SUPERSEDED Decision Notice OPW25 0042 · OPW25/0042
d. The data must be in accordance with Council’s “Planning Scheme Policy 6 –
Engineering Design Standards”, and fully detail the levels for all engineering works
including but not limited to the drainage network and structures, finished ground and
pavement surface levels.
On Maintenance
48. All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
Council’s relevant Planning Scheme Policy prior to plan sealing. To achieve ‘On
Maintenance’, the supervising RPEQ must submit to Council:
a. certification that all works have been undertaken and completed in accordance with the
requirements of this Permit;
b. as Constructed details in accordance with Council’s Planning Scheme Policy; and
c. maintenance and operational manuals for all proprietary or site specific devices.
Off Maintenance
49. Prior to requesting an Off Maintenance inspection, the developer must provide a written
request for the Off Maintenance inspection.
50. A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
where:
a. a Council inspection reveals works do not comply with approval requirements; or
b. submitted certification falsely states works comply with approval requirements.
51. A final inspection and approval of the completed reinstatement works by Council’s Inspector
is required. Please contact Council on 5329 6500 to arrange for the inspection.
5. REFERENCE DOCUMENTS
Plan No. Rev. Plan/Document Name Date
BBNE01676- 1 Overland Flow Assessment 9 June 2025
0001-REP-001
Prepared by Engeny
22BRT0122 N.A. Traffic Impact Assessment (TIA) Prepared by N.A.
Colliers
N.A. N.A. Traffic Guidance Scheme Prepared by AVADA N.A.
Traffic
25040286 0 Traffic Management Plan Prepared by AVADA 28/04/2025
Traffic
6. REFERRAL AGENCIES
Not applicable.
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
General Advisory Notes
1. As this driveway is a private structure, the owner bears full responsibly for the standard of its
construction, maintenance and any liabilities associated with its construction. It is
recommended that professional advice be sought for the construction of the driveway to
ensure that the driveway is constructed in accordance with standard drawings RS-051.
Page 11 of 15
Document Set ID: 24023937
Version: 2, Version Date: 12/08/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice OPW25 0042.pdfRelated documentApplication case desk ↗
About this file
- File size
- 192 KB (small file)
- File type
No other editions are linked here.