Attachment C - SWMP Report by Bax Engineering_compressed
CIVIL ENGINEERING PROJECT MANAGEMENT
SEDIMENT AND EROSION CONTROL
SITE BASED STORMWATER MANAGEMENT PLAN
Material Change of Use – Industrial Warehouses
9 Bartlett Road, NOOSAVILLE
DATE: 06.02.22 REF: 124-003-001
ATT: Mr Michael Klobas EMAIL: [email protected]
REV: A
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 30 pages
Page 2
CONTENTS PAGE
Lawful Point of Discharge ............................................................................................ 7
External Catchment and Overland Flows .................................................................... 7
Stormwater Infrastructure........................................................................................... 7
Flooding ....................................................................................................................... 8
SPEL Stormsacks ........................................................................................................ 10
Page 2 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 3
LIST OF FIGURES
Figure 1 - Locality Plan ......................................................................................................................................... 5
Figure 2 – Stormwater Network and Contour Plan ............................................................................................. 6
Figure 3 – Proposed catchment plan ................................................................................................................... 9
LIST OF TABLES
Table 1 - General Construction Pollutants ......................................................................................................... 10
LIST OF APPENDICES
Appendix A Engineering Plans
Prepared by Bax Engineering dated February 2022
Appendix B Water Quality Device
SPEL Stormwater Design
Appendix C Flood Mapping
Noosa Council Mapping
Page 3 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 4
INTRODUCTION
Bax Engineering has been commissioned by Mr Michael Klobas of Juklo Pty Ltd to provide a site-based
stormwater management plan for the proposed development at 9 Bartlett Road, Noosaville.
The report is intended to support the development application seeking approval for a Material Change of Use.
The proposal covers a site area of 1,528m2 and is currently used as a storage business. It is proposed that the
development would consist of a single, two storey building with three separate industrial warehouse
tenancies. This footprint area is 707m2, there is a proposed hardstand driveway and carpark of 591m2 and the
remaining area (230m2) is to be landscaped.
This report has been developed to address the stormwater management in regards to a suitable discharge
from the property and both quality and quantity requirement. The plan is in response to the Noosa Council
information request (MCU21-0215) which requires the development to -
“Provide a preliminary Stormwater Management Plan for the site, including details of collection and discharge
of stormwater runoff from the buildings and the hardstand areas and any required stormwater
pipelines/flowpaths within the site to drain low areas on the adjoining properties to prevent stormwater
ponding”
The stormwater runoff for the proposed development site has been assessed using the Queensland Urban
Drainage Manual (QUDM) with Rational Method calculations to determine the potential stormwater flows on
the development.
Page 4 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 5
THE SITE AND ITS CONTEXT
LOCALITY
The site is described as lot 48 on RP173566 at 9 Bartlett Road in Noosaville, Queensland and is within the
Noosa Council local government boundary. The development is identified in Figure 1.
The property is bounded by Bartlett Street to the north, commercial lots in the west and east with residential
lots on Gumdale Court to the south.
Figure 1 - Locality Plan
Source: Queensland Globe
The site is currently being used for self-storage and is fully impervious with concrete hardstand and roof area
covering the entire property. There is an existing high point of approximately 19.0m AHD at the north-west
frontage in Bartlett Street with fall towards the southern rear boundary to an AHD of 18.0m. There is existing
stormwater infrastructure in this location which will be utilised as a lawful point of discharge. This 225mm dia.
stormwater pipe collects runoff from the adjacent property to the east and enters the stormwater network in
Page 5 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 6
Gumdale Court to the south. This stormwater system will be upgraded to a 300mm diameter pipe from the
connection to the existing pit located adjacent in 11 Bartlett Street. This will collect minor storm events and
roof water runoff while major events will be directed to the Bartlett Road frontage. Earthworks will be needed
to achieve these design levels to allow overland flow to reach the Bartlett Street frontage.
Based on the post-development impervious fraction the site was calculated to have a peak flow for a 1% AEP
design storm event as 0.054 m3/s.
Of this volume 0.033 m3/s is a minor storm event and would be directed to the existing pipe system. The
remaining volume of 0.021m3/s would be directed to the Bartlett Street frontage.
Figure 2 – Stormwater Network and Contour Plan
Source: Noosa Council Mapping
Page 6 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 7
STORMWATER QUANITY MANAGEMENT
DRAINAGE AND EXISTING TOPOGRAPHY
Lawful Point of Discharge
In general, the site is elevated at around 19.0m AHD in Bartlett Street and grades at approximately 2% towards
an existing low point at around RL 18.0m AHD in the south-west corner. There is an existing drainage pit in this
location which will be utilised as a lawful point of discharge for roofwater and carpark drainage. Due to the
proposed design of the building, overland flows from major events will be diverted to the Bartlett Road
frontage in the north. This will ensure any pipe blockages will not create flooding to the tenancies.
External Catchment and Overland Flows
In general, the site experiences no overland flow from any upper catchments.
Stormwater Infrastructure
The proposed stormwater system utilises a 225mm diameter pipes and will ultimately discharge to the existing
pipe system. Due to the calculated volume of the upstream catchment connected to this system (0.076m3/s)
it is proposed to upgrade a section of the existing network to a 300mm diameter. This should ensure that the
capacity of the system is not exceeded with the proposed connection of the new impervious area for the site
(0.033m3/s) is connected.
Of this volume 0.033 m3/s is a minor storm event and would be directed to the existing pipe system.
Overland flows from any major storm events will be directed to the Bartlett Street frontage. This calculated
volume is 0.054m3/s. Therefore the overland flow less the piped system would result in a volume of 0.021m3/s
discharging to the northern frontage.
In accordance with QUDM Table 7.3.5 and 7.3.6, road flows must be restricted for transverse flows to d.V
values of <0.3m2/s for minor flows and 0.6m2/s for major flows. These flows are also to be contained wholly
within the reserve
Flows were calculated at the outlet point using Izzard’s equation with the velocity calculated using the
Manning’s equation. The d.V value from the site based on post development conditions was less than 0.04
and therefore well under the allowable limit.
Page 7 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 8
It is noted that the proposed development has a reduced impervious area compared to the existing site. It is
also highlighted that no flows currently reach the Bartlett Street frontage (with all flows diverted to the pipe
network). It is expected that with an increased pipe capacity and a diversion of major flows from this system,
stormwater mitigation should be improved.
Flooding
Flood mapping courtesy of the Noosa Council (ARCGIS Web Map) indicates the site is not subject to flooding
from any sources.
The mapping demonstrates all defined flood extents limited to the parkland in the west.
Page 8 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 9
STORMWATER QUALITY MANAGEMENT
The proposed development is an industrial lot which includes, driveways and carparks. It is proposed that the
driveways and carparks will flow to a single catchment shown as 1/1 as show in Figure 3.
Figure 3 – Proposed catchment plan
CONSTRUCTION PHASE
The design milestones for water quality during the construction phase of the development will be in
accordance with Table A of the SPP Code: Water Quality. The design objectives will be achieved using approved
Sediment and Erosion Control measures.
General pollutants generated during construction are listed in Table 1 below.
Page 9 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 10
Pollutant Potential Source Priority
Litter Paper, construction packaging, food packaging, cement
High
bags, off cuts
Sediment Unprotected exposed soils and stockpiles during
High
earthworks and building works
Hydrocarbons Fuel and oil spills, leaks from construction equipment and
High
temporary car park areas
Toxic Materials Cement slurry, asphalt primer, solvents, cleaning agents,
Medium
wash waters (e.g., From tile works)
Alkaline Substances Cement slurry and wash waters High
Table 1 - General Construction Pollutants
Below are the characteristic treatment measures that will be implemented prior to any construction works.
Detailed Sediment and Erosion control measures and drawings are included as part of an operational works
application.
• Sensible site planning
• Stabilized site entry / exit point
• Minimization of site disturbance and duration of disturbance
• Implementation sediment control along the lower edge of the site
• Appropriate location and protection of stockpiles
• Early connection of roof water downpipes
• Compaction of backfilled trenches
• Revegetation and stabilization of the site
OPERATIONAL PHASE
The internal drainage system has been designed to include Stormwater Quality Improvement Devices which
is detailed in the plan shown in Appendix B.
SPEL Stormsacks
SPEL Stormsack filtration solutions are deployed directly in the stormwater system to capture contaminants
close to the surface for ease of maintenance. They are placed into the stormwater inlet and use the filtration
technology for stormwater treatment. This will assist in meeting the specific site water quality goals. SPEL
Stormsack filters are also easier and quicker to clean out because pollutants are trapped just under the grate.
Page 10 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 11
The maintenance of the SPEL Stormsacks shall be completed in accordance with Noosa Council standard and
manufacturers guidelines with final ownership of the basin being that of the property owner.
PROPOSED DEVELOPMENT
The proposed development will consist of a single two storey building that will consist of three separate
commercial tenancies. It is proposed that vehicle and pedestrian access will be from the Bartlett Road frontage
with carparking in the north of the property. Construction works will consist of bulk earthworks, carparking,
stormwater drainage and the installation of stormwater improvement devices. Internal water and sanitary
drainage for the building will also be provided under a separate plumbing approval as part of the building
development. These will be connected to the existing water and sewer main connections provided for the
property.
Where required, sediment and erosion control devices will also be installed during all stages of construction.
The proposed lot configuration and development are shown in Appendix A.
DRAINAGE AND EXISTING TOPOGRAPHY
In general, the site is elevated at around 19.0m AHD in Bartlett Street and grades at approximately 2% towards
an existing low point at around RL 18.0m AHD in the south-west corner. There is an existing drainage pit in this
location which will be utilised as a lawful point of discharge for roofwater and carpark drainage. Due to the
proposed design of the building, overland flows from major events will be diverted to the Bartlett Road
frontage in the north. This will ensure any pipe blockages will not create flooding to the tenancies.
Page 11 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 12
FLOODING
Flood mapping courtesy of the Noosa Council and provided in Appendix C indicates the site is not subject to
flooding from any sources.
The mapping demonstrates all defined major and extreme flood extents are limited to the Lake Entrance
Boulevarde in the south.
Based on the proposed maximum height of the driveway (9.0m AHD adjacent to vehicle crossover) and the
proposed floor levels (9.15m AHD) it is noted that any overland flows will leave the site before entering the
finished buildings.
Page 12 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 13
CONCLUSION
The report has reviewed the pre and post development scenario for the subject and external catchment
hydrology to ensure non-actionable nuisance of flows.
In summary, the development on the subject site will result in non-actionable nuisance of stormwater runoff
quantities with minor flows to outlet to the existing stormwater pipe network in the rear of the property. This
system will be upgraded to accept the proposed calculated flows.
Due to the proposed design of the building, overland flows from major events will be diverted to the Bartlett
Road frontage in the north. This will ensure any pipe blockages will not create flooding to the tenancies.
It is anticipated the report, when reviewed in conjunction with the planning report and the development plans;
will assist in supporting the application seeking development approval.
Yours Faithfully,
GLENN AINSWORTH
MIEAust CPEng NER RPEQ CPESC
BAX ENGINEERING PTY. LTD.
Ph: 0407 021 300
Page 13 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 14
REFERENCES
Proposed Building Design
Prepared by Sprout Architects (Document No: 21010) dated 04.11.21
Civil Design
Prepared by Bax Engineering (Document No: 124-003-001 to 802) dated 26.01.22
Healthy Waterways
Controlling stormwater pollution on your building site
DBYD – Service Locations
https://www.1100.com.au/
Queensland Globe – Site Mapping
https://qldglobe.information.qld.gov.au/
Queensland Urban Drainage Manual Fourth edition, 2016 (Institute of Public Works Engineering
Australasia, Queensland Division)
SPEL Stormwater Design
https://spel.com.au/stormsack/
Page 14 of 14
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
Page 15
APPENDIX A
Engineering Plans
Prepared by Bax Engineering dated February, 2022
[OCR of page images]
APPENDIX A
Engineering Plans
Prepared by Bax Engineering dated February, 2022
Page 16
INDUSTRIAL DEVELOPMENT
9 BARTLETT RD
BAX
Engineering PTY. LTD.
2261 DAVID LOW WAY, PEREGIAN BEACH, QLD 4573
NOOSAVILLE, QLD 4566 [email protected]
Operational Works Application
KLOBAS
NORTH POINT
DRAWING SCHEDULE
ET ST
SHEET TITLE
GENERAL
BARTLE
124-003-001 COVER SHEET
124-003-002 GENERAL NOTES
124-003-100 SITE LAYOUT PLAN
RENE ST 124-003-200 EARTHWORKS LAYOUT PLAN
124-003-201 EARTHWORKS SECTIONS
124-003-250 SEDIMENT & EROSION CONTROL PLAN
124-003-251 SEDIMENT AND EROSION DETAILS
124-003-300 GRADING & DRAINAGE LAYOUT PLAN
124-003-301 PAVEMENT LAYOUT PLAN
SITE LOCATION 124-003-302 SIGNAGE & LINEMARKING LAYOUT PLAN
STORMWATER
124-003-400 CATCHMENT LAYOUT PLAN
BARTLE
E T ST 124-003-401 DRAINAGE LONGITUDINAL SECTIONS
124-003-402 DRAINAGE CALCULATIONS TABLE
WATER RETICULATION
124-003-500 WATER RETICULATION GENERAL NOTES
124-003-501 WATER RETICULATION LAYOUT PLAN
124-003-502 WATER RETICULATION DETAIL PLAN
SEWER RETICULATION
124-003-600 SEWER RETICULATION GENERAL NOTES
124-003-601 SEWER RETICULATION LAYOUT PLAN
MISCELLANEOUS
124-003-700 CONCRETE & JOINTING DETAILS
VEHICLE SWEPT PATH
RENE ST
124-003-800 VEHICLE SWEPT PATH SHEET 1 OF 3
124-003-801 VEHICLE SWEPT PATH SHEET 2 OF 3
124-003-802 VEHICLE SWEPT PATH SHEET 3 OF 3
LOCALITY PLAN
PRO ECT DESCRIPTION
PROPERTY DESCRIPTION PROJECT NAME:
LOT:
48 9 BARTLETT RD NOOSAVILLE
PLAN: PROJECT NO:
RP173566 124-003
REVISION DATE:
LOCAL AUTHORITY:
26.01.22
NOOSA SHIRE COUNCIL
LOCAL AUTHORITY APPROVAL NO:
PLAN ISSUE:
MCU 21/0215
FOR APPROVAL
Page 17
GENERAL EARTHWORKS ROADWORKS SEDIMENT AND EROSION
STORMWATER
·
·
·
·
·
·
LINEMARKING
ENERGY SERVICE PROVIDERS TELECOMMUNICATIONS
SERVICE PROVIDERS elstra Manual of Uniform Traffic Control Devices
BEFORE YOU DIG SERVICE LOCATIONS AGL
ERGON. AUSTRALIA
IT IS THE RESPONSIBILITY OF THE PRINCIPAL
ENERGY
energex ' yes' Telstra visionstream
CONTRACTOR TO CONTACT ALL RELEVANT origin OPTUS WARNING: OPTIC FIBRE NOTE: ALL SIGNS & LINE MARKING TO BE IN
SERVICE AUTHORITIES TO VERIFY THE NOTE: SERVICE LOCATIONS ARE APPROXIMATE ONLY FROM NOTE: SERVICE LOCATIONS ARE APPROXIMATE ONLY FROM EXTREME CARE TO BE TAKEN WHILE EXCAVATING IN THE
LOCATION OF ALL EXISTING SERVICES PRIOR PROVIDERS PLANS. LOCATIONS ARE TO BE CONFIRMED PROVIDERS PLANS. LOCATIONS ARE TO BE CONFIRMED VICINITY OF OPTIC FIBRE CABLES. LOCATIONS ARE TO ACCORDANCE WITH THE MANUAL OF
PRIOR TO START OF CONSTRUCTION. PHONE DBYD PRIOR TO START OF CONSTRUCTION. PHONE DBYD
TO THE START OF CONSTRUCTION SERVICE LOCATIONS ON 1100 FOR DETAILS. SERVICE LOCATIONS ON 1100 FOR DETAILS.
BE CONFIRMED PRIOR TO START OF CONSTRUCTION. UNIFORM TRAFFIC CONTROL DEVICES.
BAX
SCALE: SURVEYED: CLIENT: NORTH POINT TITLE:
KLOBAS GENERAL NOTES
DATUM: Skyline Surveyors
PROJECT NO:
124-003
LOCAL AUTHORITY APPROVAL NO:
DATE
CHECKED
DRAWN
APPROVED:
GLENN AINSWORTH
CPESC No: 7678
RPEQ No: 19204
Engineering PTY. LTD.
PROJECT:
9 BARTLETT ROAD,
No. DATE REVISIONS BY CKD MCU 21/0215 DESIGNED FOR AND ON BEHALF OF BAX ENGINEERING PTY. LTD.
2261 DAVID LOW WAY, PEREGIAN BEACH, QLD 4573
[email protected] NOOSAVILLE, QLD 4566 PLAN No 124-003-002 REVISION A A1
Page 18
LEGEND:
EXISTING LAYOUT PROPOSED LAYOUT
BAX
SCALE: SURVEYED: CLIENT: NORTH POINT TITLE:
KLOBAS SITE LAYOUT PLAN
DATUM: Skyline Surveyors
PROJECT NO:
124-003
LOCAL AUTHORITY APPROVAL NO:
DATE
CHECKED
DRAWN
APPROVED:
GLENN AINSWORTH
CPESC No: 7678
RPEQ No: 19204
Engineering PTY. LTD.
PROJECT:
9 BARTLETT ROAD,
No. DATE REVISIONS BY CKD MCU 21/0215 DESIGNED FOR AND ON BEHALF OF BAX ENGINEERING PTY. LTD.
2261 DAVID LOW WAY, PEREGIAN BEACH, QLD 4573
[email protected] NOOSAVILLE, QLD 4566 PLAN No 124-003-100 REVISION A A1
Page 19
LEGEND:
BAX
SCALE: SURVEYED: CLIENT: NORTH POINT TITLE:
KLOBAS EARTHWORKS LAYOUT PLAN
DATUM: Skyline Surveyors
PROJECT NO:
124-003
LOCAL AUTHORITY APPROVAL NO:
DATE
CHECKED
DRAWN
APPROVED:
GLENN AINSWORTH
CPESC No: 7678
RPEQ No: 19204
Engineering PTY. LTD.
PROJECT:
9 BARTLETT ROAD,
No. DATE REVISIONS BY CKD MCU 21/0215 DESIGNED FOR AND ON BEHALF OF BAX ENGINEERING PTY. LTD.
2261 DAVID LOW WAY, PEREGIAN BEACH, QLD 4573
[email protected] NOOSAVILLE, QLD 4566 PLAN No 124-003-200 REVISION A A1
Page 20
BAX
SCALE: SURVEYED: CLIENT: NORTH POINT TITLE:
KLOBAS EARTHWORKS SECTIONS
DATUM: Skyline Surveyors
PROJECT NO:
124-003
LOCAL AUTHORITY APPROVAL NO:
DATE
CHECKED
DRAWN
APPROVED:
GLENN AINSWORTH
CPESC No: 7678
RPEQ No: 19204
Engineering PTY. LTD.
PROJECT:
9 BARTLETT ROAD,
No. DATE REVISIONS BY CKD MCU 21/0215 DESIGNED FOR AND ON BEHALF OF BAX ENGINEERING PTY. LTD.
2261 DAVID LOW WAY, PEREGIAN BEACH, QLD 4573
[email protected] NOOSAVILLE, QLD 4566 PLAN No 124-003-201 REVISION A A1
Page 21
NOTE:
LEGEND:
BAX
SCALE: SURVEYED: CLIENT: NORTH POINT TITLE:
KLOBAS SEDIMENT & EROSION CONTROL PLAN
DATUM: Skyline Surveyors
PROJECT NO:
124-003
LOCAL AUTHORITY APPROVAL NO:
DATE
CHECKED
DRAWN
APPROVED:
GLENN AINSWORTH
CPESC No: 7678
RPEQ No: 19204
Engineering PTY. LTD.
PROJECT:
9 BARTLETT ROAD,
No. DATE REVISIONS BY CKD MCU 21/0215 DESIGNED FOR AND ON BEHALF OF BAX ENGINEERING PTY. LTD.
2261 DAVID LOW WAY, PEREGIAN BEACH, QLD 4573
[email protected] NOOSAVILLE, QLD 4566 PLAN No 124-003-250 REVISION A A1
Page 22
STABILISED SITE ACCESS
SEDIMENT FENCE
BARRIER FENCE
BAX
SCALE: SURVEYED: CLIENT: NORTH POINT TITLE:
KLOBAS SEDIMENT AND EROSION DETAILS
DATUM: Skyline Surveyors
PROJECT NO:
124-003
LOCAL AUTHORITY APPROVAL NO:
DATE
CHECKED
DRAWN
APPROVED:
GLENN AINSWORTH
CPESC No: 7678
RPEQ No: 19204
Engineering PTY. LTD.
PROJECT:
9 BARTLETT ROAD,
No. DATE REVISIONS BY CKD MCU 21/0215 DESIGNED FOR AND ON BEHALF OF BAX ENGINEERING PTY. LTD.
2261 DAVID LOW WAY, PEREGIAN BEACH, QLD 4573
[email protected] NOOSAVILLE, QLD 4566 PLAN No 124-003-251 REVISION A A1
Page 23
LEGEND:
BAX
SCALE: SURVEYED: CLIENT: NORTH POINT TITLE:
KLOBAS GRADING & DRAINAGE LAYOUT PLAN
DATUM: Skyline Surveyors
PROJECT NO:
124-003
LOCAL AUTHORITY APPROVAL NO:
DATE
CHECKED
DRAWN
APPROVED:
GLENN AINSWORTH
CPESC No: 7678
RPEQ No: 19204
Engineering PTY. LTD.
PROJECT:
9 BARTLETT ROAD,
No. DATE REVISIONS BY CKD MCU 21/0215 DESIGNED FOR AND ON BEHALF OF BAX ENGINEERING PTY. LTD.
2261 DAVID LOW WAY, PEREGIAN BEACH, QLD 4573
[email protected] NOOSAVILLE, QLD 4566 PLAN No 124-003-300 REVISION A A1
Page 24
BAX
SCALE: SURVEYED: CLIENT: NORTH POINT TITLE:
KLOBAS CATCHMENT LAYOUT PLAN
DATUM: Skyline Surveyors
PROJECT NO:
124-003
LOCAL AUTHORITY APPROVAL NO:
DATE
CHECKED
DRAWN
APPROVED:
GLENN AINSWORTH
CPESC No: 7678
RPEQ No: 19204
Engineering PTY. LTD.
PROJECT:
9 BARTLETT ROAD,
No. DATE REVISIONS BY CKD MCU 21/0215 DESIGNED FOR AND ON BEHALF OF BAX ENGINEERING PTY. LTD.
2261 DAVID LOW WAY, PEREGIAN BEACH, QLD 4573
[email protected] NOOSAVILLE, QLD 4566 PLAN No 124-003-400 REVISION A A1
Page 25
BAX
SCALE: SURVEYED: CLIENT: NORTH POINT TITLE:
KLOBAS DRAINAGE LONGITUDINAL SECTIONS
DATUM: Skyline Surveyors
PROJECT NO:
124-003
LOCAL AUTHORITY APPROVAL NO:
DATE
CHECKED
DRAWN
APPROVED:
GLENN AINSWORTH
CPESC No: 7678
RPEQ No: 19204
Engineering PTY. LTD.
PROJECT:
9 BARTLETT ROAD,
No. DATE REVISIONS BY CKD MCU 21/0215 DESIGNED FOR AND ON BEHALF OF BAX ENGINEERING PTY. LTD.
2261 DAVID LOW WAY, PEREGIAN BEACH, QLD 4573
[email protected] NOOSAVILLE, QLD 4566 PLAN No 124-003-401 REVISION A A1
Page 26
BAX
SCALE: SURVEYED: CLIENT: NORTH POINT TITLE:
KLOBAS DRAINAGE CALCULATIONS TABLE
DATUM: Skyline Surveyors
PROJECT NO:
124-003
LOCAL AUTHORITY APPROVAL NO:
DATE
CHECKED
DRAWN
APPROVED:
GLENN AINSWORTH
CPESC No: 7678
RPEQ No: 19204
Engineering PTY. LTD.
PROJECT:
9 BARTLETT ROAD,
No. DATE REVISIONS BY CKD MCU 21/0215 DESIGNED FOR AND ON BEHALF OF BAX ENGINEERING PTY. LTD.
2261 DAVID LOW WAY, PEREGIAN BEACH, QLD 4573
[email protected] NOOSAVILLE, QLD 4566 PLAN No 124-003-402 REVISION A A1
Page 27
APPENDIX B Water Quality Device SPEL Stormwater Design [OCR of page images] APPENDIX B Water Quality Device SPEL Stormwater Design
Page 28
SPEL Stormsack®
At Source Gross Pollutant Trap (GPT)
OVERVIEW
The SPEL StormSack®
is specifically designed
for the capture of
gross pollutants:
sediment, litter, and
oil and grease. Ideally
suited for municipal
storm drain retrofits,
the SPEL StormSack’s
unique design allows
maintenance to be
performed using
conventional vacuum
suction equipment.
BENEFITS
• Quick and easy installation.
• Cost efficient gross pollutant
capture.
• Adjusts to custom pit sizes.
• Can be modelled in MUSIC in
conjunction with bio-retention.
• Adjusts to custom pit sizes.
APPLICATIONS
Council Storm Drain Retrofits
Commercial/Retail/Residential
Litter Prone Urban Areas
Scrap Metal/Solid Waste/Oil
Storage/Etc
Part of Treatment Train
Construction Sediment
<200 micron capture
www.spel.com.au
Page 29
SPEL Stormsack®
At Source Gross Pollutant Trap (GPT)
Sizes
Dimensions (mm)*
450x450
600x600
600x900
900x900
Custom sizes (i.e. 1200x900mm) can be
manufactured on short lead times.
Application Regulatory Issue Target Pollutants
Council Storm Drain Retrofits At-source litter capture Sediment, Litter, O&G
Commercial/Retail/Residential Stormwater Compliance Sediment, Litter, O&G
Litter Prone Urban Areas Cost effective litter control Litter ≥ 5 mm
Scrap Metal/Solid Waste/ Industrial Multi-Sector
Gross Pollutants, O&G
Oil Storage/Etc General Permit
Council Stormwater Quality
Part of Treatment Train Sediment, Litter, O&G
Improvement Targets
Construction Sediment/Erosion Sediment Control Plan Sediment/Erosion Control
Features
1. Ultra-Durable Aluminium Frame
• Custom pit arrangements upon request
2. Black Poly Surround riveted to Frame
• Can be cut to suit on site
3. Reinforced Stormsack Bag
• Bag has sewed eyelets
• Square bottom design for even distribution
4. Karabiners attach Bag to Frame for easy
service & replacement
SPEL Stormwater accepts no responsibility for any loss or damage resulting from any person acting on this information. The details and
dimensions contained in this document may change, please check with SPEL Stormwater for confirmation of current specifications. www.spel.com.au
Page 30
APPENDIX C Flood Mapping Noosa Council Mapping [OCR of page images] APPENDIX C Flood Mapping Noosa Council Mapping
Page 31
Noosa Shire Council does not warrant the accuracy of information in this publication and 14/12/2021 any person using or relying upon such information does so on the basis that Noosa Shire Council shall bear no responsibility or liability whatsoever for any errors, faults, 1:4500 defects or omissions in the information.