Decision Notice - Change to an Existing Approval - 010.2004.00005743.003 [As Published] · 132004.5743.03
Officer: Tracy Jones
Direct Telephone: (07) 5449 5228
Response Address: PO Box 141, Tewantin QLD 4565
Email: [email protected]
Our Reference: 2004/5743
Your Reference:
11 December 2008
Dynamic Cafes Pty Ltd
PO Box 217
NOOSA HEADS QLD 4567
Dear Sir
Change to an Existing Approval
Integrated Planning Act 1997
I refer to your request to make a change to an existing approval. On 11 December 2008 Council
decided your requested changes.
Details of the decision with the consolidated conditions are as follows:
1 APPLICATION DETAILS
Application No: 2004/5743
Street address: 18 Douglas Street, Sunshine Beach
Real property description: Lot 10 SP 208608
Planning Scheme: The Noosa Plan
2 DECISION DETAILS
Council on 29 November 2006 decided to issue the following type of approval:-
Development Permit for Material Change of Use - Duplex Dwelling
In relation to a request to change the existing approval, Council on 5 September 2007 decided to:
A. Amend Conditions 1, 4.1, 7, 8, 11, 22, 24, 26 and 27
B. Delete Condition 2
C. Include one additional condition
D. Issue a Compiled Decision Notice
In relation to the request to make a change to the existing approval, Council on 11 December 2008
decided to:
A. Approve a change to Condition 1
B. Include an additional condition
C. Issue a Change to an Existing Approval
Page 1 of 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 12 pages
Page 2
2004/5743
3 RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager
conditions.
4 ASSESSMENT MANAGER CONDITIONS
Land Use
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are titled and numbered Site/Roof Plan
Dwg No. 61.04.01B dated 8 August 2006, Changes Application - Plans A (Basement and
Level 1) Dwg No. 61.04.52B dated 23 August 2007, Changes Application - Plans B (Level 2 &
3) Dwg No. 61.04.53A dated 22 May 2007, Changes Application - Sections Dwg No.
61.04.54B dated 23 August 2007, Changes Application - Elevations Dwg No. 61.04.55B dated
23 August 2007 prepared by Will Franklin Design and Ground Level Floor Plan Issue A
prepared by Design International and dated October 2008 and as may be amended by these
conditions.
2. Deleted.
3. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
4. The open space and setback areas are to be landscaped in accordance with Council’s Policy
on Landscaping Guidelines and a properly prepared landscape plan prepared by a suitably
qualified Landscape Architect or Horticulturalist. Such landscaping is to be completed prior to
the premises being occupied and maintained at all times thereafter. The submitted
landscaping plan shall detail the following:-
4.1 The retainment of mature melaleuca species in the road reserve and the five trees
along the site’s side (north eastern) boundary;
4.2 the provision of dense screening vegetation along the side (eastern and western)
property boundaries of the site in order to screen the basement walls, and entry areas
as illustrated on Level 1 floor plans and provide privacy screening to adjoining
properties.
4.3 the provision of dense screening vegetation along the Douglas Lane property boundary
and setback area to screen the swimming pool, basement walls and any fencing.
4.4 the provision of dense screening vegetation along the Douglas Street property boundary
and setback area, particularly between the swimming pool and front property boundary
to screen the swimming pool from the street. Landscaping shall enhance the amenity of
the streetscape.
5. Existing trees on the site and within road reserves are to be retained, except where required to
be removed due to building operations or the conduct of the approved use.
6. All fencing shall be setback at least 1 metre from the front property boundary (Douglas Street),
with at least half of the fencing setback 2 metres. The area of land between the fence and the
front property boundary shall be densely landscaped to screen any fencing from the street.
7. The swimming pool located in the north western corner of the site shall not project greater
than 1 metre above natural ground level within the front 6 metre setback.
8. Any deck or balcony areas are not be enclosed with shutters, glass panelling or the like, thus
remaining as open structures except where in accordance with the approved plans.
9. All hot water systems installed shall be either solar systems; electric heat pump systems; or
gas systems (LPG or natural).
Page 2 of 13
Page 3
2004/5743
10. The development shall not exceed a maximum height of 3 storeys and 12 metres above
natural and finished ground level.
11. The natural ground level is to be reinstated around the building.
12. The proposed development shall have all kitchen, laundry and bathroom fittings that comply
with the AAA Water Conservation Rating System as defined by the AS/NZS 6400 (Water
Efficient Products - Rating and Labelling 2003) and AS/NZS 3500 (National Plumbing and
Drainage Standard Part 1.2), with toilets to comply with the AAAA Water Conservation Rating
System. All tap ware and shower roses shall not exceed a maximum flow of 9 litres per min.
Dishwashers and washing machines are excluded from this requirement.
13. A verification survey of the building is to be carried out by a Licensed Surveyor and a
certificate lodged with Council during construction and upon completion of work confirming
compliance with the maximum allowable building height as required by either the conditions of
approval or the Planning Scheme.
14. Security in the form of a cash bond or trading bank guarantee to the sum of $15,000 must be
submitted, to secure performance of all conditions of this approval, prior to the issue of a
Development Permit for operational works. The cash bond or trading bank guarantee will be
returned on performance of the conditions of approval less any costs incurred by Council in
respect of enforcing performance of this permit.
15. The requirements of this development approval are to be effected, prior to the use of the
premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
this approval to effect compliance with conditions.
16. The Development Permit for a material change of use of premises lapses if the use has not
happened by 29 November 2010, unless an application to extend the currency is approved by
Council.
17. The developer must obtain all of the other Development Permits referred to in the Decision
Notice, prior to obtaining a Development Permit for Building Works.
Land Development
Lot Amalgamation
18. All separate, adjoining lots that form part of this application shall be amalgamated into one
undivided lot in accordance with Section 3.7.3 of the Integrated Planning Act and the Plan of
Survey submitted for registration at the Land Titles Office. Proof of title being issued for the
amalgamated lot shall be submitted to Council prior to the issue of the Development Permit for
Operational Works.
Vehicle Access
19. A vehicular access driveway to serve the development shall be constructed with a maximum
width of 3.0m from the existing kerb and channel in Douglas Street to the front property
boundary and then widen within the site to the full width of the entrance to the carparking area.
20. The driveway shall be designed and constructed to Council’s design standards and to grades
that prevent vehicles from scraping and/or bottoming whilst also allowing pedestrians
movements along the footpath without any level difference. Should any driveways be
constructed to grades that do not comply with AS/NZS 2890.1-2004, Council will require that
the driveway be removed and reconstructed to levels that do comply.
Please note, a step between the driveway and the footpath shall be avoided, as it is preferred
to have the footpath continue at a constant grade to minimise the potential for pedestrians to
trip or fall.
21. All vehicles shall enter and leave the site in a forward direction.
Page 3 of 13
Page 4
2004/5743
Carparking
22. Carparking shall be provided within the site generally as shown on drawing number 61.04.52B
dated 23 August 2007 by Will Franklin Design, except as modified herein.
23. A minimum of 3 covered car park spaces shall be provided on site, including 1 clearly defined
visitor car park spaces.
24. The car parking area shall be designed to comply with the provisions of AS/NZS 2890.1-2004
for user class 1A with allowance for vehicles to enter and leave the site in a forward gear and
with a minimum head clearance (headroom) at any point of 2.2m. In this regard the proposal
plans shall be modified such that:
i. the double carspaces shall have an overall width of 5.4m in accordance with 2.4.1(b)(ii) of
AS/NZS 2890.1-2004 and
ii. the single carspaces shall have clearance to all walls and obstructions in accordance with
figure 5.2 of AS/NZS 2890.1-2004 and
iii. the proposed visitor carspace shall be a minimum of 5.4m x 3.0m and.
iv. The access aisle in the basement carparking area shall have a minimum width of 5.8m.
25. The proposed turning area at the end of the aisle that serves the proposed double carspaces
shall be line-marked with chevrons and have the words “No Parking” painted on the pavement.
A sign shall also be provided to indicate that the area is a “Turning Area Only” and that “No
Parking is Permitted”.
26. The proposed visitor carspace shown on drawing number 61.04.52B dated 23 Aguust 2007 by
Will Franklin Design shall be dedicated as a visitor car space and shall be signposted “visitor
parking” and shall have similar wording painted onto the pavement to prevent misuse of this
space.
27. To ensure that visitors to the site are aware of the on-site visitor parking facilities, a small sign
shall be erected on the front property boundary, adjacent to the driveway, to advise visitors to
park on-site in the designated visitor car park space.
28. All carparking shall be kept, maintained and line-marked in a condition fit for use.
Frontage Works
29. Footpath improvements such as topsoiling, grassing, and tree planting are required to the
Douglas Street frontage of the site in accordance with Planning Scheme Policy PSP03
Landscaping Plants & Guidelines. Grass shall be couch, free of weeds.
30. A new 1.5m wide concrete path shall be constructed along the Douglas Street frontage of the
site in accordance with Council’s design standards and to an alignment that protects any
significant vegetation or any underground services.
31. All paths shall be designed and constructed to ensure pedestrian safety using non-slip
materials, to produce an evenly graded surface finish, and to be in accordance with the
Disability Discrimination Act 1992 and Australian Standard 1428.1 Design for Access &
Mobility.
32. All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel,
footpath paving and landscaping such as trees and grasses in accordance with Council’s
Standard specifications prior to commencement of the use permitted by this permit.
Stormwater Drainage
33. All stormwater drainage shall be collected on site and discharged so there is no net increase
in stormwater runoff from the site. Stormwater drainage permitted to drain from the site shall
be discharged to Council’s existing drainage structures in Douglas Lane. Plans of the
drainage design shall be prepared by a Registered Professional Civil Engineer and submitted
to Council prior to obtaining a Development Permit for Operational Works.
Page 4 of 13
Page 5
2004/5743
The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street
drainage system at any one location is 25 litres/second.
34. Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank
(minimum storage 3000 litres per dwelling/unit) that is installed to ensure water from the tank
can be used for external uses (such as watering gardens, irrigation, ornamental ponds, water
features, topping-up swimming pools, outdoor cleaning, etc) and for use in flushing of toilets
internal to the dwelling/unit. All rainwater tanks are to be designed and installed in
accordance with the Queensland Development Code (QDC), Part 25 – Rainwater Tanks, and
shall be part of the plumbing application in conjunction with the building approval. The
location and capacity of the tanks shall be clearly shown on the plans submitted for Building
Works approval and any overflow shall be directed to the stormwater drainage system.
35. To ensure that polluted run-off does not enter Council’s stormwater drainage system,
stormwater run-off from the carparking areas and the driveways shall have the first flush (the
first 12 mm of rainfall or hose-down) collected in a grease/oil arrestor provided on site prior to
being permitted to discharge into Council’s drainage system.
All other clean stormwater, such as roof water, can be collected on site and discharged
through a single underground drain line directly into the existing drainage system, bypassing
the grease/oil arrestor.
To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil
arrestors, which shall be submitted to the Council for approval prior to obtaining a
Development Permit for Operational Works.
The approved maintenance plan shall be incorporated in the Community Management
Scheme for the development and a copy of this shall be provided for Council’s records prior to
commencement of the approved Use.
A Development Permit for Building Works shall not be granted until a Development Permit for
Operational Works has been issued in regard to the drainage scheme.
36. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
37. The site shall be connected to Council’s existing sewerage reticulation systems and be
constructed in accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply
38. The site shall be connected to Council’s existing town water supply and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
39. Each individual water connection to the water reticulation system shall extend to the property
boundary and be metered. All fees for the supply of water meters shall be paid to the Council.
40. For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the development
shall either be served by:
40.1 a single Body Corporate water meter to measure the combined/shared Body Corporate
and individual Use flows (including fire hose reels, but excluding fire hydrants and fire
sprinkler systems), or
40.2 multiple water meters to separately measure Body Corporate (if any) and individual Use
flows (including fire hose reels, but excluding fire hydrants and fire sprinkler systems).
41. All water meters must be located outside the property boundary and in an easily assessable
location to facilitate unhindered reading by Council and/or Council’s contracted water meter
readers, and not behind fences or locked gates. In this regard approval of the water meter
configuration and location must be obtained from Council’s Water & Sewerage Capital Works
Manager prior to lodgement and approval of hydraulic drawings.
Page 5 of 13
Page 6
2004/5743
Earthworks
42. Earthworks and construction works carried out on site shall not affect the structural integrity of
any of the existing fences or structures or lands that border the development site. Fences that
are affected shall be replaced prior to the Building Certifier issuing the Certificate of
Classification. In this regard any fences to be replaced shall be clearly shown on the plans
submitted for Operational Works approval.
43. The use of vibrating installation techniques for sheet piling and any other vibration causing
construction techniques for excavating, earthmoving, demolition or compaction, including
vibrating rollers, is not permitted.
Site Stability
44. A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site,
determine the soil classification, establish whether any measures are required to protect the
stability of adjoining buildings and/or structures and/or land, and make recommendations on
the type of foundation system(s) best suited for the proposed development. The
recommendations of this report shall be incorporated into the design and construction of the
proposed development.
Erosion and Sediment Control
45. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to
be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
General
46. A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
specifications for all engineering works that will become Council infrastructure, which shall be
submitted in conjunction with an application for a Development Permit for Operational Works.
In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be
submitted in conjunction with any application for Operational Works.
47. Digital detailed design drawings and calculations shall be submitted with any application for a
Development Permit for Operational Works in respect of roadworks and stormwater drainage
works. The design shall be in accordance with Council’s Planning Scheme Policy PSP05 –
Engineering Design Standards – Roads, Drainage and Earthworks. To avoid conflict with
underground pipes or services, all existing and proposed services required by the
development shall be shown on the plans.
48. To facilitate production of As Constructed drawings it is suggested that all design drawings are
submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the
use of ADAC are available at www.adac.com.au).
49. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
50. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
51. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to or
from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
Page 6 of 13
Page 7
2004/5743
52. As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
for design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and
type of all services and structures. All of which shall be submitted to Council for checking and
for Council’s records.
The data must fully detail levels for all engineering works including but not limited to drainage
structures, finished ground levels and pavement surface levels. The data shall be submitted in
the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC
are available at www.adac.com.au).
Approval of works shall not be granted until all As Constructed information has been supplied
and accepted by Council.
Environmental Health
53. A Waste Management Plan shall be submitted prior to demolition, removal or relocation of the
existing building on- site.
A Waste Management Plan is also required for construction of any building that requires
development approval.
Waste Management Plans are required to be submitted in accordance with Planning Scheme
Policy 11, see table below.
Waste storage areas are to provide for adequate separation of all reusable, recyclable and
waste materials. These shall be located so that they are convenient and safe to use. (Waste
Management Code)
The Plan shall contain the following information:
The site area for the storage and separation of waste is to be shown on the plan
drawings accompanying the application.
A waste management table as indicated below is to be completed showing how waste
material is to be segregated - recycled – reused or disposed.
MATERIALS ON-SITE DESTINATION
Re-use and Recycling Disposal
Expected waste Estimate On-site Off-site *specify
materials volume *specify re-use or *specify contractor and
(m³) recycling contractor and landfill site
methods end user
Excavation
material
Green waste
Bricks
Concrete
Timber-please
specify
Plasterboard
Metals - please
specify
Asbestos (see
below)
Other - please
specify
Note: If a demolition contractor is undertaking works, then the Waste Management table is to
be completed by the demolition contractor.
Page 7 of 13
Page 8
2004/5743
The purpose of the Waste Management Plan is to facilitate the segregation of waste for the
effective reuse and recycling of such materials. Additionally Council rewards those who
segregate waste by significantly reducing disposal fees at the landfill, some items are free.
Higher gate fees are charged for loads of mixed waste.
54. Noise emission from swimming pool and spa equipment (including heating equipment) shall
comply with the following requirements:
54.1 The equipment shall be installed and located in a manner that prevents excessive noise
in accordance with Council’s Local Law No. 12 - Control of Nuisances. Infringement
Notices (on-the-spot fines) may apply for offences.
54.2 A person must not use equipment on any day if it makes or causes noise to be made –
54.2.1 From 10pm to 7am: Which is audible outside the most exposed part of an
affected building
54.2.2 From 7am to 7pm: More than the lower of either –
50 dB(A)
5 dB(A) above the background noise level
54.2.3 From 7pm to 10pm: More than 3 dB(A) above the background noise level.
55. Noise emission from mechanical equipment (air conditioners, refrigeration equipment or pool
pumps etc) shall comply with the following requirements:
55.1 The equipment shall be installed and located in a manner that prevents excessive noise
in accordance with Council’s Local Law No. 12 - Control of Nuisances. Infringement
Notices (on-the-spot fines) may apply for offences.
55.2 A person must not use equipment on any day if it makes or causes noise to be made –
55.2.1 From 10pm to 7am: More than the lower of either –
40 dB(A)
3 dB(A) above the background noise level
55.2.2 From 7am to 7pm: More than the lower of either –
50 dB(A)
5 dB(A) above the background noise level
55.2.3 From 7pm to 10pm: More than 3 dB(A) above the background noise level.
55.3 Submission of written certification from a suitably qualified person confirming that the
noise levels comply when measured at either the residential boundary or outside the
most exposed part of an affected building, whichever is the closest to the equipment.
This is required immediately after installation of the equipment and prior to any
occupation of the building, and in a format approved by Council. This assessment must
take into account noise from any other fixed equipment on the property e.g. swimming
pool pump, heating equipment, that may increase the overall noise level emitted.
56. Noise from building works associated with residential development shall comply with the
following –
56.1 Limited to between 7:00am to 6:30pm Monday to Saturday.
56.2 All reasonable measures are taken to minimise noise emissions.
56.3 Not permitted on Sunday or public holidays.
Page 8 of 13
Page 9
2004/5743
Land Use Additional Condition
57. The removal of the four existing mature trees along the site’s front (northern) boundary and
one existing mature tree along the site’s western side boundary are to be replaced with native
species of 100 Litre pot size and planted in similar locations on-site
58. Screening devices shall be installed along the south-western elevation of the new balcony on
Level 3 of Unit 1. These screening devices shall extend from the main façade for a distance
equivalent to the existing two glass panels out from the facade and shall have a height of 1.8
metres to ensure privacy protection to the adjoining residential premises.
5 REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Referral Trigger Referral Status Referral Agency Referral Address
Nil
6 APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the Assessment
Manager conditions.
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. The applicant is advised that a Compliance Permit for all plumbing and drainage works within
the boundaries of the development site shall be obtained from Council’s Plumbing Services
Section prior to obtaining a Development Permit for Building Works.
2. Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if
the cost of operational works exceeds $80,000, then a portable long service leave levy is
required to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight
the approved form issued by the Building and Construction Industry (Portable Long Service
Leave) Authority that confirms that the requirements of the Act have been satisfied. A statutory
declaration outlining the cost of the operational works must be submitted to Council with the
lodgement of any application for operational works over the site.
3. We advise ‘interested parties’ i.e. ‘developer’, ‘owner’, ‘tenant’ to consider their responsibilities
under the Disability Discrimination Act (DDA) in regard to the installation of disabled access
and the provision of disabled facilities, and that access to this building and the provision of
sanitary facilities may need to comply with the requirements of Section D Part D3 and Section
F Clause F2.4 of the Building Code of Australia.
4. Fencing to the future swimming pool must comply with the Queensland Building Act 1975 Part
3 (as amended) and Part 5 of Standard Building Regulation 1993 in all respects. Direct access
from the dwelling to the pool enclosure is not permitted.
5. The development should be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting, air-borne hazards, atmospheric pollutants (including dust or odours) nuisance or any
other emissions in accordance with the nuisance provisions of the Environmental Protection
Regulation 1998 or Council’s Local Law No. 12 – Control of Nuisances.
Page 9 of 13
Page 10
2004/5743
6. In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud, paint,
cement, concrete, builder’s waste or rubbish should not be permitted to enter or be placed
where it could reasonably be expected to move into a roadside gutter, storm water drain or a
watercourse. On the spot fines apply for such offences.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act
can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural
heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.
8 PROPERTY NOTES
Not applicable
9 PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable
10 FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
Development Permit for Building Works All Building Works
Development Permit for Operational Landscaping, Access and/or Carparking, Site Civil
Works Works, Stormwater Drainage, Frontage Works and
Erosion & Sediment Control
11 SELF ASSESSABLE CODES
Not applicable
12 SUBMISSIONS
There were three (3) properly made submissions about the application.
13 REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable
14 RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Integrated Planning Act 1997 is attached.
15 OTHER DETAILS
Should you wish to obtain more information about Council’s decision electronic copies are available
on line at www.sunshinecoast.qld.gov.au, or at Council Offices.
Page 10 of 13
Page 11
2004/5743
DECISION NOTICE HISTORY
Original Decision Notice issued 29 November
2006
Compiled Decision Notice issued 5
September 2007 with amendment to
Conditions 1, 4.1, 7, 8, 11, 22, 24, 26 & 27,
deletion of Condition 2 and inclusion of an
additional condition.
Change to an Existing Approval issued 11
December 2008 with amendment to Condition
1 and inclusion of an additional condition.
Yours faithfully,
Kerri Coyle
MANAGER – LAND USE
Page 11 of 13
Page 12
2004/5743
Appeal Rights
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION
The following is an extract from the Integrated (6) If an application involves assessment against a
Planning Act (Chapter 4). concurrence agency code, appeal rights for submitters
for the application are not available against the part of
Division 8 - Appeals to court relating to the approval that represents the concurrence agency’s
development applications response for the code.
Appeals by applicants Appeals by advice agency submitters
4.1.27.(1) An applicant for a development application 4.1.29.(1) An advice agency may, within the limits of its
may appeal to the court against any of the following- jurisdiction, appeal to the court about the giving of a
(a) the refusal, or the refusal in part, of a development development approval for a development application if-
application; (a) the development application involves impact
(b) a matter stated in a development approval, including assessment; and
any condition applying to the development, and the (b) the advice agency told the applicant and the
identification of a code under section 3.1.6;1 assessment manager to treat its response to the
(c) the decision to give a preliminary approval when a application as a submission for an appeal.
development permit was applied for; (2) The appeal must be started within 20 business
(d) the length of a relevant period; days after the day the decision notice or negotiated
decision notice is given to the advice agency as a
(e) a deemed refusal. submitter.
(2) An appeal under subsection (1)(a) to (d) must be Appeals for matters arising after approval given
started within 20 business days (the “applicant’s appeal
(co-respondents)
period”) after the day the decision notice or negotiated
decision notice is given to the applicant. 4.1.30.(1) For a development approval given for a
development application, a person to whom any of the
(3) An appeal under subsection (1)(e) may be started
following notices have been given may appeal to the
at any time after the last day a decision on the matter
court against the decision in the notice-
should have been made.
(a) a notice giving a decision on a request for extension
Appeals by submitters
of the relevanrt period for an approval;
4.1.28.(1) A submitter for a development application may
(b) a notice giving a decision on a request to make a
appeal to the court about-
minor change to an approval.
(a) the giving of a development approval, including any
(2) The appeal must be started within 20 business
conditions (or lack of conditions) or other provisions
days after the day the notice of the decision is given to
of the approval; or
the person.
(b) the length of a relevant period for the approval.
(3) Subsection (1)(a) does not apply if the approval
(2) The appeal must be started within 20 business resulted from a development application (superseded
days (the “submitters appeal period”) after the day the planning scheme) that was assessed as if it were an
decision notice or negotiated decision notice is given to application under a superseded planning scheme.
the submitter.
(4) Also, a person who has made a request
(3) If a person withdraws a submission before the mentioned in subsection (1) may appeal to the court
application is decided, the person may not appeal the against a deemed refusal of the request.
decision.
(5) An appeal under subsection (4) may be started at
(4) If an application involves both impact assessment any time after the last day the decision on the matter
and code assessment, appeal rights for submitters are should have been made.
available only for the part of the application involving
impact assessment. Division 9 - Appeals to court about other matters
(5) If an application is processed under section Appeals for matters arising after approval given
6.1.28(2), appeal rights for submitters for the application (no co-respondents)
are available only for the aspects of the development that 4.1.31.(1) A person to whom any of the following notices
would have required public notification under the have been given may appeal to the court against the
repealed Act. decision in the notice-
(a) a notice giving a decision on a request to change or
cancel a condition of a development approval.
1
Section 3.1.6 (Preliminary approval may override local
planning instrument)
Page 12 of 13
Page 13
2004/5743
(b) a notice under section 6.1.442 giving a decision to (c) the decision to give a preliminary approval when a
change or cancel a condition of a development development permit was applied for;
approval. (d) the length of a period mentioned in section 3.5.21
(2) The appeal must be started within 20 business relevant period;
days after the day the notice of the decision is (e) a deemed refusal.
given to the person.
(2) An appeal under subsection (1)(a) to (d) must be
(3) Also, a person who has made a request started within 20 business days (the “applicant’s appeal
mentioned in subsection (1)(a) may appeal to the period”) after the day the decision notice or negotiated
court against a deemed refusal of the request. decision notice is given to the applicant.
(4) An appeal under subsection (3) may be started at (3) An appeal under subsection (1)(e) may be started
any time after the last day the decision on the at any time after the last day a decision on the matter
matter should have been made. should have been made.
Appeals against decisions to change approval conditions The Registrar for the Building and Development
under the repealed Act Tribunal may be contacted at the website
4.1.33A.(1) A person who is dissatisfied with a decision http://www.localgovernment.qld.gov.au/
made on an application to change the conditions
attached to an approval given under section 2.19(3)or For Infrastructure Charges Only
section 4.4 of the repealed Act may appeal to the court 4.1.36 Appeals about particular infrastructure
against- charges
(a) the decision; or (1) This section applies to a person who has been
(b) a deemed refusal of the application. given, and is dissatisfied with, an infrastructure charges
notice or a regulated State infrastructure charges notice.
(2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of (2) The person may appeal to the court against the
the decision is to be given to the person. notice.
(3) An appeal under subsection (1)(b) may be started (3) The appeal must be started within 20 business days
at any time after the last day a decision on the matter after-
should have been made. (a) if the notice is given because of a development
Appeals against local laws approval or master plan approval-the day the
applicant is given notice of the decision about the
4.1.33B.(1) An applicant who is dissatisfied with a
approval; or
decision of a local government or the conditions applied
under a local law about the use of premises or the (b) otherwise-the day the notice is given to the person.
erection of a building or other structure permitted by the (4) An appeal under this section may only be about-
planning scheme may appeal to the court against the
(a) whether a charge in the notice is so unreasonable
decision or the conditions applied. that no reasonable relevant local government, State
(2) The appeal must be started within 20 business infrastructure provider or coordinating agency could
days after the day notice of the decision is given to the have imposed it; or
applicant.
(b) an error in the calculation of the charge.
For Building Works Only (5) To remove any doubt, it is declared that an appeal
Rights of appeal conferred by Section 4.2.9 of the under this section can not be about the methodology
Integrated Planning Act 1997 as follows: used to establish the charge in the relevant infrastructure
Division 3 – Appeals to tribunals relating to charges schedule or regulated State infrastructure
development applications charges schedule.
Appeals by applicants
4.2.9(1) An applicant for a development application may
appeal to the Building and Development Tribunal against
any of the following-
(a) the refusal, or the refusal in part, of a development
application;
(b) a matter stated in a development approval, including
any condition applying to the development, and the
identification of a code under section 3.1.6;3
2
Section 6.1.44 (Conditions may be changed or
cancelled by assessment manager or concurrence
agency in certain circumstances)
3
Section 3.1.6 (Preliminary approval may override local
planning instrument)
Page 13 of 13
Used in these records
Decision Notice - Change to an Existing Approval - 010.2004.00005743.003 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 76 KB (small file)
- File type
No other editions are linked here.