                                                                                        2004/5743

      The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street
      drainage system at any one location is 25 litres/second.
34.   Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank
      (minimum storage 3000 litres per dwelling/unit) that is installed to ensure water from the tank
      can be used for external uses (such as watering gardens, irrigation, ornamental ponds, water
      features, topping-up swimming pools, outdoor cleaning, etc) and for use in flushing of toilets
      internal to the dwelling/unit.    All rainwater tanks are to be designed and installed in
      accordance with the Queensland Development Code (QDC), Part 25 – Rainwater Tanks, and
      shall be part of the plumbing application in conjunction with the building approval. The
      location and capacity of the tanks shall be clearly shown on the plans submitted for Building
      Works approval and any overflow shall be directed to the stormwater drainage system.
35.   To ensure that polluted run-off does not enter Council’s stormwater drainage system,
      stormwater run-off from the carparking areas and the driveways shall have the first flush (the
      first 12 mm of rainfall or hose-down) collected in a grease/oil arrestor provided on site prior to
      being permitted to discharge into Council’s drainage system.
      All other clean stormwater, such as roof water, can be collected on site and discharged
      through a single underground drain line directly into the existing drainage system, bypassing
      the grease/oil arrestor.
      To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil
      arrestors, which shall be submitted to the Council for approval prior to obtaining a
      Development Permit for Operational Works.
      The approved maintenance plan shall be incorporated in the Community Management
      Scheme for the development and a copy of this shall be provided for Council’s records prior to
      commencement of the approved Use.
      A Development Permit for Building Works shall not be granted until a Development Permit for
      Operational Works has been issued in regard to the drainage scheme.
36.   All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
37.   The site shall be connected to Council’s existing sewerage reticulation systems and be
      constructed in accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply
38.   The site shall be connected to Council’s existing town water supply and be constructed in
      accordance with Council’s standards and requirements at no cost to Council.
39.   Each individual water connection to the water reticulation system shall extend to the property
      boundary and be metered. All fees for the supply of water meters shall be paid to the Council.
40.   For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the development
      shall either be served by:
      40.1 a single Body Corporate water meter to measure the combined/shared Body Corporate
           and individual Use flows (including fire hose reels, but excluding fire hydrants and fire
           sprinkler systems), or
      40.2 multiple water meters to separately measure Body Corporate (if any) and individual Use
           flows (including fire hose reels, but excluding fire hydrants and fire sprinkler systems).
41.   All water meters must be located outside the property boundary and in an easily assessable
      location to facilitate unhindered reading by Council and/or Council’s contracted water meter
      readers, and not behind fences or locked gates. In this regard approval of the water meter
      configuration and location must be obtained from Council’s Water & Sewerage Capital Works
      Manager prior to lodgement and approval of hydraulic drawings.
                                                                                      Page 5 of 13

Used in these records

About this file

File size
76 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Change to an Existing Approval - 010.2004.00005743.003 [As Published].pdf · 76 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.