Council Reference: 32003.221172.8 & OPW17/0225
Our Reference:     02353 L02 NG



30th May 2018


Chief Executive Officer
Noosa Council
Po Box 141
TEWANTIN QLD 4565


Attention: Development Assessment

Confidential Email Transmission: [email protected]
Original in Post: No


Dear Sir/Madam

RE:     EXTENSION APPLICATION                               ______________________________
Application for an Extension of the Currency period for Development Approval 32003.221172.8
for a Multiple Dwelling Type 2 Duplex, and Operational Works OPW17/0225 for Roadworks,
Stormwater Drainage, Earthworks & Landscaping) for Premises located at 61 Elanda Street,
Sunshine Beach and described as Lot 408 on RP48112

Martoo Consulting has been engaged by Wade Jenner being the owner of the above site, to request
an extension to the currency period for the above development approvals. The applicant seeks to
extend the relevant period by an additional 2 years.

A number of development approvals have been granted over the site as detailed in the table below:

 Approval             Date and Comments
 23657DA              14/10/2004 – Preliminary Approval for Duplex
 23657DA              16/12/2004 – Development Permit for Duplex
 132003.221172.2      09/12/2008 – Extension to relevant period until 16/12/2010
 132003.221172.3      09/08/2010 – Extension to relevant period until 16/12/2012
 132003.221172.4      25/07/2010 – Extension to relevant period until 16/12/2014
 132003.221172.5      17/10/2014 – Extension to relevant period until 16/12/2018
 132003.221172.6      16/02/2015 – Changes to conditions 2 (plans), 6 (landscaping), 11 (height), 21 & 22
                      (carparking). Delete 14 & 23.
 132003.221172.7      06/07/2017 – Change condition 2 (plans)
 OPW17/0225           05/09/2017 - Development Permit for Operational Work (Roadworks, Stormwater
                      Drainage, Earthworks & Landscaping)
 132003.221172.7      3.05.2018 – Change to MCU conditions to provide new architectural plans.
 OPW17/0225           Amended Operational works submitted by not approved due to inconsistencies with
                      MCU approval

The site was recently sold with the new owner submitting the application to change the approved
plans. The new owner is committed to commencing construction on the duplex as soon as the relevant
approvals have been issued however has noted that the currency period for the approval finishes on
16th December 2018. The owner indicates that the development will take approximately 12 to 18
months to build and therefore requests an extension of 2 years for the Material Change of Use and
Operational works approvals.

In support of the extension of currency the owner notes:

         •   The Noosa Plan includes the site in the Attached Housing zone which supports the
             development of a duplex dwellings across the sites;
Full text of the other 1 page

Page 2

         Page 2

          •   The current approval was assessed under the 2006 Noosa Plan which is still relevant over
              the site and local area;

          •   The approved Duplex plans have recently been approved by Council under a minor
              change application issued May 2018;


STATUTORY REQUIREMENTS:

In accordance with Section 87 of the Planning Act 2016, in assessing an extension application, the
assessment manager may:

        87(1) When assessing an extension application, the assessment manager may consider any
        matter that the assessment manager considers relevant, even if the matter was not relevant to
        assessing the development application.

ASSESSMENT:

The current development approval was assessed under the current Noosa Plan and is therefore
consistent with the current laws and policies. There are no new referral agencies and the conditions
are still appropriate. The proposed extension is considered to meet the criteria of the Act and the
applicant requests for an extension of the currency period as detailed below:

    •    132003.221172.8: approval lapses 16th December 2018. A further 2 years until 16th December
         2020 is requested.
    •    OPW17/00225: A further 2 years until 16th December 2020 to be consistent with the MCU
         approval.

This development application has been prepared in accordance with the Planning Act 2009 and is
being submitted with the following attached completed Council form. Councils application fees will be
paid upon receipt of Council file reference and fee link.


Please contact me if you require any further information and/or clarification.

Yours sincerely,




Nadine Gorton
Senior Planner
martoo consulting pty. ltd.

Used in these records

About this file

File size
380 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Martoo Consulting letter of support.pdf · 380 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.