessment
                      Branch with the Reference No. MCU21/0156 separate to any Operational Works application.
                      To avoid delays and assessment issues with the Operational Works application, it is
                      recommended the plan/s be resubmitted prior to lodgement of any Operational Works
                      application. However, should the plan/s not be submitted, the applicant is advised that a
                      Preliminary Approval for OPW may be issued in lieu of a Development Permit.
                      Balance Lot for Staged Building Format Plans
               9.     In accordance with the Planning Act 2016, any proposal to stage the titling arrangements of
                      the development such that a Building Format Plan is registered with a balance lot for future
                      development will first require a Development Permit for Reconfiguring a Lot be obtained from
                      Council.
                      Sustainability
               10.    In line with Noosa Council’s Corporate Plan, Council seeks to encourage sustainable building
                      design for residential and commercial development. Council encourages the use of
                      sustainable building materials, energy efficient fittings, solar hot water, photovoltaic systems
                      (including the use of inverter/charges), water saving devices and rainwater harvesting. For
                      further information go to http://www.noosa.qld.gov.au/sustainable-homes
                      Fires in Urban Areas
               11.    Please note that in urban areas of the Noosa Shire Council area, fires are prohibited except
                      where in an appliance used for domestic heating or cooking purposes, which must comply
                      with particular Standards. Any area identified as a fire pit area on approved plans is to be in
                      accordance with Local Law & Subordinate Local Law No. 3, Schedule 3. Refer to the
                      following link for details:
                      https://www.noosa.qld.gov.au/community/local-laws/local-laws-overview
               7.     PROPERTY NOTES

               Not applicable
               8.     VARIATION APPROVAL DETAILS

               Not applicable.




                                                                                                           Page 14 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
10.

11.

7.

that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
of Aboriginal cultural heritage.

You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
Equitable Access and Facilities

The plans for the proposed building work have NOT been assessed for compliance with the
requirements of the National Construction Code - Building Code of Australia (Volume 1) as
they relate to people with disabilities. Your attention is also directed to the fact that in addition
to the requirements of the National Construction Code as they relate to people with
disabilities, one or more of the following may impact on the proposed building work:

a. _ the Disability Discrimination Act 1992 (Commonwealth);
b. the Anti-Discrimination Act 1991 (Queensland); and

Cc. the Disability (Access to Premises — Buildings) Standards.
Development Compliance Inspection

Prior to the commencement of the use, please contact Council's Development Assessment
Branch to arrange a Development Compliance Inspection.

Resubmission of Amended Plans Required

The conditions of this Decision Notice require resubmission of plans to Council with
amendments. Please address the amended plan/s to Councils Development Assessment
Branch with the Reference No. MCU21/0156 separate to any Operational Works application.
To avoid delays and assessment issues with the Operational Works application, it is
recommended the plan/s be resubmitted prior to lodgement of any Operational Works
application. However, should the plan/s not be submitted, the applicant is advised that a
Preliminary Approval for OPW may be issued in lieu of a Development Permit.

Balance Lot for Staged Building Format Plans

In accordance with the Planning Act 2016, any proposal to stage the titling arrangements of
the development such that a Building Format Plan is registered with a balance lot for future
development will first require a Development Permit for Reconfiguring a Lot be obtained from
Council.

Sustainability

In line with Noosa Council’s Corporate Plan, Council seeks to encourage sustainable building
design for residential and commercial development. Council encourages the use of
sustainable building materials, energy efficient fittings, solar hot water, photovoltaic systems
(including the use of inverter/charges), water saving devices and rainwater harvesting. For
further information go to http://www.noosa.qld.gov.au/sustainable-homes

 

Fires in Urban Areas

Please note that in urban areas of the Noosa Shire Council area, fires are prohibited except
where in an appliance used for domestic heating or cooking purposes, which must comply
with particular Standards. Any area identified as a fire pit area on approved plans is to be in
accordance with Local Law & Subordinate Local Law No. 3, Schedule 3. Refer to the
following link for details:

https://www.noosa.qld.gov.au/community/local-laws/local-laws-overview

 

PROPERTY NOTES

Not applicable

8.

VARIATION APPROVAL DETAILS

Not applicable.

Page 14 of 16

Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025

Page 15

               9.        FURTHER DEVELOPMENT PERMITS REQUIRED

                   Type of Development Permit Required                          Subject of the required Development Permit

                   Development Permit for Operational Works                     Access, carparking, Stormwater, Drainage work,
                                                                                Earthworks, Landscaping, Vegetation Clearing.

                   Development Permit for Building Works                        All building work.

               10.       SUBMISSIONS

               Not applicable.
               11.       RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               12.       OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.

               Yours faithfully,




               Georgina Schramm
               Senior Development Planner
               Enc:      Appeal Rights
                         Approved Plans/Documents



               DECISION NOTICE HISTORY
               •     Original Decision Notice – 4 April 2022
               •     Negotiated Decision Notice – 1 June 2022, with an amendment to
                     conditions 2, 15 & 25; delete condition 7.
               •     Decision Notice – Minor – MCU21/0156.01 – 8 July 2022; Amend
                     conditions 2 & 45.
               •     Decision Notice – Generally in Accordance – MCU21/0156.02; 20
                     February 2024,
               •     Decision Notice – Minor – 25 February 2025, amend condition 2.




                                                                                                                 Page 15 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
9. FURTHER DEVELOPMENT PERMITS REQUIRED

Type of Development Permit Required Subject of the required Development Permit

Development Permit for Operational Works — Access, carparking, Stormwater, Drainage work,
Earthworks, Landscaping, Vegetation Clearing.

Development Permit for Building Works All building work.

10. SUBMISSIONS
Not applicable.
11. RIGHTS OF APPEAL

You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.

During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.

12. OTHER DETAILS

If you wish to obtain more information about the decision, electronic copies are available on line at
www.noosa.qld.gov.au or at Council Offices.

Yours faithfully,

Cel wom

Georgina Schramm
Senior Development Planner

Enc: Appeal Rights
Approved Plans/Documents

DECISION NOTICE HISTORY
e Original Decision Notice — 4 April 2022

e Negotiated Decision Notice — 1 June 2022, with an amendment to
conditions 2, 15 & 25; delete condition 7.

e Decision Notice — Minor —- MCU21/0156.01 — 8 July 2022; Amend
conditions 2 & 45.

e Decision Notice — Generally in Accordance —- MCU21/0156.02; 20
February 2024,

e Decision Notice — Minor — 25 February 2025, amend condition 2.

Page 15 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025

Page 16

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                 Page 16 of 16
Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025


[OCR of page images]
PLANNING ACT 2016 & PLANNING REGULATION 2017

wd NOOSA Appeal Rights
ar

Council

Chapter 6 Dispute resolution
Part 1 Appeal rights
229 Appeals to tribunal or P&E Court
(1) Schedule 1 of the Planning Act 2016 states —
(a) Matters that may be appealed to —
(i) either a tribunal or the P&E Court; or
(ii) only a tribunal; or
(iii) only the P&E Court; and
(b) The person-
(i) who may appeal a matter (the appellant); and
(ii) who is a respondent in an appeal of the matter; and
(iii) who is a co-respondent in an appeal of the matter; and
(

iv}

who may elect to be a co-respondent in an appeal of the
matter.

(2) An appellant may start an appeal within the appeal period.
(3) The appeal period is —
(a) for an appeal by a building advisory agency — 10 business

days after a decision notice for the decision is given to the
agency; or

(b) for an appeal against a deemed refusal — at any time after the
deemed refusal happens; or

(c) for an appeal against a decision of the Minister, under chapter
7, part 4, to register premises or to renew the registration of
premises — 20 business days after a notice us published under
section 269(3)(a) or (4); or

(d) for an appeal against an infrastructure charges notice — 20
business days after the infrastructure charges notice is given
to the person; or

(e) for an appeal about a deemed approval of a development
application for which a decision notice has not been given —
30 business days after the applicant gives the deemed
approval notice to the assessment manager; or

(f) for any other appeal — 20 business days after a notice of the
decision for the matter, including an enforcement notice, is
given to the person.

Note —

See the P&E Court Act for the court's power to extend the appeal

period.

(4) Each respondent and co-respondent for an appeal may be heard
in the appeal.

(5) If an appeal is only about a referral agency's response, the
assessment manager may apply to the tribunal or P&E Court to
withdraw from the appeal.

(6) To remove any doubt. It is declared that an appeal against an
infrastructure charges notice must not be about-

(a) the adopted charge itself; or
(b) for a decision about an offset or refund-

(i) the establishment cost of trunk infrastructure identified in
aLGIP; or

(ii) the cost of infrastructure decided using the method
included in the local government's charges resolution.

230 Notice of appeal

(1) An appellant starts an appeal by lodging, with the registrar of the
tribunal or P&E Court, a notice of appeal that-

(a) is in the approved form; and
(b) succinctly states the grounds of the appeal.

(2) The notice of appeal must be accompanied by the required fee.

Document Set ID: 23576112
Version: 3, Version Date: 25/02/2025

(3)

(4)

(5)

(6)

The appellant or, for an appeal to a tribunal, the registrar must,
within the service period, give a copy of the notice of appeal to —

(a) the respondent for the appeal; and
(b) each co-respondent for the appeal; and

(c) for an appeal about a development application under schedule
1, table 1, item 1 - each principal submitter for the
development application; and

(d) for and appeal about a change application under schedule 1,
table 1, item 2 - each principal submitter for the change
application; and

(e) each person who may elect to become a co-respondent for the
appeal, other than an eligible submitter who is not a principal
submitter in an appeal under paragraph (c) or (d); and

(f) for an appeal to the P&E Court — the chief executive; and

(g) for an appeal to a tribunal under another Act — any other
person who the registrar considers appropriate.

The service period is —

(a) if a submitter or advice agency started the appeal in the P&E
Court — 2 business days after the appeal has started; or

(b) otherwise — 10 business days after the appeal is started.

A notice of appeal given to a person who may elect to be a co-
respondent must state the effect of subsection (6).

A person elects to be a co-respondent by filing a notice of election,
in the approved form, within 10 business days after the notice of
appeal is given to the person.

231 Other appeals

(1)

(2)

(3)

(4)

Subject to this chapter, schedule 1 and the P&E Court Act, unless
the Supreme Court decides a decision or other matter under this
Act is affected by jurisdictional error, the decision or matter is non-
appealable.

The Judicial Review Act 1991, part 5 applies to the decision or
matter to the extent it is affected by jurisdictional error.

A person who, but for subsection (1) could have made an
application under the Judicial Review Act 1997 in relation to the
decision or matter, may apply under part 4 of that Act for a
statement of reasons in relation to the decision or matter.

In this section —
decision includes-

(a) conduct engaged in for the purpose of making a decision; and
(b) other conduct that relates to the making of a decision; and

(c) the making of a decision or failure to make a decision; and
(d) a purported decision; and

(e) adeemed refusal.

non-appealable, for a decision or matter, means the decision or
matter-

(a) is final and conclusive; and

(b) may not be challenged, appealed against, reviewed, quashed,
set aside or called into question in any other way under the
Judicial Review Act 1991 or otherwise, whether by the
Supreme Court, another court, a tribunal or another entity; and

(c) is not subject to any declaratory, injunctive or other order of
the Supreme Court, another court, a tribunal or another entity
on any ground.

232 Rules of the P&E Court

(1)

(2)

A person who is appealing to the P&E Court must comply with the
rules of the court that apply to the appeal.

However, the P&E Court may hear and decide an appeal even if
the person has not complied with the rules of the P&E Court

Page 16 of 16

Used in these records

About this file

File size
200 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval MCU21_0156.03 [As Published].pdf · 200 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.