                       AGENDA


            Ordinary Meeting

           Thursday, 21 January 2021

                    commencing at 5pm
           Council Chambers, 9 Pelican Street, Tewantin




Crs Clare Stewart (Chair), Karen Finzel, Joe Jurisevic, Amelia Lorentson,
Brian Stockwell, Tom Wegener, Frank Wilkie



                    “Noosa Shire – different by nature”
Log in to download the original file

2021-01-21 Ordinary Meeting Agenda(PDF, 2MB).pdf · 2.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 25 sections

Section 2

ORDINARY MEETING AGENDA                                       21 JANUARY 2021


TABLE OF CONTENTS

ITEM                                                                        PAGE

       1    ATTENDANCE & APOLOGIES                                              3

       2    CONFIRMATION OF MINUTES                                             3

       3    MAYORAL MINUTES                                                     3

       4    PETITIONS                                                           3

       5    NOTIFIED MOTIONS                                                    3

       6    PRESENTATIONS                                                       3

       7    DEPUTATIONS                                                         3

       8    CONSIDERATION OF COMMITTEE REPORTS                                  4

            1    GENERAL COMMITTEE MEETING REPORT – 18 JANUARY 2021             4

       9    ORDINARY MEETING REPORTS                                           11

            1.   T000018 PEREGIAN BEACH COMMUNITY HOUSE AND GREENSPACE
                 CONTRACT AWARD                                                11

       10   CLOSED SESSION                                               26

       11   PUBLIC QUESTION TIME                                               26

       12   NEXT MEETING                                                       26

       13   MEETING CLOSURE                                                    26




                                                                      Page 2 of 26

Section 3

ORDINARY MEETING AGENDA                                                  21 JANUARY 2021



1   ATTENDANCE & APOLOGIES




2   CONFIRMATION OF MINUTES

    The Minutes of the Ordinary Meeting held on 17 December 2020 be received and confirmed.




3   MAYORAL MINUTES




4   PETITIONS




5   NOTIFIED MOTIONS

    Nil.




6   PRESENTATIONS

    Nil.




7   DEPUTATIONS

    Nil.




                                                                               Page 3 of 26

Section 4

ORDINARY MEETING AGENDA                                                                21 JANUARY 2021


8   CONSIDERATION OF COMMITTEE REPORTS


1   GENERAL COMMITTEE MEETING REPORT – 18 JANUARY 2021

    ATTENDANCE & APOLOGIES

    COUNCILLORS
    Cr Frank Wilkie (Chair)
    Cr Karen Finzel
    Cr Joe Jurisevic
    Cr Amelia Lorentson
    Cr Clare Stewart
    Cr Brian Stockwell
    Cr Tom Wegener

    EXECUTIVE
    B de Chastel, Chief Executive Officer
    A Dow, Acting Director Environment and Sustainable Development (for reports 1-6 and 11)
    M Shave, Director Corporate Services (for report 9)
    B O’Connor, Acting Director Infrastructure Services (for report 7)
    K Contini, Director Community Services (for report 8)


    COMMITTEE RECOMMENDATIONS TO COUNCIL

    1    NOOSA BIOSPHERE RESERVE FOUNDATION 2019 20 ANNUAL REPORT
         That Council note the report by the Environmental Services Manager to the General
         Committee Meeting dated 18 January 2021 and note the 2019/20 Annual Report and
         audited Financial Statement received from the Noosa Biosphere Reserve Foundation as
         provided at Attachments 1 and 2.

    2    NOOSA RIVER PLAN CONSULTATION & NOOSA RIVER STAKEHOLDER
         ADVISORY GROUP
         That Council note the report by the Environment Services Manager and Environment
         Officer (Rivers and Coast) to the General Committee Meeting dated 18 January 2021
         and defer consideration of the matter to the Ordinary Meeting dated 21 January 2021 to
         enable Councillors to have further consideration of the Draft Terms of Reference.

    3    DRAFT COASTAL HAZARDS ADAPTATION PLAN (CHAP) FOR COMMUNITY
         CONSULTATION
         In accordance with Chapter 5B of the Local Government Act 2009, Cr Lorentson provided the
         following declaration to the meeting of a prescribed conflict of interest in this matter:
         I, Cr Lorentson, inform the meeting that I have a prescribed conflict of interest in this matter as
         my brother, Gabriel Cerasani, owns a property at Beaches Estate, Sunrise Beach which is one of
         the properties identified as `at risk' under the CHAP. As a result of my conflict of interest, I will
         now leave the meeting room while the matter is considered and voted on.
         In accordance with Chapter 5B of the Local Government Act 2009, Cr Stockwell provided the
         following declaration to the meeting of a prescribed conflict of interest in this matter:
         I, Cr Stockwell, inform the meeting that I have a prescribed conflict of interest in this matter as I
         am the owner of Lot 45 Noosa Lakes resort at 3 Hilton Terrace, Tewantin. The draft Coastal
         Hazards Adaptation Plan identifies that, "riverine areas including Noosaville and Tewantin will be

                                                                                              Page 4 of 26

Section 5

ORDINARY MEETING AGENDA                                                              21 JANUARY 2021


        most affected by periodic storm tide inundation and permanent sea level rise." p.7 and further the
        property is mapped in Figure 5 which relates to the potential inundation resulting from sea levels
        rise. In particular the plan suggests, "low lying areas will be exposed to more frequent inundation
        under everyday conditions and also with storm tides" p.15. At best this means that access to the
        property will be more frequently inundated and actions and investigations are envisaged to adapt
        to this increased risk from climate change. As such I stand to benefit more from the
        recommendations in the draft plan than the majority of residents in the Shire. As a result of my
        conflict of interest, I will now leave the meeting room while the matter is considered and voted on.
        That Council note the report by the Principal Strategic Planner and Program Coordinator
        Climate Change Adaptation to the General Committee Meeting dated 18 January 2021
        and
        A.    Approve the draft Coastal Hazards Adaptation Plan and supporting information for
              the purpose of community consultation, as provided in Attachments 1 - 4;
        B.    Approve the Community Engagement and Communications Plan, as provided in
              Attachment 5; and
        C.    Note that updates have been made to the coastal hazard mapping of erosion for
              beachfront areas between Peregian Beach and Sunshine Beach and that this
              updated mapping has been made available to the public through Council’s online
              mapping via Council’s website.

    4   MCU20/0097 APPLICATION FOR A DEVELOPMENT PERMIT FOR MATERIAL
        CHANGE OF USE FOR SHORT TERM ACCOMMODATION AT 1/27 HILL STREET,
        SUNSHINE BEACH
        That Council note the report by the Coordinator Planning to the General Committee
        Meeting dated 18 January 2021 regarding Application No. MCU20/0097 for a
        Development Permit for Material Change of Use - Short-term accommodation situated
        at 1/27 Hill St, Sunshine Beach and:
        A.    Approve the application in accordance with the following conditions:
              PLANNING
              When Conditions must be Complied With
              1.     Unless otherwise stated, all conditions of this Decision Notice must be
                     complied with prior to the use commencing, and then compliance maintained
                     at all times while the use continues.
              Approved Plans
              2.     Development undertaken in accordance with this approval must generally
                     comply with the approved plans of development. The approved plans are
                     listed in the following table unless otherwise amended by these conditions.

              Plan No.       Rev.    Plan/Document Name                                  Date
              18-076 - 04    4       Proposed Ground Floor Plan prepared by ICON         03.05.2019
                                     Building Design as annotated by Council
              18-076 - 05    4       Proposed First Floor Plan prepared by ICON          03.05.2019
                                     Building Design as annotated by Council
              18-076 - 06    4       Elevations prepared by ICON Building Design         03.05.2019
                                     as annotated by Council
              18-076 - 07    4       Elevations prepared by ICON Building Design         03.05.2019
                                     as annotated by Council
              Currency
              3.     This development approval lapses if the use has not happened by 21

                                                                                            Page 5 of 26

Section 6

ORDINARY MEETING AGENDA                                                      21 JANUARY 2021


                  January 2027, unless an application to extend the currency period is
                  approved by Council.
            Nature and Extent of Approved Use
            4.    The total number of bedrooms on the site must not exceed 2.
            5.    No more than 4 guests may occupy the premises at any time.
            6.    All outdoor areas, including balconies, decks, pool and the like, must not be
                  used after 10pm each night except that in relation to the pool, it must not be
                  used after 9pm each night.
            7.    The premises must not be used as a party house, with no events, functions
                  or parties (e.g. bucks parties, hen’s parties, raves, or wedding receptions for
                  example) permitted on site.
            Amenity
            8.    The operation of the approved use must not detrimentally affect the
                  residential amenity (including but not limited to noise, overlooking, light spill
                  or odour) enjoyed by surrounding residents or cause a nuisance, including a
                  noise nuisance.
            Car Parking
            9.    Existing car parking on site, as detailed on the approved plans, must be
                  maintained and kept available for users of the short term accommodation.
            10.   All car parking areas and access driveways must be maintained exclusively
                  for vehicle parking and manoeuvring and kept in a tidy and safe condition at
                  all times.
            Waste Management
            11.   Waste storage and disposal facilities must be provided in accordance with
                  Planning Scheme Policy 9, Waste Management, including an external
                  imperviously paved area correctly sized for all refuse and recycling
                  containers and suitably screened from public places and neighbouring
                  properties.
            12.   Waste containers must:
                  a.    At all times be regularly cleaned and maintained in a clean, tidy,
                        sanitary and hygienic condition.
                  b.    Be placed on the kerb side frontage of the premises, for the collection
                        of general waste from the container; and
                  c.    Not be placed on the kerb side frontage for longer than 24 hours before
                        or after the scheduled collection day for the collection of waste in the
                        container.
            Contact Person
            13.   Prior to the commencement of the use written confirmation must be provided
                  to Council confirming:
                  a.    the name and telephone number of the contact person (which may
                        include the name and contact details of an individual, letting agency,
                        property manager, security firm or the like) for the purposes of the
                        operation of the short stay letting at the premises; and
                  b.    that the contact person is available 24 hours a day, 7 days a week; and
                  c.    that the contact person resides within 20 minutes travel time (by
                        vehicle) of the premises; and

                                                                                    Page 6 of 26

Section 7

ORDINARY MEETING AGENDA                                                   21 JANUARY 2021


                  d.   that the contact person is to be responsible for the supervision and
                       management of the premises, including addressing complaints about
                       the use of the premises for short stay letting and visitor queries.
            14.   A sign must prominently and permanently display in letters and numbers not
                  less than 50mm in height, a current up to date written notice detailing the
                  contact person’s phone number, and a statement that the contact person is
                  responsible for the supervision and maintenance of the premises. The sign
                  must not exceed 0.2m2, be displayed at the front of the premises and be
                  visible to members of the public at all times.
                  Code of Conduct
            15.   A code of conduct must be developed and provided to all users and
                  occupants of the short term accommodation, including any website or social
                  media used to promote the use of the premises for short term
                  accommodation.
            16.   The code of conduct must advise all users of the premises:
                  a.   That the use of the premises must not:
                       i.     detrimentally affect the residential amenity (including but not
                              limited to noise, overlooking, light spill or odour) enjoyed by
                              residents in the vicinity of the premises; or
                       ii.    cause a nuisance (including a noise nuisance);
                       iii.   display unacceptable behavior including:
                              a.   loud aggressive behaviour;
                              b.   yelling, screaming, arguing; or
                              c.   excessively loud cheering, clapping and singing.
                       iv.    create a level of noise above the acceptable levels described by
                              Queensland Government legislation for environmental protection
                              (noise).
                  b.   That a user of the premises must not sleep or camp on the premises in
                       a tent, caravan, campervan or similar facility.
                  c.   That each vehicle used by an user of the premises must:
                       i.     be stored in a manner that does not cause a nuisance or
                              inconvenience to adjoining premises; and
                       ii.    be parked within the parking facilities at the premises where
                              provided.
                  d.   That each user of the premises must store general waste (including the
                       separation of recyclable waste) produced as a result of the ordinary
                       use or occupation of the premises in a waste container.
                  e.   That each user of the premises must ensure that the premises,
                       including the grounds of the premises, are kept in a safe and tidy
                       condition.
                  f.   That pets occupying the premises must be managed and not cause a
                       nuisance (including a noise nuisance).
                  g.   The nature and extent of the approved use as detailed in conditions
                       numbers 4 to 7 of this development approval.
            17.   The Code of Conduct must be displayed in a prominent location at the
                  premises so that it can be viewed by guests.

                                                                                 Page 7 of 26

Section 8

ORDINARY MEETING AGENDA                                                    21 JANUARY 2021


                   Complaints Management
             18.   The contact person must maintain a record of all complaints received,
                   identifying how each complaint has been resolved or addressed within a
                   reasonable time.
             19.   The contact person must respond to all complaints within 30 minutes of
                   notification of a complaint.
             20.   The contact person, must keep and maintain a register of the use of the
                   premises for short stay letting or home hosted accommodation, and record
                   in the register, each of the following:
                   a.   on each occasion on which the premises are used, or occupied, for
                        short stay letting or home hosted accommodation on a commercial
                        basis:
                        i.    the number of adults who are users of the premises; and
                        ii.   the number of minors, an individual who is under 18, who are
                              users of the premises.
                   b.   the dates when each person’s use, or occupation, of the premises for
                        short stay letting or home hosted accommodation began and ended.
             21.   The contact person, must make available, for inspection by Council, within 5
                   business days of receipt of a written request given at any time, each of:
                   i.   the written record of complaints referred to in condition 18; and
                   ii.  the register referred to in condition 20
        B.   Note the report is provided in accordance with Section 63(5) of the Planning Act
             2016.
        C.   Include the following advisory note on the Decision Notice:
             1.    It is the responsibility of the owner and the identified contact person to
                   operate the short term accommodation in compliance with the development
                   approval conditions at all times. Should the development approval conditions
                   not be met Council may issue an Infringement and/or take action under the
                   Planning Act 2016 to enforce compliance.



    5   MCU20/0111 DEVELOPMENT APPLICATION FOR EXTENSION TO FOOD & DRINK
        OUTLET & SHOP AT 2 PARKYN CT, TEWANTIN
        That Council note the report by the Manager Development Assessment to the General
        Committee Meeting dated 18 January 2021 regarding Application No. MCU20/0111 for
        a Development Permit for Material Change of Use – Extension to Food & Drink Outlet
        and Shop situated at 2 Parkyn Ct Tewantin and:
        A.   Approve the application in accordance with the following conditions:
             When Conditions must be Complied With
             1.    Unless otherwise stated, all conditions of this Decision Notice must be
                   complied with prior to the use commencing, and then compliance maintained
                   at all times while the use continues.
             Approved Plans
             2.    Development undertaken in accordance with this approval must generally
                   comply with the approved plans of development. The approved plans are
                   listed in the following table unless otherwise amended by these conditions.


                                                                                    Page 8 of 26

Section 9

ORDINARY MEETING AGENDA                                                                21 JANUARY 2021


                     Plan No.          Rev.       Plan/Document Name                            Date
                     2260-A01          B          Existing and Proposed Site Layouts            3/06/20
                     2260-A02          B          Floor & Roof Demolition Layouts               3/06/20
                     2260-A03          B          Proposed Floor & Roof Layouts                 3/06/20
                     2260-A04          B          Elevations                                    3/06/20
                     2260-A05          B          Sections A-A & B-B                            3/06/20
                     2260-A01          B          Existing and Proposed Site Layouts            3/06/20
                     2260-A01          A          Existing and Proposed Site Layouts            29/10/20
                     2260-A02          A          Demolition Plan & Proposed Roof Plan          29/10/20
                     2260-A03          A          Sections A-A & Roof Detail                    29/10/20
              3.     The existing car parking spaces must be maintained on site and made
                     available and accessible at all times.
              4.     All landscaping works must be maintained in accordance with an approved
                     design for the life of the development, and in a manner that ensures, healthy,
                     sustained and vigorous plant growth. All plant material must be allowed to
                     grow to full form and be refurbished its life expectancy is reached.
                     Currency Period
              5.     This development approval lapses if the use has not happened by 21
                     January 2027, unless an application to extend the currency period is
                     approved by Council.
        B.    Find the following matters relevant to the assessment and sufficient reason to
              approve the application:
              1.     The proposal will not result in any increase in scale and intensity of
                     commercial operations on the Noosa River.
              2.     The proposal remains consistent with the intent for the site to operate as a
                     marina with ancillary type business uses and food and drink outlets.
        C.    Note the report is provided in accordance with Section 63(5) of the Planning Act
              2016.

    6   PLANNING APPLICATIONS DECIDED BY DELEGATED AUTHORITY
        That Council note the report by the Development Assessment Manger to the General
        Committee Meeting dated 18 January 2021 regarding planning applications that have
        been decided by delegated authority.

    7   PATHWAYS AND BOARDWALKS ASSET MANAGEMENT PLAN
        That Council note the report by the Acting Director Infrastructure Services to the General
        Committee Meeting dated 18 January 2021 and approve the Pathways and Boardwalks
        Asset Management Plan (provided as Attachment 1 to the report) as a document that
        specifies the activities, resources and asset classes to achieve Noosa Council’s asset
        management objectives.

    8   REGIONAL ARTS DEVELOPMENT FUND (RADF) - GRANT RECOMMENDATIONS
        2020-21
        In accordance with Chapter 5B of the Local Government Act 2009, Cr Wilkie provided the
        following declaration to the meeting of a declarable conflict of interest in this matter:
        I, Cr Wilkie inform the meeting that I have a declarable conflict of interest in this matter as grant
        applicant Tania Nash is a personal friend. As a result of my conflict of interest I will now leave the
        meeting room while the matter is considered and voted on.
        In accordance with Chapter 5B of the Local Government Act 2009, Cr Jurisevic provided the
        following declaration to the meeting of a declarable conflict of interest in this matter:


                                                                                              Page 9 of 26

Section 10

ORDINARY MEETING AGENDA                                                                 21 JANUARY 2021


         I, Cr Jurisevic inform the meeting that I have a declarable conflict of interest in this matter as I
         have performed as an amateur in theatre productions in the region produced by Jally Productions
         who are a grant applicant. Although I have a declarable conflict of interest, I do not believe a
         reasonable person could have a perception of bias because I believe I do not stand to receive a
         personal benefit or loss in relation to this matter. Therefore, I will choose to remain in the meeting
         room. However, I will respect the decision of the meeting on whether I can remain and participate
         in the decision.
         That Council note the report by the Community Development Manager to the General
         Committee Meeting dated 18 January 2021 and approve the Regional Arts Development
         Fund recommendations for 2020/21 as outlined in Attachment 1 to the report.

    9    FINANCIAL PERFORMANCE REPORT - DECEMBER 2020
         That Council note the report by the Manager Financial Services to the General
         Committee Meeting dated 18 January 2021 outlining December 2020 year to date
         financial performance against budget, including performance against key financial
         sustainability indicators.

    10   APPOINTMENT OF EXTERNAL MEMBER TO COUNCILS AUDIT AND RISK
         COMMITTEE
         That Council note the report by the Chief Executive Officer to the General Committee
         Meeting dated 18 January 2021 in relation to the vacancy for an external member on
         Council’s Audit and Risk Committee and:
         A.    Thank Scott Williams for his outstanding contribution to the Audit and Risk
               Committee in his capacity as the Chairperson of that committee for the past 6 ½
               years;
         B.    Appoint Tim Cronin as the external Chairperson of the Audit and Risk Committee
               for a term of 3 years; and
         C.    Appoint Kerry Phillips as an external member of the Audit and Risk Committee for
               a term of 2 years.

    11   ENVIRONMENT LEVY PROPOSED
         LAND PURCHASE
         That Council note the report by the Principal Environment Officer to the General
         Committee Meeting dated 18 January 2021 and:
         A.    Authorise the CEO to enter into a contract of sale with the owner of the two lots
               detailed in the report for a price not exceeding the amount set out in the valuation
               report with the funding for that purchase to be funded from the Environment Levy;
               and
         B.    Remove the confidentiality in relation to this report upon the signing of a contract
               to purchase.



Committee Recommendation

That the report of the General Committee dated 18 January 2020 be received and the
recommendations therein be adopted except where dealt with by separate resolution.




                                                                                              Page 10 of 26

Section 11

ORDINARY MEETING AGENDA                                                       21 JANUARY 2021


9   ORDINARY MEETING REPORTS

    1.   T000018 PEREGIAN            BEACH     COMMUNITY       HOUSE      AND     GREENSPACE
         CONTRACT AWARD

    Author:    Director Community Services, Kerri Contini

    Index      ECM/ 46.02 - Council Owned Buildings / Properties
                   ECM/ Project and Contract/ T000018

    Attachments       1.    Design images
                      2.    T000018 Evaluation Workbook


    EXECUTIVE SUMMARY
    This report provides a recommendation for the tender award to the preferred contractor for the
    construction of the Peregian Beach community house, carpark and greenspace works.

    RECOMMENDATION
    That Council note the report by the Director Community Services to the Ordinary Meeting dated
    21 January 2021 and award tender T000018 – for the construction of the Peregian Beach
    Community House and Greenspace to Kane Constructions (Qld) Pty Ltd.

    REPORT
    1.   Background
    Between August and October 2018, Council received a combined $2.7 million of grant funding
    from the Federal Government under the ‘Building Better Regions’ and the State Government
    under the ‘Maturing the Infrastructure Pipeline Program’ to construct the third stage of the
    Rufous Street Masterplan, which includes the two major elements of the new Peregian Beach
    Community House and repurposing the existing community house to expand the Digital Hub.
    To date the redevelopment of the Rufous Street precinct has consisted of the following stages:

     Stage    Description                      Year       Status                            Cost
     1        Land purchase and site           2014-15    Completed                         $1M
              preparations
     2        Masterplan for the Rufous St     2016-18    Completed                         $4M
              precinct, design and
              construction of Rufous Street,
              Digital Hub and car parking
     3        Planning, Design and             2019-22     Community House &             $5.2M
              construction of New community                 Greenspace -
              house, Digital Hub expansion,                 Procurement (This report)
              additional car parking and                   Digital Hub expansion -
              greenspace                                    Design phase.
                                                           Carpark - completed
     Total                                                                               $10.2M

    Once all of Stage 3 is constructed, a total $10.2M of Council, State and Federal Government
    funding will have been invested into the Rufous Street precinct.
    Council previously tendered the project as a design and construct project as “RUFOUS
    STREET COMMUNITY HOUSE (STAGE 3) AND CAR PARK, CONTRACT NO. 1819T084”

                                                                                    Page 11 of 26

Section 12

ORDINARY MEETING AGENDA                                                     21 JANUARY 2021


    and following Council’s Ordinary Meeting dated 17 October 2019, executed the contract with
    Peregian based contractor Ri-con Contractors on 28 October 2019.
    On 20 January 2020, Council was advised without prior notice that Ri-con Contractors had
    gone into liquidation. At this point the carpark was complete and the community house design
    had commenced but was not complete. To enable the project to proceed, Council procured
    the necessary design services to complete the designs and specifications and prepared a
    traditional construct only tender.
    2.   Design
    The design of Stage 3 is generally in accordance with the Rufous Street Masterplan, Material
    Change of Use (MCU) approval MCU16/0044.01 and REC16/0009 and prepared in
    consultation with the Peregian Beach Community House committee and Rufous Street Project
    Control Group.
    Specifically, the new community house design was developed to provide enduring, adaptable
    and complementary community facilities that are suitable to the Peregian Beach location,
    minimise energy use, and be in keeping with the Noosa Design Principles.
    The community house scope includes:
        130m2 Hall
        40m2 Hire room
        35m2 Meeting room
        Office & reception
        Under croft carpark – 23 spaces
        Rooms for hire
        Kitchen
        Storerooms
        Lift access
        Landscaping
    The Greenspace scope includes:
        4000m2 of sculptured gardens
        Playground
        Footpaths
        Turfed areas
    Refer Attachment 1 – Design images.
    3.   Tender process
    Council prepared and called for public tenders in accordance with the Local Government Act
    2009. Tender T000018 was released via Vendor Panel on 19 August 2020, and also advertised
    in Noosa Today on 21 August 2020 and online with Noosa News from 20 August 2020. The
    tender closed on 22 September 2020 with four compliant submissions received.
    4.   Tender Assessment
    The tender evaluation panel undertook an assessment of the following conforming tender
    submissions, which are listed in alphabetical order:
         Kane Construction (QLD) Pty Ltd
         Midson Constructions (QLD) Pty Ltd
         Murphy Builders Qld Pty Ltd
         WAC & Co Pty Ltd

    Two additional submissions were received and assessed as non-conforming and were not
    considered.
    The conforming tenderers were evaluated using the following criteria and weightings:


                                                                                  Page 12 of 26

Section 13

ORDINARY MEETING AGENDA                                                      21 JANUARY 2021


     PART A – Non price elements                                          Weightings
     Financial Capability and Resourcing                                      20%
     Contract Experience and Capacity                                         10%
     Methodology                                                              5%
     Quality                                                                  5%
     Workplace Health and Safety                                              5%
     Environment and Sustainability                                           5%
     Contribution to Local Economy                                            10%
     PART B – Price element                                               Weightings
     Price                                                                    40%

    Note. Attachment 2 presents the evaluation outcome of the conforming submissions against
    the above criteria.
    The Tender evaluation panel completed the evaluation process and consider Kane
    Constructions (Qld) Pty Ltd to be the most advantageous to Council, presenting the best value
    for money.
    Kane Construction (Qld) tender submission is most favourable based on their tender
    demonstrating the following:
       Full compliance with the tender requirements
       Highest level of financial capability
       A highly detailed methodology and programme identifying a thorough understanding of
        the project
       Highest level of experience delivering projects of a similar nature
       The necessary resources and processes in place to deliver the project within the
        specified timeframe
       Certified Quality System
       Certified Workplace Health and Safety systems
       Economic benefits through strong local content
       They scored highest for non-price criteria and scored highest on combined non-price and
        price criteria
    Refer Attachment 2 – T000018 Tender Evaluation Summary

    5.       Programme
    The insolvency of Ri-con Contractors resulted in an estimated 12-month delay to the project.
    The Community House building and Greenscape works are now forecast to be completed by
    5 October 2021 subject to weather and other unforeseen delays.
    Council has communicated the programme impacts with the Building Better Regions Funding
    body who have acknowledged the impact and provided a revised Stage 3 project completion
    date of 30 June 2022. The revised overall completion date is to include the Community House,
    Greenspace and the Digital Hub expansion which is not included in this contract award scope.

    Previous Council Consideration
    Ordinary Meeting, 17 October 2019, Item 4, Page 8
    That Council note the report by the Director Community Services to the Services &
    Organisation Committee Meeting dated 8 October 2019 and award the tender 1819T084 – for
    the Design and Construction of Rufous Street Community House (Stage 3) and Car Park to
    Ri-con Contractors Pty Ltd.


                                                                                    Page 13 of 26

Section 14

ORDINARY MEETING AGENDA                                                           21 JANUARY 2021


    Finance
    a.      Capital costs

    The below table identifies the estimated project capital costs of the Rufous St Stage 3 project
    and details the community house and greenspace tendered elements.

    Table 1. Rufous Street Stage 3 Capital Costs
         Project Element                                                Cost
         Planning                                                              $265,482
         Design                                                                $373,821
         Approvals                                                              $25,150
         Procurement                                                            $59,827
         Construction
              Water Main                                                      $116,373
              Carpark                                                         $394,861
              Community House and Greenspace
              Ri-con Contractors D&C costs to date in Trust               $174,545
              Site costs to date (UXO, fencing, Unity water charges)        $12,766
              Kane Constructions (This contract)                         $3,039,764
              Digital Hub Expansion                                       $459,000
         SUB TOTAL                                                        $4,996,761
         5% Contingency on remaining works                                 $193,474
         TOTAL                                                            $5,190,776
         TOTAL PROJECT BUDGET                                             $5,213,994

    b.      Whole of life cost analysis
    In accordance with Council’s internal policy, a detailed analysis of the expected operating,
    maintenance, and depreciation for the Peregian Beach Community House and greenspace
    infrastructure and services is under development. The methodology and analysis are well-
    developed, with preliminary operating and maintenance cost forecasts developed to reflect
    expected levels of service for the assets, along with consideration of more direct, fixed
    operational costs (such as electricity, insurance, cleaning) that rely on recent experience with
    similar Council infrastructure.
    Specifically, the whole of life costing considers:
           Annual operating costs – the ongoing costs required to keep the asset in operation.
           Annual maintenance costs – the ongoing costs required to keep the asset at a desired
            condition level.
           Depreciation – consumption of assets and infrastructure over an estimated useful life.
    Based on current estimated construction costs, the analysis is outputting annual maintenance
    and operating costs in the vicinity of $250k per annum, with ongoing depreciation expense in
    the vicinity of $150k per annum (with a detailed breakdown by asset type yet to be finalised).
    Assuming a total future ongoing operating budget impact of $400k, this equates to a general
    rate impact of approximately 0.8% that will be partially realised in the 2021/22 budget once the
    project is completed and commissioned.
    The analysis takes a conservative approach regarding operations and maintenance to ensure
    that Council can appropriately and adequately consider financial sustainability impacts on
    Council and the community.
    A new lease is to be established with the Peregian Beach Community House that will consider
    the new operational costs and any potential opportunities to offset.


                                                                                          Page 14 of 26

Section 15

ORDINARY MEETING AGENDA                                                              21 JANUARY 2021


    Risks & Opportunities

     Finance Risks                                 Mitigation
     Council request for scope increases.          This is to be mitigated through Project Control
                                                   Group and Capital Works Executive management
                                                   and limitation of client requested scope variations.
     Community requests for scope changes          Council acceptance of scope as awarded with
     once construction commences and project       intention of not increasing scope.
     becomes publicly visible.
     Geotechnical conditions give rise for         Pre-tender geotechnical investigations, and
     contractor claiming variation costs.          contract conditions have mitigated much of this
                                                   risk
     Contractor claims for variations based on     This has been mitigated through the lump sum
     changes required for design.                  contract and a fully detailed design with further
                                                   mitigation to be managed through the
                                                   Superintendent and Project Control Group.
     Clashes with underground services give rise   The contract conditions require full investigations
     for contractor claiming variation costs.      by the contractor before proceeding with work.
                                                   Pre-tender “Dial before you dig” report on the
                                                   entire site has concluded that the likelihood of
                                                   clashes is mitigated. This report is part of the
                                                   tender documents.
     Contingency amount being insufficient         This project has a contingency at 5%and is to be
                                                   mitigated through a review of saving options and
                                                   strict variation control.


     Programme Risks                               Mitigation
     There is the potential that the project is    The site is to be managed to minimise lost time
     delayed due to above average wet weather      from weather. The site is predominantly free
     forecast.                                     draining sand and generally lower risk of effects of
                                                   wet weather. The project has contingency
                                                   measures to mitigate knock on effects to other
                                                   stages.
     Covid causes impacts to labour and            It is assumed that construction industry will remain
     materials                                     an essential service and impacts are not forecast
                                                   into the programme,
     Resource risk                                 The project has no unusual or specialist
                                                   construction resource requirement and presents a
                                                   low risk to the contractor. The utilisation of
                                                   Council’s Superintendent and appointment of an
                                                   external Project manager consultant overseen by
                                                   Council’s Project Manager mitigates the
                                                   resourcing risk for Council.
     Structure construction takes longer than      The contractor is well resourced with an ability to
     allowed for.                                  increase crews to reduce risk of delays.


     Safety Risks                                  Mitigation
     This is a medium to low-risk project due to   Kane Constructions have extensive experience at
     the working at heights up to 8 metres above   this scale and type of project and would be
     ground, with relatively flat topography and   appointed as the Principal Contractor responsible
     adequate space for normal construction        for all Workplace Health and Safety of the site.
     activities                                    Prior to construction commencing, workplace
                                                   health and safety and pedestrian and traffic
                                                   management plans will be required to be

                                                                                           Page 15 of 26

Section 16

ORDINARY MEETING AGENDA                                                               21 JANUARY 2021


    Safety Risks                                    Mitigation
                                                    submitted to Council for review. Regular audits on
                                                    contractor compliance with these approved plans
                                                    will be undertaken by Council throughout
                                                    construction.
    Preschool, and community Traffic and            Specific requirements for contractor to manage
    pedestrians must share Rufous street with       safety of pedestrians and traffic are included in the
    construction vehicles and machinery             contract conditions. Regular audits on contractor
    operating and accessing the work site.          compliance with these approved plans will be
                                                    undertaken by Council throughout construction.


    Environmental Harm Risks                        Mitigation
    Environmental harm risks are generally          The contractor is to prepare an environmental
    limited to any contaminants found during        management plan, workplace health and safety
    excavation such as acid sulphate soils or       management plan and safe work method
    previously discarded materials such as          statements to manage risks.
    asbestos and unexploded ordinance.              A hold point will be established prior to excavation
                                                    and a risk-based approach for construction
                                                    methodology to ensure impacts are minimised.


    Scope And Quality Risks                         Mitigation
    Risk of not meeting project objectives          To be managed through Superintendent and
                                                    Council staff reviews supported by specialist
                                                    consultants who developed the designs and
                                                    specifications.


    Public Disruption and Council                   Mitigation
    Reputation Risks
     There is a risk that the proposed pedestrian   Specific requirements for contractor to manage
    and traffic management plans do not             safety of pedestrians and traffic are included in the
    provide an acceptable level of service during   contract conditions. Regular audits on contractor
    the construction period                         compliance with these approved plans will be
                                                    undertaken by Council throughout construction.
                                                    There will be regular contact with adjacent tenants
                                                    to review impacts as well as weekly review of
                                                    systems in place and seek opportunities to
                                                    improve wherever possible.
    Noise may be a cause of disruption due to       Specific requirements for contractor to manage
    noise from plant and equipment.                 safety of pedestrians and traffic are included in the
                                                    contract conditions. Regular audits on contractor
                                                    compliance with these approved plans will be
                                                    undertaken by Council throughout construction.
    Vibration                                       Not expected to be of concern due to excavation in
                                                    soft soils. Specific requirements are included in the
                                                    conditions to ensure that adequate notification of
                                                    surrounding tenants is provided.
    Amenity of the site reduced by construction     Propose to appropriately screen construction
    process and not acceptable for surrounding      fencing and work areas.
    tenants.




                                                                                            Page 16 of 26

Section 17

ORDINARY MEETING AGENDA                                                            21 JANUARY 2021


    Consultation
    External Consultation - Community & Stakeholder
    The stakeholders based in and around the Rufous St precinct including the community
    organisations on-site have been provided periodic project updates. They have been informed
    that tender submissions were called and that Council will be considering a report on the
    evaluation of the tenders.

    Internal Consultation

    Departments/Sections Consulted:

   Chief Executive Officer   X   Community Services                      X   Corporate Services
   Executive Officer         X   Director                                X   Director
   Executive Support             Community Development                   X   Financial Services
                                 Community Facilities                        ICT
                                 Libraries & Galleries                   X   Procurement & Fleet
                                 Local Laws                                  Property
                                 Waste & Environmental Health                Revenue Services

   Executive Services            Environment & Sustainable Development   X   Infrastructure Services
   Director                      Director                                    Director
   Community Engagement          Building & Plumbing Services                Asset Management
   Customer Service              Development Assessment                      Buildings and Facilities
   Governance                    Economic Development                        Civil Operations
   People and Culture            Environmental Services                      Disaster Management
                                 Strategic Land Use Planning             X   Infrastructure Planning,
                                                                             Design and Delivery




                                                                                          Page 17 of 26

Section 18

ORDINARY MEETING AGENDA   21 JANUARY 2021




                                             Attachment 1




                                            Page 18 of 26

ORDINARY MEETING AGENDA                                                              21 JANUARY 2021

                                                                                                                                                 Attachment 1
                                                                                              T000018eregian Beach Community House and Greenspace Contract Award
                                                                                              Att 1. Design Images

                                                         er              |  | papell                             f e                            |

      eH                                                                 Vs                         Pf H
      F                                             ‘          We —7 :         .              ae                                                    }
     1)              ae        ee                             bE        le ia                                     i                         A
    =                 — Ss                                hee       —                                                                      a
                       ie EB                                                            oe                                                 H        }
                                               as            :        eS                                                                            |
                                            oe                        ‘ae                                                                          :
             a             |        2            OS    Pee                                                                            .
              =)
                                                                                                                                                    |
                                                                                                                                                Page 18 of 26

Section 19

ORDINARY MEETING AGENDA   21 JANUARY 2021




                                            Page 19 of 26

ORDINARY MEETING AGENDA                               21 JANUARY 2021
               |              . @)  2 2    @&    8)    Q_,  O©
        \ (-)    NN    Va       |    :  :   !     4 o ;    | | |    \ \
   ?                 OV ea
          \             YR ee                  oF                       |
           \            :               oT           vb             |   \
             ,               Sb                                     [
            \           LS                        |      A              A
              |         YOO                            [AG
              \            | 7       \4      eee       [*) fk) i“     ‘
              VQ        WW                        I  pl               td
                       RMON                       |       Dd          ee
     yt       Neely                                       (Ds |
     “           spect ane iS a     Fd                      a an icoaa
     bo)            oS             SQPRQE Age ares Seager age gengE AoE abeabe sme age PSA)
     “To    of OO      : -   Ve         Pbogtaatessce            yey
     .            meee     We     —          aaa aaarnarinarii   K   {Nhe a
             i   oem te rm   waw                                       ‘
      Sa |                     =     SS          Seat iy            Er,        tn      aT
      2 =                                                       ee
                                                                                            Page 19 of 26

Section 20

ORDINARY MEETING AGENDA   21 JANUARY 2021




                                            Page 20 of 26

ORDINARY MEETING AGENDA                                                                                   21 JANUARY 2021

          1@\\(\\\                                                                                  )     ©                  |               ®
          ~%     \E\     TY  \   A                                                                                           |                   |                                  ‘
           S\VV\               \  le                       ®            ©            ©                @                     |       fo         ||      p        @
           WS  \       \V \   \   \
           WA     \ AN        \          i       \                                                                         |
            WAY    \ AA \    \   \       I        \                                                                        \           i        \
             Wat    \i\   A   AN         |          \       |            |            |                        |            \          |        rAd              |
       (A)   RR                         ti              ei              pi                         PI                                          PAI             PS              de.
             VW    \     VAY    \  A     i             \    i                                                           “              |                i
             WA     \AM\\\                              \   |                                                  |                                t   \!       seaed
              \\ \   \XW\         YY                     \  |            |            |                      oT                        |        Sh >                              \
                 \e\   \Va\bae  \  \  \                fa                                                   fer                                             =    H        NN       \
               W\Y\     Wath     \\\i                  Bt       eee                                         ‘ns                    rr                     2
                   \          WY  \  \  \t             H           H     }                                  Hj    ome   |          mat |        }    =      —                  \
        OLLA\N \A\                 \ \  A             UES          ALS                          _           fe -- SS -4            a                  a
               ok               A pr rf                     rll en           as             —     4     pre le ergo i errr grrr
                     AW          \\fi          jhe      @ || 2            S| ©                  :          eal                         2                |
           F      IN    \  YU i \      H     eer ee            => |      i,    ===              SS | — | — — / — | | —                         | —               H   \           \
     2     EV)              (SQ              ii                          =                                                                              —|!           \@ |        \
        ole           AO                     IT                                               lg dd
                   \                                        if                                                                         H                 nue     THON               \
           bors                (i  Sh. es                   if           a     [S|                             3                       ;                 me |
           5    3:                                                                                                                                               bb
                ey              ;    yd                                               |                 neers                                           I        ry       GS
                2    |  \                      rt           [|                                                 |                       |                         if
                s    4        en    en            eors      ti           |            |                        |                       |                |        1H
               SOR ete                              ON                                             eee
        ©             ye                                   Ti            |            i                        |                       I                i        ray
               ee          ee ne                                                                      =        |                       !                a
                                  t     i                    1                                        cane                                                            \      \
       (E)     a?                          RT Te BP
             emcee   '       ¥     ‘    \                     enn enn                   nn                                                                             \      \
            OMiEngnee's                  v                               :                                                                                              \     \
            Ones        ‘           \    1                  |            |                                                                                       H      \     \
                              \     ‘     \s                  E          j                                                                                       H,      \     4
           Poy          \      Sak                                       |                                                                                       ,       \
            | /         SATIS                               mot                 A             ES
                  /    ~~) SK 7H EE Oh                                                                                                                           H  \      \     \
                 '     /          — ~ Py                                 |                                                                                       H    \     \    \
                 /    /         ti     \ |  \          — | =       =    ——     —                — ——    —+= -.          = —                      —, | —          H    \      \    \
       (F)     pe tig PS Fo                                                                                                                         eS
               '     /           ae en                                   TV           TX             \         T\            \         rN               i        TN             \
              /      !            TY    iO AS                                                                                 \        iN               i\       i  \       XQ    \
             hoy                  aH                                                                                 LY        Xt            XQ         trot         \       XX
             '    ch cenennenennnnneneen eee pont    Ht                  :    \       :      \           \     :     \            \    |        \       |   \    |     \        .
        eb                   oh i            AL            ee           ee ee                                                                  ee on or ae
      Pas         ’          ;        \            :            a              L              \                        X     Bares 7 \                         \          ‘          x
     or                     j         Vl                    i            |       rj             =         Oy             Ve                       om           “          =
          A,                i          Mi         |         i    |       i       Li             \         A i             \            i\           \   i        i           \
                                                                                                                                                      Developed Design Submission
          es.                               teem ea                                           petince bacae At +    RBH                Propet         Orang Tite         Pret No.
          Lae ee onan hem                fee fees ree                                                22 ia      ts. GEE               Rufous Street   Basement Floor              1911
         Al sie beads aed dated survey formation of setons [asans | ferceusa eee —           Fae aa cae, A A   ao sag                 Community Centre Plan              as
          Sea aS                                                                              aycae                :                   CET                  ere                 DD.101
          ee Spe                          [PaNEra2 | Dewaioped esas Sunrise                   Bl tana! © coped     83   te      Bark “2""=            Approms Oy 50       —=_—
         Seeeeeoeneeaas _                 {+                                                  Hey of Bae EG pone mre 3   i|       a    Ome Croembe 209 Sco 1000 @ AZ                E
                                                                                                                                                                                     Page 20 of 26

Section 21

ORDINARY MEETING AGENDA   21 JANUARY 2021




                                            Page 21 of 26

ORDINARY MEETING AGENDA                                                  21 JANUARY 2021

      a               |                                             oe               (9          ¢
      N\ Di) \ Le                      ©        ©         ©           '    "@        |    '®      VP\         o
      No \ VAR                  \       i                                           |             ;        eet
       \i\ \KW \\N            ——                   _---- je        mes   dee                               come
    @A    A AAA BA         to     ere       etre          |                |        \       foo tN Tt                      oo
        i \ RA)            TE           i              fj         =                         j=!      \ —) LS              \
      yW\\ \th e\) |          | Baer SB                                                     a]
      |    \\ Wa YA           te zo etewe    i                             ||               |        PONE                YY |
    ol      \\Q     rn i et                pe                                          ©    i   ©             |        \
          \   \    a\ Vet lb   A  i     7              7  :                ‘                :           :     :
           v   vy   VW \ N =   —————         S-      oo —S                         eee   ————         = ed               Age
      |    La \EAAWAT\          oH      ©                 Po                                             =“   F
      I    | \ \ \Y \\Y eK \ — a AG              | set    ———                                                 '
  > |      \\\      tn)       i = OY             i  ome >2          SS ——                        =        zi      -<>     |
    ©    a Sait —— bce        |    Lec     aS Cn           a ———————————                     a ae                        44.
            \\\NVWU\NA             6     1                                               ae                                \
          2‘\\\ \\\ ¥yqirx           =            e      SSS                                            i     (     ©    i
          s \\ \\ \\\ V1 fi\ \             see             So                        ae
      HOF        \\ 4d 4 Gi \ oo      i     =       me     PY                                           }     i]  Lea {7
          PAWLSMAL      AQ         OA            Ce        en                                           ie =)       YK?
          g  \\      YOANN TSS        1                           3)                      | 2                        v      |
    OL   ---*      A                          oo...        PAG                             iP           ZO a                A
              Wi      4  &    \      kb        NP         |           cate |                ie me       IES   Hef
    epi RN                                                            ei    ©             @@qs       abe fe             11 \.
              /\ rt            ere   | ae            LA   i | | A |        LA              I |)         |     iE | \
             J \ SS net                  FO          ei                                                       an        |
            p  \\  \--ANK           \TA creer        me   |       [7 me                                     oO         eS
      4     '   .   \   '  A         4  concer &)   cer   |   qh    an)                                 |       Z\,     \
      "|       ay   Uy     ich           fo      |        i|  Wy  tt                                  S|      ifg \      \
    | font KP pin A                              =        aa                                         2        at + SX
           )   DGS -die             | Pas                 i}  le            ©        ©            ©           i  \       \e
           mo        (Pt             il                   i   Re        Ee             ee eee eee             ie \        \
         a   /       \ =F ‘i hi          CN “or                  ey          Sennnnnvenvvveynnnnnnnnanyenananannangnnnnnesaavaanvanangnnnnennsanany ] \
        j    /       Nave -}/ \         |        I  \     1  o\      \     |  |}             Oe                         J
            /          Sah Me           |        i  \     1   \       \    |     Poe                    dS
           ee           ei A=           |        |   \    |   \        \    OO —=EEaower sees       Eee  SSS         lt  °
   a /                ae !    wingers Selec cece bec    RABI     eect nee eneetglecencnentecetbenethedeennestan tN
      a]          ;      \\!            !        |        |      =      er         e       T         eT       F       =
      /   '       i      Vi                 |    i     \  i      \        \i        \       i\        \ i     \       \
      =            ar     =                                     $e tent soon                re        Developed Design Submission
      Saal =                   eee        —                   Bee, Pye                      Fufous Steet Ground Floor Plan _ 1911
      Hien       SS         See                                 Seeks         3             ae oe wire                  DD.102
       steeeions eect, F_ [22032000 _| Devoted Dewey Sutrression ald tana coped je     Bark feeon Gntacos: Approved By: 58 —_
      See             -     t+]                                 Ey of San Sate ponate rnin F i| Owe Oecembe 2019 Sea 00 @ AP i=
                                                                                                                             Page 21 of 26

Section 22

ORDINARY MEETING AGENDA   21 JANUARY 2021




                                            Page 22 of 26

ORDINARY MEETING AGENDA                                                                  21 JANUARY 2021

              on              y <   i                                                                                                                 >
                                      =
                          Es       ‘Zn   oe
             ;           f           ;
             |           hd         Ce
        na re             04 \/                                                                                                                   x
           _        ;    ig
         :      h        :                                                                                                                     Bey
                                                                                                                                                 Co
                                                                                                                                         a
           f                                                                                    es   >                      )            ye          f

                                                                                     = —           La       ln      —       ,        er         P
                :                                SS       a        ee ee                                  —S=   S                       ‘       ae
                     ae                    ea   ta                      EB     =        =             =   Se                              iia
        a              oot     =           ;   a =                      ee ee     ——           [sah ee          Cae Cy             Fy            ;     P
        Pe            f                        a             re                =    et        lL                i aren                           ee
                      |         Tae |               VE         Moe        Li    it                 ;   2    2 eh                     |          :
        ee                     es,                           “meet           ee ||                         |      ae
                        aes            eS        2 ae                     Le                                 ew                          ae
                       ee               ee            a           !        =                    i                                        :
                         .                                            3                      ee                             .                          )
                                                                o eli                           nS  \
                                                           -                          oS)
                                                         yi)                                   — \¢ ys    a E

                =                         :          q                  .              ——                          —
        Cie from North West

                                                                                                   ‘ei                          Developed Design Submission
   SOE                          EE                                            Uae faved amenaiors      a.        Oe   )!|LTCTLCLlTlT— lO
   SaaS eS.                   5                                                    es    at. et            -       Rufous Street Extemal3D Views         1911
         "=                    pee]                                           Trae Saige sa A MMR SEE cong c7     Community Centre               ——_—.
                                —                                             etek fam, Suge     : its     7       fanaa        Bren By | FETC         DD.502
                                   OS                                         conse” Stee          Be            [te mente me = Sam sgezeA2      Uk
   KS                                                                         ia oe werures § Hiyl       PBK           ere           ee
                                                                                                                                                        Page 22 of 26

Section 23

ORDINARY MEETING AGENDA   21 JANUARY 2021




                                            Page 23 of 26

ORDINARY MEETING AGENDA                                                                            21 JANUARY 2021

                                                                                                                                             5

                               «                                            gues
                                          :           it      —                     ’
                           7
                           -            7
                                 &

                                                :                             Il                        |                         sie
                                                                                        ma                     a             am E       ]   .
                                                                                      q
                                                                                          7                         en     a
                                                                                |          ‘                                U
                                                                                i         Ee                   Oi        2:

                          4 —\ View from West

                                                                                                                                           Developed Design Submission
     fe                                    sa                                        Use figued amansicrs   as =<“ —_ 2.”                    aa) Ue                   ee
     Boece seecereterishinstn, .  ie faasan oent arg ota                             seeeatiss vntee i Te! £ Hoult           Rufous Street External 3D Views a       1911
            .                      -——                                               SSE Eee oe SO C7                        onnueones                   =           eos
                                        J                                            patel doo Bugs       2 Pa     a7       BeachQLD 4573  oneney ve.te            DD.503
                                    —                                                eee oe              Shei]        Bark cca          |        ee          =
                                    Po                                               ara     wo serentdamee BASES 8
                                                                                                                                                                         Page 23 of 26

Section 24

ORDINARY MEETING AGENDA   21 JANUARY 2021




                                            Page 24 of 26

ORDINARY MEETING AGENDA                                                                                                                                                            21     JANUARY 2021

                                                                                                                                                                                                                                                                                      ,                  Pe
     |                                                                                                                                                                                                                                                                                                                                                |
     |                                                                                                                                                                                                                                                -                                                                                               |
                                                                                                                                                                                                                                                                                                                                                      |
     |                                                                                                                                                                                                                                                                             -                                —<                                |
     |
     |                                                                                                                                                                                                                                                                                                                                               ll
                                                                                                                                                                                                                                                                                                                   a                 ~          ll    |
     |

     |                                                                                                                                                                                                                                                                                                                                                |
     |                                                      |!                                                                                            ,            7                                                                                                    am                                a
     |                                                                                                                                         wre                                                                                                                                                                             etter:
                                                                                                                               ewe                                                                                                                                                           :                                                        |
     |                                                                                                                                                                                                                                                                                                                                                |
     |                                                                                                                                                                                                                                                                                                                                                |

     |

                                                                                                                                                                                                                                                                                                                 Page 24 of 26

Section 25

ORDINARY MEETING AGENDA   21 JANUARY 2021




                               Attachment 2




                              Page 25 of 26

ORDINARY MEETING AGENDA                                                                     21 JANUARY 2021

                                                                                                           Attachment 2
                                                                   T0000 18eregian Beach Community House and Greenspace Contract Award
                                                                   Att 2. Evaulation Workbook
                                                           Final Evaluation

               NOOSA SHIRECOUNCIL          Weighted Attribute Evaluation Spreadsheet - Final Evaluation
[comes                                   ([ereeganconmentyiomeecermne
           a
              NAME OF TENDERER                                  PRICE
              (Contorming Tenders Onty)                      {excl of GST)
            a
            2 [Kame Constractions (QLD) Ptyits                      0887
            3
            4
            StL.

                                                                 ia              2               3               4
    | Pamrationprceetements                             |         wins   |    uni      | pens           | WACRCOP LAE
                                     :                        son Comstructon | Kone Comstructhhons =
            pemincme                     |   ees |               Soe]           | Se |           Se] |
             fet tecmmicnscre            | Cm           | Ce | ls |e                                    | les

pare ectement                                           |        omits   |    une       |     pens       | MACRO EA
                                    S                         son Comstructon | Kone Comstructhons  a
               fotal Fees (Pc)                  40%           $2,814,500     $3,035,765       $3,308,744     $222,627
              Average Fees (Pew) $_..          $3,321,753
              Price Score                                       us              106             100             76
              Normalised Price Score (Pr)                       100              s4             37              ee
              Weighted Price Score (Pw)

              |        Financia CapabiityAcsessmentPanes |                  Psion Title

                ‘The Contract Administrator confirms the above scores and  ok
                          weightings ~ of this: evaluation               ;

                                                                                                         Page 25 of 26

Section 26

ORDINARY MEETING AGENDA                                                          21 JANUARY 2021


10   CLOSED SESSION

     Nil.




11   PUBLIC QUESTION TIME

     1      IAN HODGETTS
     Q1: The Council effectively advised the State by letter dated 29 July 2020 from the Acting
         CEO to the Executive Director DSDMIP, that the planning scheme amendments to
         address coastal erosion would reduce the value of a limited number or properties along
         the coast". Are these “to be” devalued properties, as identified by Council on 29 July
         2020, in the following streets and if there are properties "to be" devalued in other streets,
         please list those other streets: Seaview Tee, Arakoon Tce, The Esplanade, Stevens St,
         Belmore Crs. Park Crs, Ross Crs, Tingira Crs, David Low Way (at Sunrise), Lorikeet
         Drive, Pitta St?

     Q2: What criteria did the Council use in identifying this limited number of properties? Was it
         the Coastal Hazard line as at 2100; or 2070; or 2040 or at present?




12   NEXT MEETING

     The next Ordinary Meeting will be held on 18 February 2021 at the Council Chambers,
     9 Pelican Street, Tewantin commencing at 5pm.




13   MEETING CLOSURE




                                                                                      Page 26 of 26

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.